EXCAVATION (ROADWAY)
|
CY
|
5,363.000
|
$15.000
|
$14.250
|
$10.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY A)
|
CY
|
1,612.000
|
$26.000
|
$8.400
|
$20.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
2,780.000
|
$23.000
|
$10.750
|
$16.000
|
|
|
CELL FBR MLCH SEED(PERM)(URBAN)(CLAY)
|
SY
|
35,876.000
|
$0.300
|
$0.290
|
$0.340
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
17,938.000
|
$0.330
|
$0.270
|
$0.450
|
|
|
CELL FBR MLCH SEED(TEMP)(COOL)
|
SY
|
17,938.000
|
$0.330
|
$0.270
|
$0.450
|
|
|
VEGETATIVE WATERING
|
MG
|
304.000
|
$26.000
|
$9.400
|
$15.000
|
|
|
FL BS(RDWY DEL)(TY D GR 1-2)(FNAL POS)
|
CY
|
3,816.000
|
$74.000
|
$74.000
|
$95.000
|
|
|
CEMENT
|
TON
|
605.000
|
$200.000
|
$195.000
|
$220.000
|
|
|
CEMENT TRT (MX EXST MTL & NW BS)(10")
|
SY
|
30,186.000
|
$3.000
|
$1.900
|
$3.800
|
|
|
PRIME COAT (AE-P)
|
GAL
|
6,041.000
|
$3.370
|
$3.100
|
$3.250
|
|
|
ASPH (AC-20-5TR)
|
GAL
|
10,871.000
|
$3.500
|
$2.600
|
$3.250
|
|
|
AGGR(TY-PD GR-4 OR TY-PL GR-4)
|
CY
|
235.000
|
$200.000
|
$190.000
|
$185.000
|
|
|
SUPERPAVE MIXTURES SP-C PG64-22
|
TON
|
3,324.000
|
$90.000
|
$76.000
|
$94.000
|
|
|
CEM STABIL BKFL
|
CY
|
11.000
|
$125.000
|
$90.000
|
$58.000
|
|
|
CUT AND RESTORE PAV (FLEX BASE)
|
SY
|
204.000
|
$40.000
|
$38.000
|
$11.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
65.000
|
$300.000
|
$460.000
|
$625.000
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
885.000
|
$180.000
|
$205.000
|
$195.000
|
|
|
CONC BOX CULV (4 FT X 3 FT)
|
LF
|
242.000
|
$180.000
|
$230.000
|
$235.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
637.000
|
$50.000
|
$54.000
|
$63.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
413.000
|
$65.000
|
$63.000
|
$72.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
43.000
|
$116.000
|
$112.000
|
$86.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
24.000
|
$300.000
|
$255.000
|
$156.000
|
|
|
INLET (COMPL)(PSL)(FG)(3FTX5FT-3FTX5FT)
|
EA
|
8.000
|
$5,000.000
|
$2,950.000
|
$2,500.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 48 IN)
|
EA
|
1.000
|
$12,000.000
|
$10,200.000
|
$20,000.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (P)
|
EA
|
1.000
|
$7,500.000
|
$6,400.000
|
$3,950.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (P)
|
EA
|
1.000
|
$8,000.000
|
$7,800.000
|
$2,600.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
40.000
|
$800.000
|
$760.000
|
$660.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
46.000
|
$1,000.000
|
$1,040.000
|
$1,025.000
|
|
|
SET (TY II) (48 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$3,000.000
|
$4,020.000
|
$3,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,298.000
|
$20.000
|
$12.300
|
$10.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$100,000.000
|
$71,000.000
|
$45,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$5,000.000
|
$1,500.000
|
$4,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
211.000
|
$27.000
|
$30.000
|
$29.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
20.000
|
$60.000
|
$49.000
|
$55.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
231.000
|
$9.600
|
$8.200
|
$8.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
200.000
|
$5.000
|
$5.100
|
$19.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
200.000
|
$1.300
|
$1.000
|
$5.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
126.000
|
$110.000
|
$170.000
|
$136.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
444.000
|
$45.000
|
$63.000
|
$39.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
682.000
|
$30.000
|
$18.000
|
$23.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
850.000
|
$20.000
|
$19.250
|
$20.500
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,665.000
|
$1,750.000
|
$2,110.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
EA
|
1.000
|
$30.000
|
$100.000
|
$1,110.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
389.000
|
$3.600
|
$2.500
|
$5.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
10.000
|
$2,150.000
|
$2,100.000
|
$2,560.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
8.000
|
$350.000
|
$280.000
|
$335.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
19.000
|
$240.000
|
$415.000
|
$170.000
|
|
|
MAILBOX INSTALL-D (TWW-POST) TY 4
|
EA
|
5.000
|
$220.000
|
$300.000
|
$235.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
2.000
|
$485.000
|
$540.000
|
$190.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
13.000
|
$365.000
|
$360.000
|
$400.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)SRF
|
EA
|
90.000
|
$110.000
|
$68.000
|
$100.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
21.000
|
$15.200
|
$27.500
|
$50.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
80.000
|
$1.660
|
$1.600
|
$1.400
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
1,533.000
|
$1.500
|
$1.600
|
$1.400
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
800.000
|
$0.650
|
$0.700
|
$1.400
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
12,277.000
|
$0.310
|
$0.350
|
$0.470
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
2,920.000
|
$0.310
|
$0.350
|
$0.470
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
13,140.000
|
$0.310
|
$0.350
|
$0.470
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
82.000
|
$11.200
|
$15.400
|
$19.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
4.000
|
$149.000
|
$205.000
|
$260.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
40.000
|
$3.050
|
$4.100
|
$5.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
77.000
|
$3.050
|
$4.100
|
$6.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
728.000
|
$0.360
|
$0.650
|
$0.400
|
|
|
TMA (STATIONARY)
|
DAY
|
180.000
|
$180.000
|
$125.000
|
$87.000
|
|
Totals: |
$1,914,138.850
|
$1,709,304.360
|
$1,928,518.130
|