CASS VA (0919-00-081)

Items: 15

County: CASS
Length: N/A
Highway: VA
District: ATLANTA
Control Number: 0919-00-081
DBE Goal: N/A
Project: F 2022(293)
Guaranty: N/A
Time: 57 WORKING DAYS
Engineer's Estimate: $1,146,416.40
Date: 01/06/2022 (4 years ago)
Contract Number: N/A
Type: SEAL COAT PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$1,146,416.40
$934,909.00
Over/Under Est: -18.45% -$211,507.40
$996,679.87
Over/Under Est: -13.06% -$149,736.53
Amt Left: 6.61% $61,770.87
Over/Under Est: 4.46% $51,137.44
Amt Left: 28.09% $262,644.84
Delta: -20.15% -$200,873.97
Over/Under Est: 4.76% $54,560.18
Amt Left: 28.46% $266,067.58
Delta: -0.29% -$3,422.74

Bid Items & Bid Tabulations

15 Total 0 of 15
CASS  |  VA  |  ATLANTA  |  0919-00-081  |  01/06/2022  |  $1,146,416.40  |  F 2022(293)  |  SEAL COAT PAVMT MRK  |  57 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPING TECHNOLOGY, L.P.
STRIPE-A-ZONE, LLC
TRP CONSTRUCTION GROUP, LLC
TOTAL HIGHWAY MAINTENANCE, LLC
MOBILIZATION
LS 1.000 $100,000.000 $1.000 $1.000 $42,500.000 $35,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $7,000.000 $1.000 $1.000 $500.000 $2,500.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,981.000 $1.000 $1.000 $1.200 $0.800 $1.000
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
LF 220,368.000 $0.450 $0.520 $0.550 $0.560 $0.480
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 42,939.000 $3.000 $2.900 $2.900 $3.400 $4.100
PREFORMED CENTERLINE RUMBLE STRIP
LF 43,912.000 $3.500 $2.900 $2.900 $3.400 $4.100
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
LF 560,631.000 $0.380 $0.340 $0.390 $0.440 $0.420
REFL PAV MRK AWT (W) 4" (BRK) (100MIL)
LF 13,150.000 $0.450 $0.500 $0.440 $0.480 $0.460
REFL PAV MRK AWT (W) 6" (SLD) (100MIL)
LF 172,012.000 $0.550 $0.450 $0.480 $0.640 $0.540
REFL PAV MRK AWT (W) 6" (BRK) (100MIL)
LF 21,790.000 $0.600 $0.650 $0.510 $0.680 $0.590
REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)
LF 582,564.000 $0.380 $0.350 $0.390 $0.440 $0.430
REFL PAV MRK AWT (Y) 4" (BRK) (100MIL)
LF 23,170.000 $0.400 $0.500 $0.440 $0.480 $0.470
REFL PAV MRK AWT (Y) 6" (SLD) (100MIL)
LF 130,392.000 $0.550 $0.450 $0.480 $0.640 $0.560
REFL PAV MRK AWT (Y) 6" (BRK) (100MIL)
LF 3,830.000 $0.500 $0.650 $0.490 $0.680 $0.610
TMA (MOBILE OPERATION)
DAY 57.000 $50.000 $1.000 $1.000 $10.000 $125.000
Totals: $1,146,416.400 $934,909.000 $996,679.870 $1,197,553.840 $1,200,976.580