Bid Cobra

CASS FM 994 (1216-01-010)

Items: 38

County: CASS
Length: 3.1260 MILES
Highway: FM 994
District: ATLANTA
Control Number: 1216-01-010
DBE Goal: 0.0%
Project: C 1216-1-10
Guaranty: $45,000.00
Time: 102 WORKING DAYS
Engineer's Estimate: $2,240,718.50
Date: 12/04/2024 (1 year ago)
Contract Number: 12243214
Type: WIDEN ROAD - ADD SHOULDERS
Project ID: A00196488
Project Description: WIDEN EXISTING 2-LANE ROADWAY TO ADD SHOULDERS
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$2,240,718.50
$1,327,253.73
Over/Under Est: -40.77% -$913,464.77
Over/Under Est: -31.4% -$703,584.30
Amt Left: 15.81% $209,880.47
Over/Under Est: -14.13% -$316,655.39
Amt Left: 44.97% $596,809.38
Delta: -25.17% -$386,928.91
Over/Under Est: 1.24% $27,776.10
Amt Left: 70.92% $941,240.87
Delta: -17.90% -$344,431.49
$2,605,227.50
Over/Under Est: 16.27% $364,509.00
Amt Left: 96.29% $1,277,973.77
Delta: -14.84% -$336,732.90
Over/Under Est: 19.04% $426,540.86
Amt Left: 100.96% $1,340,005.63
Delta: -2.38% -$62,031.86

Bid Items & Bid Tabulations

38 Total 0 of 38
CASS  |  FM 994  |  ATLANTA  |  1216-01-010  |  12/04/2024  |  $2,240,718.50  |  C 1216-1-10  |  WIDEN ROAD - ADD SHOULDERS  |  102 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
H. V. CAVER, INC.
H. H. HOWARD & SONS, INC.
A. K. GILLIS & SONS, LLC
EAST TEXAS BRIDGE, INC.
FNH CONSTRUCTION, LLC
L. S. EQUIPMENT CO., INC.
PREPARING ROW
STA 124.000 $4,000.000 $1,900.000 $2,000.000 $1,945.000 $4,000.000 $2,500.000 $4,500.000
SUBGR WIDEN (OC)
STA 158.730 $650.000 $500.000 $500.000 $496.700 $650.000 $2,500.000 $1,600.000
EMBANK (VEH)(OC)(TY C)
CY 142.000 $60.000 $50.000 $50.000 $100.000 $60.000 $50.000 $50.000
BACKFILL (TY B)
STA 158.730 $350.000 $200.000 $300.000 $300.000 $400.000 $450.000 $225.000
BROADCAST SEED (TEMP_WARM_COOL)
SY 27,558.000 $0.250 $0.120 $0.150 $0.150 $0.150 $1.000 $0.300
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 55,774.000 $1.000 $0.520 $0.500 $0.550 $0.600 $1.000 $1.100
VEGETATIVE WATERING
TGL 551.000 $50.000 $0.010 $2.000 $2.000 $25.000 $50.000 $0.010
FL BS (CMP IN PLC)(TY A GR 1-2) (10")
SY 8,818.000 $65.000 $46.570 $45.000 $77.060 $65.000 $60.000 $65.000
PRIME COAT (MC-30)
GAL 2,999.000 $12.000 $5.000 $8.000 $6.430 $8.000 $10.000 $6.000
ASPH (AC-20-5TR)
GAL 19,170.000 $5.000 $5.000 $7.000 $6.550 $6.500 $10.000 $6.000
AGGR (TY-PB, GR-4)(SAC-A)
CY 407.000 $250.000 $168.000 $275.000 $235.720 $285.000 $500.000 $338.500
RIPRAP (CONC)(4 IN)
CY 36.000 $800.000 $525.000 $800.000 $650.000 $1,300.000 $550.000 $1,200.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.000 $700.000 $500.000 $800.000 $650.000 $1,000.000 $550.000 $1,200.000
MOBILIZATION
LS 1.000 $272,000.000 $73,000.000 $75,000.000 $241,425.000 $250,000.000 $300,000.000 $275,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,000.000 $3,000.000 $4,000.000 $9,625.000 $15,000.000 $15,000.000 $25,000.000
TMA (STATIONARY)
DAY 65.000 $350.000 $200.000 $500.000 $200.000 $300.000 $250.000 $300.000
TMA (MOBILE OPERATION)
DAY 15.000 $400.000 $250.000 $500.000 $250.000 $500.000 $550.000 $300.000
TURNOUTS (SURF TREAT)
SY 199.000 $55.000 $125.000 $100.000 $162.470 $65.000 $100.000 $125.000
MTL W-BEAM GD FEN (TIM POST)
LF 425.000 $30.000 $21.000 $25.000 $21.000 $26.000 $30.000 $35.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $880.000 $675.000 $850.000 $675.000 $950.000 $1,850.000 $1,300.000
MTL W-BEAM GD FEN (SPECIAL)
LF 37.500 $190.000 $48.000 $45.000 $48.000 $50.000 $200.000 $65.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 125.000 $90.000 $85.000 $100.000 $85.000 $100.000 $100.000 $145.000
REMOVE METAL BEAM GUARD FENCE
LF 525.000 $5.000 $2.000 $2.000 $2.000 $2.500 $3.000 $7.500
REMOVE TERMINAL ANCHOR SECTION
EA 8.000 $300.000 $300.000 $200.000 $300.000 $250.000 $500.000 $325.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,250.000 $2,725.000 $3,000.000 $2,725.000 $3,200.000 $3,850.000 $3,200.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 9.000 $300.000 $227.500 $500.000 $321.000 $400.000 $1,100.000 $500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 46.000 $800.000 $688.730 $720.000 $680.000 $750.000 $1,100.000 $800.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 6.000 $1,050.000 $992.060 $950.000 $1,010.000 $1,100.000 $1,100.000 $1,200.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 6.000 $600.000 $504.580 $600.000 $435.000 $500.000 $1,100.000 $625.000
REMOVE SM RD SN SUP&AM
EA 58.000 $150.000 $100.000 $150.000 $99.000 $115.000 $200.000 $125.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 14.000 $45.000 $42.950 $20.000 $42.950 $50.000 $100.000 $68.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,652.000 $2.000 $1.000 $4.000 $2.350 $2.000 $6.000 $1.000
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 33,010.000 $1.000 $0.700 $1.000 $0.700 $1.000 $1.500 $1.800
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 24,240.000 $1.000 $0.700 $1.000 $0.700 $1.000 $1.500 $1.800
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 2,200.000 $1.000 $0.740 $1.250 $0.740 $1.150 $1.500 $1.250
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 3,302.000 $6.000 $4.000 $6.000 $4.000 $5.750 $1.000 $7.550
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 6,604.000 $6.000 $4.000 $6.000 $4.000 $5.750 $1.000 $7.550
REFL PAV MRKR TY II-A-A
EA 634.000 $8.000 $4.950 $6.000 $4.950 $5.500 $6.000 $7.500
Totals: $2,240,718.500 $1,327,253.730 $1,537,134.200 $1,924,063.111 $2,268,494.600 $2,605,227.500 $2,667,259.360