CASS SH 49 (0222-04-072)

Items: 77

County: CASS
Length: 5.3510 MILES
Highway: SH 49
District: ATLANTA
Control Number: 0222-04-072
DBE Goal: 0.0%
Project: C 222-4-72
Guaranty: $100,000.00
Time: 406 WORKING DAYS
Engineer's Estimate: $13,278,536.48
Date: 10/08/2025 (8 months ago)
Contract Number: 10253005
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00208073
Project Description: REHABILITATE EXISTING 2-LANE ROADWAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$13,278,536.48
$11,029,939.11
Over/Under Est: -16.93% -$2,248,597.37
$12,666,988.87
Over/Under Est: -4.61% -$611,547.61
Amt Left: 14.84% $1,637,049.76
Over/Under Est: -0.4% -$52,573.09
Amt Left: 19.91% $2,196,024.28
Delta: -4.41% -$558,974.52
$13,467,956.80
Over/Under Est: 1.43% $189,420.32
Amt Left: 22.1% $2,438,017.69
Delta: -1.83% -$241,993.41
Over/Under Est: 4.1% $544,563.71
Amt Left: 25.32% $2,793,161.08
Delta: -2.64% -$355,143.39
Over/Under Est: 4.63% $614,761.82
Amt Left: 25.96% $2,863,359.19
Delta: -0.51% -$70,198.11
$13,996,913.01
Over/Under Est: 5.41% $718,376.53
Amt Left: 26.9% $2,966,973.90
Delta: -0.75% -$103,614.71
Over/Under Est: 14.62% $1,941,151.20
Amt Left: 37.99% $4,189,748.57
Delta: -8.74% -$1,222,774.67
Over/Under Est: 17.7% $2,350,758.42
Amt Left: 41.7% $4,599,355.79
Delta: -2.69% -$409,607.22
Subcontractor Percentage Amount
RK HALL, LLC 48.48% $5,381,576.51
TEXOP CONSTRUCTION 3.24% $359,659.82
STRIPING TECHNOLOGY, L.P. 1.61% $178,719.85
SOUTHWEST ENVIRONMENT SERVICES LLC 0.49% $54,393.00
J. H. ODEN CONTRACTING COMPANY 0.47% $52,172.87
PANOLA SIGN & BARRICADE, INC. 0.27% $29,971.65
MORRIS COUNTY CONTRACTORS, L.L.C. 0.25% $27,751.53
J.C. JOHNSON CONSTRUCTION 0.19% $21,091.16
WEST TEXAS RUMBLE STRIP LLC 0.07% $7,770.43
Total: 55.07% $6,113,106.82

Bid Items & Bid Tabulations

77 Total 0 of 77
CASS  |  SH 49  |  ATLANTA  |  0222-04-072  |  10/08/2025  |  $13,278,536.48  |  C 222-4-72  |  REHAB EXIST ROADWAY  |  406 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
L. S. EQUIPMENT CO., INC.
H. V. CAVER, INC.
D. L. LENNON INCORPORATED - CONTRACTOR
EAST TEXAS BRIDGE, INC.
H. H. HOWARD & SONS, INC.
BAKER & COMPANY CONSTRUCTION, LLC
RK HALL, LLC
PINTO CONSTRUCTION CO., INC.
LONGVIEW BRIDGE AND ROAD, LTD.
PREPARING ROW
STA 269.000 $2,000.000 $1,000.000 $1,450.000 $1,452.110 $1,950.000 $1,400.000 $1,490.000 $1,500.000 $2,452.000 $3,000.000
REMOV CONC (MOWSTRIP)
LF 630.000 $30.000 $21.500 $8.990 $15.000 $10.000 $10.000 $5.950 $16.200 $18.500 $11.000
RMV (6"-10") TRT/UNTRT BASE & ASPH PAV
SY 110,333.000 $8.500 $3.250 $3.830 $6.790 $7.750 $9.200 $4.300 $8.520 $9.600 $7.000
EMBANK (VEH)(OC)(TY C)
CY 100.000 $40.000 $25.000 $50.000 $63.000 $40.000 $40.000 $23.750 $68.040 $35.000 $55.000
BACKFILL (TY B)
STA 287.750 $70.000 $100.000 $300.000 $260.000 $175.000 $500.000 $350.000 $280.800 $300.000 $420.000
BLADING
STA 287.750 $113.000 $100.000 $300.000 $310.000 $125.000 $250.000 $280.000 $334.800 $150.000 $270.000
BROADCAST SEED (TEMP_WARM)
SY 19,670.000 $0.250 $0.170 $0.170 $0.090 $0.100 $0.100 $0.120 $0.100 $0.100 $0.200
BROADCAST SEED (TEMP_COOL)
SY 19,670.000 $0.250 $0.220 $0.220 $0.090 $0.100 $0.100 $0.120 $0.100 $0.100 $0.250
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 78,676.000 $0.500 $0.590 $0.590 $0.530 $0.580 $0.550 $0.800 $0.570 $0.590 $0.900
VEGETATIVE WATERING
TGL 1,888.300 $0.220 $0.010 $0.010 $25.000 $5.000 $5.000 $1.000 $41.540 $0.010 $25.000
FL BS (CMP IN PLC)(TY A GR 4) (8")
SY 103,951.000 $20.000 $20.250 $26.000 $26.800 $27.000 $25.000 $26.000 $24.840 $28.370 $27.000
CEMENT
TON 2,780.000 $257.000 $240.000 $235.000 $275.000 $270.000 $300.000 $275.000 $297.000 $218.390 $280.000
CEMENT TRT (NEW BASE)(8")
SY 103,951.000 $4.000 $2.250 $4.000 $3.600 $2.850 $3.500 $5.650 $4.020 $5.000 $2.500
CEMENT TRT (SUBGRADE) (8")
SY 79,883.000 $3.000 $2.250 $4.030 $3.600 $2.650 $3.500 $6.700 $6.430 $5.000 $2.250
PRIME COAT & BLOTTER (MC-30)
GAL 25,989.000 $6.250 $4.000 $8.040 $7.500 $5.450 $6.000 $7.950 $8.100 $8.800 $7.750
ASPH (AC-20-5TR)
GAL 37,422.000 $4.000 $4.850 $5.910 $5.000 $5.250 $4.750 $8.600 $5.400 $4.650 $5.000
AGGR (TY-PB, GR-4)(SAC-A)
CY 744.000 $165.000 $185.000 $196.580 $212.000 $175.000 $200.000 $267.000 $228.960 $215.950 $225.000
SP MIXES SP-C PG70-22
TON 16,632.000 $165.000 $149.000 $147.000 $151.200 $150.000 $146.200 $157.000 $146.200 $160.820 $170.000
SP MIXES SP-C SAC-A PG76-22
TON 17,772.000 $162.000 $154.000 $153.500 $157.610 $158.000 $152.610 $159.000 $152.610 $167.870 $172.000
TACK COAT
GAL 27,031.000 $3.000 $7.140 $7.350 $7.140 $4.750 $7.140 $9.300 $7.140 $7.850 $5.000
PLANE ASPH CONC PAV(2")
SY 3,222.000 $3.300 $3.250 $2.740 $6.860 $4.500 $5.000 $6.750 $2.290 $6.500 $3.250
PLANE ASPH CONC PAV(3")
SY 7,927.000 $2.250 $3.250 $2.840 $6.790 $4.650 $5.000 $3.450 $2.510 $5.870 $4.000
PLANE ASPH CONC PAV(4")
SY 96,818.000 $3.000 $2.500 $1.690 $5.450 $3.150 $5.700 $3.400 $3.000 $3.500 $5.250
CUT & RESTORE ASPH PAVING
SY 33.000 $152.000 $279.000 $350.000 $100.000 $100.000 $150.000 $330.000 $194.640 $286.000 $300.000
RIPRAP (MOW STRIP)(4 IN)
CY 34.000 $641.000 $900.000 $433.890 $825.000 $700.000 $700.000 $891.000 $891.000 $990.000 $550.000
RC PIPE (CL III)(18 IN)
LF 144.000 $58.000 $55.000 $52.570 $60.000 $65.000 $80.000 $61.500 $64.800 $77.000 $75.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 8.000 $800.000 $900.000 $770.000 $1,000.000 $1,000.000 $900.000 $1,068.000 $1,080.000 $1,100.000 $1,200.000
REMOV STR (SET)
EA 2.000 $615.000 $250.000 $550.000 $250.000 $250.000 $100.000 $990.000 $270.000 $550.000 $1,100.000
REMOV STR (PIPE)
LF 120.000 $21.000 $10.000 $20.000 $20.000 $10.000 $10.000 $16.500 $21.600 $18.700 $40.000
MOBILIZATION
LS 1.000 $1,220,000.000 $500,000.000 $775,000.000 $298,275.000 $940,000.000 $1,000,000.000 $550,000.000 $888,632.290 $1,370,300.000 $1,500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $6,000.000 $3,000.000 $7,072.370 $7,056.500 $5,000.000 $3,000.000 $14,800.000 $11,000.000 $2,500.000 $23,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $6,000.000 $1,600.000 $15,000.000 $15,000.000 $18,000.000 $20,000.000 $13,125.000 $19,151.620 $20,000.000 $18,000.000
TMA (STATIONARY)
DAY 365.000 $185.000 $150.000 $200.000 $200.000 $250.000 $200.000 $245.000 $470.930 $250.000 $330.000
TMA (MOBILE OPERATION)
DAY 20.000 $260.000 $150.000 $225.000 $200.000 $300.000 $500.000 $1,510.000 $107.280 $50.000 $550.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 128.000 $47.000 $46.000 $46.000 $38.000 $42.000 $40.000 $29.000 $41.040 $41.800 $50.000
ROCK FILTER DAMS (REMOVE)
LF 128.000 $14.000 $16.000 $16.000 $9.000 $10.000 $10.000 $3.000 $9.720 $9.900 $18.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 264.000 $4.000 $5.000 $5.000 $4.000 $4.500 $4.000 $5.250 $4.320 $4.400 $5.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 264.000 $1.000 $1.000 $1.000 $0.690 $0.750 $1.000 $1.050 $0.750 $0.760 $1.100
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 54,951.000 $0.300 $0.280 $0.160 $1.070 $0.300 $0.250 $0.300 $0.160 $0.350 $0.200
MTL W-BEAM GD FEN (TIM POST)
LF 400.000 $24.500 $25.500 $20.000 $20.000 $22.000 $25.000 $21.000 $21.600 $27.500 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $3,000.000 $1,650.000 $2,095.000 $1,825.000 $1,700.000 $1,575.000 $1,600.000 $1,647.000 $2,600.000 $1,750.000
REMOVE METAL BEAM GUARD FENCE
LF 350.000 $3.450 $4.000 $3.000 $3.000 $3.300 $3.000 $3.150 $3.240 $3.300 $2.200
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $140.000 $157.500 $200.000 $200.000 $220.000 $150.000 $210.000 $571.920 $275.000 $165.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,135.000 $3,050.000 $2,900.000 $2,900.000 $3,200.000 $3,000.000 $3,045.000 $3,132.000 $3,245.000 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $400.000 $212.000 $200.000 $200.000 $220.000 $250.000 $210.000 $216.000 $330.000 $220.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 23.000 $290.000 $307.000 $307.000 $230.000 $340.000 $350.000 $242.000 $331.560 $337.700 $340.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 3.000 $345.000 $343.000 $343.000 $300.000 $380.000 $500.000 $285.000 $370.440 $377.300 $375.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $745.000 $772.000 $772.000 $870.000 $850.000 $800.000 $915.000 $833.760 $849.200 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $730.000 $722.000 $722.000 $755.000 $800.000 $1,000.000 $830.000 $779.760 $794.200 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 8.000 $827.000 $775.000 $775.000 $830.000 $850.000 $900.000 $1,008.000 $837.000 $852.500 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 3.000 $839.000 $1,030.000 $1,030.000 $1,225.000 $1,135.000 $1,500.000 $1,330.000 $1,112.400 $1,133.000 $1,150.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $1,750.000 $907.000 $907.000 $1,030.000 $1,000.000 $1,000.000 $1,055.000 $979.560 $997.700 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 2.000 $950.000 $990.000 $990.000 $1,160.000 $1,100.000 $1,000.000 $1,071.000 $1,069.200 $1,089.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $787.000 $1,060.000 $1,060.000 $1,265.000 $1,175.000 $1,200.000 $1,330.000 $1,144.800 $1,166.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,250.000 $1,074.000 $1,074.000 $1,290.000 $1,185.000 $1,100.000 $1,305.000 $1,159.920 $1,181.400 $1,200.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 30.000 $459.000 $458.000 $458.000 $340.000 $500.000 $500.000 $546.000 $494.640 $503.800 $500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 3.000 $380.000 $532.000 $532.000 $460.000 $585.000 $600.000 $693.000 $574.560 $585.200 $585.000
REMOVE SM RD SN SUP&AM
EA 57.000 $100.000 $101.000 $101.000 $75.000 $100.000 $100.000 $142.000 $109.080 $111.100 $110.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $36.000 $27.000 $31.000 $31.000 $34.000 $30.000 $33.000 $33.480 $55.000 $27.500
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 38.000 $47.000 $126.000 $126.000 $50.000 $135.000 $130.000 $100.000 $136.080 $138.600 $140.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 117,102.000 $0.350 $0.280 $0.230 $0.230 $0.330 $0.320 $0.250 $0.320 $0.250 $0.350
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 117,102.000 $0.350 $0.280 $0.230 $0.230 $0.330 $0.320 $0.250 $0.320 $0.250 $0.350
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 38.000 $0.500 $1.000 $2.000 $2.000 $1.000 $10.000 $3.150 $1.330 $2.500 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,302.000 $2.620 $1.000 $1.750 $2.000 $1.000 $10.000 $3.150 $1.330 $2.500 $1.500
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 59,551.000 $0.580 $0.650 $0.600 $0.600 $1.000 $1.000 $0.650 $0.970 $0.660 $1.000
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 30.000 $0.650 $1.250 $1.000 $1.000 $2.200 $3.000 $1.050 $2.160 $1.100 $2.200
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 40,498.000 $0.630 $0.750 $0.680 $0.680 $1.000 $1.000 $0.700 $0.970 $0.750 $1.000
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 1,970.000 $0.600 $1.300 $1.000 $1.000 $1.350 $1.500 $1.050 $1.350 $1.100 $1.400
ALL-WTHER PM TY I (W) 8"(SLD)(100MIL)
LF 50.000 $11.000 $2.500 $2.000 $2.000 $2.200 $2.000 $2.100 $2.160 $2.200 $2.200
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 5,689.000 $3.000 $6.500 $6.500 $6.500 $5.500 $6.000 $6.850 $5.400 $7.150 $5.500
PREFAB PM TY C (W)(8")(SLD)
LF 50.000 $6.500 $8.000 $8.000 $8.000 $5.500 $5.000 $8.400 $5.400 $8.800 $5.500
PREFAB PM TY C (W)(24")(SLD)
LF 250.000 $16.000 $17.650 $17.650 $17.650 $16.500 $20.000 $18.550 $16.200 $19.420 $16.500
PREFAB PM TY C (W)(ARROW)
EA 1.000 $241.000 $305.000 $300.000 $300.000 $330.000 $300.000 $315.000 $324.000 $330.000 $330.000
PREFAB PM TY C (W)(WORD)
EA 1.000 $321.000 $425.000 $400.000 $400.000 $550.000 $1,000.000 $420.000 $540.000 $440.000 $550.000
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 400.000 $4.000 $7.000 $6.500 $6.500 $13.750 $15.000 $6.850 $13.500 $7.150 $13.750
REFL PAV MRKR TY II-A-A
EA 703.000 $4.150 $5.750 $5.750 $5.750 $5.500 $5.000 $6.050 $5.400 $6.330 $5.500
REFL PAV MRKR TY II-C-C
EA 6.000 $5.000 $5.750 $5.750 $5.750 $5.500 $6.000 $6.050 $5.400 $6.330 $5.500
Totals: $13,278,536.486 $11,029,939.113 $12,666,988.873 $13,225,963.390 $13,467,956.800 $13,823,100.190 $13,893,298.300 $13,996,913.012 $15,219,687.683 $15,629,294.900
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FORCE ACCOUNT WORK (NON-PART) $21,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $67,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $134,000.00
Total: $227,000.00