CHAMBERS IH 10 (0508-02-129)

Items: 33

County: CHAMBERS
Length: N/A
Highway: IH 10
District: BEAUMONT
Control Number: 0508-02-129
DBE Goal: 0.0%
Project: C 508-2-129
Guaranty: N/A
Time: 44 WORKING DAYS
Engineer's Estimate: $2,629,217.87
Date: 01/04/2024 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
ROBERTO M RODRIGUEZ
NYEMB NYEMB
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$2,629,217.87
Over/Under Est: -7.81% -$205,328.17
Over/Under Est: -6.43% -$169,153.25
Amt Left: 1.49% $36,174.92
Over/Under Est: -5.03% -$132,327.47
Amt Left: 3.01% $73,000.70
Delta: -1.50% -$36,825.78
Subcontractor Percentage Amount
BATTERSON, LLP 3.36% $78,460.69
KINGZ INDUSTRIAL LLC 1.81% $42,266.02
HAZMAT INTERNATIONAL, INC. 1.19% $27,788.16
SOUTHWEST ENVIRONMENT SERVICES LLC 0.26% $6,071.36
STRIPE LINES, INC. 0.26% $6,071.36
Total: 6.88% $160,657.59

Bid Items & Bid Tabulations

33 Total 0 of 33
CHAMBERS  |  IH 10  |  BEAUMONT  |  0508-02-129  |  01/04/2024  |  $2,629,217.87  |  C 508-2-129  |  REHAB EXIST ROADWAY  |  44 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
BACKFILL (TY A OR B)
STA 587.000 $275.000 $125.000 $182.220 $310.000
CELL FBR MLCH SEED(PERM)(URBAN)(SANDY)
SY 13,038.000 $0.440 $0.750 $0.770 $0.500
VEGETATIVE WATERING
MG 23.000 $80.000 $100.000 $395.980 $210.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 1,265.000 $147.000 $90.000 $81.420 $113.000
PLANE CONC PAV(0" TO 2")
SY 45,800.000 $11.220 $2.250 $4.280 $0.100
RIPRAP (MOW STRIP)(4 IN)
CY 11.000 $800.000 $1,500.000 $512.040 $1,200.000
MOBILIZATION
LS 1.000 $237,947.910 $240,000.000 $193,014.490 $73,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,883.000 $4,000.000 $1,253.460 $1,200.000
PERM CTB (F-SHAPE) (TY 1)
LF 240.000 $21.150 $210.000 $133.130 $145.000
INTRSCT, DRVWAYS, & TURNOUT (ACP)
SY 224.000 $70.000 $40.000 $183.900 $170.000
DRIVEWAYS (BASE)
SY 243.000 $57.700 $60.000 $94.050 $70.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,165.000 $2,000.000 $3,055.520 $2,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 43.000 $623.000 $505.000 $584.540 $750.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 6,980.000 $0.700 $0.400 $0.420 $0.400
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 33,434.000 $0.610 $0.400 $0.390 $0.300
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 31,132.000 $0.330 $0.400 $0.390 $0.350
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,069.000 $1.760 $1.000 $1.300 $0.700
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 427.000 $1.120 $1.000 $1.380 $2.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 48.000 $9.400 $6.000 $9.730 $8.000
REFL PAV MRK TY I (Y)24"(SLD)(090MIL)
LF 782.000 $7.880 $6.000 $6.910 $8.000
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 6,980.000 $0.740 $0.550 $0.830 $0.700
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 33,434.000 $0.580 $0.550 $0.670 $0.600
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 31,132.000 $0.710 $0.550 $0.670 $0.650
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $278.000 $250.000 $260.110 $275.000
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 8.000 $26.000 $38.000 $25.600 $75.000
REFL PAV MRKR TY II-A-A
EA 334.000 $6.800 $5.750 $5.100 $5.000
REFL PAV MRKR TY II-C-R
EA 344.000 $4.760 $5.750 $5.100 $5.000
PAV SURF PREP FOR MRK (6")
LF 3,300.000 $1.000 $0.100 $0.100 $0.050
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 9,067.000 $140.000 $180.000 $171.390 $200.000
TACK COAT
GAL 4,731.000 $6.000 $4.000 $7.230 $3.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $7,000.000 $4,017.680 $6,700.000
TMA (STATIONARY)
DAY 40.000 $400.000 $180.000 $414.110 $250.000
TMA (MOBILE OPERATION)
DAY 4.000 $351.380 $180.000 $414.110 $650.000
Totals: $2,629,217.870 $2,423,889.700 $2,460,064.620 $2,496,890.400