CARSON FM 2373 (2218-01-035)

Items: 84

County: CARSON
Length: N/A
Highway: FM 2373
District: AMARILLO
Control Number: 2218-01-035
DBE Goal: N/A
Project: BR 1902(241)
Guaranty: N/A
Time: 121 WORKING DAYS
Engineer's Estimate: $4,863,893.50
Date: 10/02/2019 (6 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES, RELOCATE RAMP
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$4,863,893.50
$5,732,295.93
Over/Under Est: 17.85% $868,402.43
$5,959,892.88
Over/Under Est: 22.53% $1,095,999.38
Amt Left: 3.97% $227,596.95

Bid Items & Bid Tabulations

84 Total 0 of 84
CARSON  |  FM 2373  |  AMARILLO  |  2218-01-035  |  10/02/2019  |  $4,863,893.50  |  BR 1902(241)  |  REPLACE BRIDGE AND APPROACHES, RELOC...  |  121 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. LEE MILLIGAN, INC.
GILVIN-TERRILL, LTD.
PREPARING ROW
AC 6.000 $15,000.000 $10,400.000 $25,000.000
REMOVING CONC (MISC)
SY 96.000 $15.000 $80.000 $25.000
REMOVE CONC (MISC)
EA 15.000 $1,000.000 $660.000 $500.000
EXCAVATION (ROADWAY)
CY 2,505.000 $8.000 $55.250 $15.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 39,654.000 $12.000 $25.600 $20.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 42,768.000 $0.250 $0.120 $0.250
DRILL SEED (TEMP)(WARM OR COOL)
SY 42,768.000 $0.250 $0.120 $0.250
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 703.000 $2.000 $2.650 $2.000
FL BS (CMP IN PLC)(TY A OR B GR4)(10")
SY 14,410.000 $25.000 $20.150 $20.000
REWORK BS MTL (TY A) (6") (DENS CONT)
SY 6,980.000 $5.000 $1.200 $2.500
PRIME COAT (AE-P)
GAL 3,630.000 $4.000 $5.100 $4.600
SUPERPAVE MIXTURES SP-C SAC-A PG70-28
TON 4,309.000 $165.000 $133.000 $110.000
TACK COAT
GAL 3,401.000 $4.000 $3.500 $3.700
PLANE ASPH CONC PAV (2")
SY 2,215.000 $10.000 $13.550 $15.000
CEM STABIL BKFL
CY 200.000 $225.000 $267.000 $250.000
TEMPORARY SPL SHORING
SF 2,600.000 $25.000 $5.800 $34.000
DRILL SHAFT (36 IN)
LF 857.000 $200.000 $250.000 $350.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 144.000 $200.000 $316.500 $200.000
CL C CONC (ABUT)(HPC)
CY 51.400 $1,500.000 $1,450.000 $2,000.000
CL C CONC (CAP)(HPC)
CY 23.400 $1,500.000 $1,600.000 $2,000.000
CL C CONC (COLUMN)(HPC)
CY 32.700 $1,750.000 $1,570.000 $2,000.000
REINF CONC SLAB (HPC)
SF 8,280.000 $27.000 $45.000 $45.000
APPROACH SLAB (HPC)
CY 70.700 $1,100.000 $822.000 $2,000.000
RETAINING WALL (MSE)
SF 5,466.000 $60.000 $56.950 $100.000
PRESTR CONC BOX BEAM (5XB34)
LF 1,074.000 $350.000 $371.500 $400.000
SILICONE RESIN PAINT FINISH
SF 935.000 $12.000 $9.500 $8.000
RIPRAP (CONC)(4 IN)
CY 236.300 $600.000 $452.500 $500.000
RIPRAP (CONC)(6 IN)
CY 33.300 $750.000 $630.000 $600.000
RIPRAP (MOW STRIP)(4 IN)
CY 55.000 $450.000 $510.000 $500.000
RAIL (TY SSTR)(HPC)
LF 396.000 $80.000 $89.000 $90.000
HEADER TYPE EXPANSION JOINT
LF 92.000 $175.000 $110.000 $75.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 75.500 $500.000 $875.000 $1,000.000
RC PIPE (CL III)(24 IN)
LF 45.500 $125.000 $306.500 $300.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (C)
EA 4.000 $5,500.000 $10,150.000 $5,000.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(6:1) (C)
EA 2.000 $6,500.000 $12,675.000 $20,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 2.000 $3,000.000 $5,900.000 $5,000.000
REMOV STR (WINGWALL)
EA 8.000 $1,400.000 $2,400.000 $1,000.000
REMOV STR (PIPE)
LF 10.000 $30.000 $120.000 $150.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $250,000.000 $141,000.000 $350,000.000
MOBILIZATION
LS 1.000 $350,000.000 $570,000.000 $550,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $14,000.000 $13,000.000 $10,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 260.000 $5.000 $7.550 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 260.000 $2.000 $2.550 $5.000
PERM CTB (SGL SLOPE) (TY 1) (54 )
LF 20.000 $50.000 $150.000 $140.000
PERM CTB (SGL SLOPE) (TY 3) (54 )
LF 100.000 $200.000 $310.000 $300.000
MTL W-BEAM GD FEN (STEEL POST)
LF 700.000 $26.000 $28.500 $22.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,000.000 $2,530.000 $1,650.000
REMOVE METAL BEAM GUARD FENCE
LF 1,325.000 $4.000 $3.700 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $350.000 $315.000 $200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,800.000 $3,165.000 $2,675.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $300.000 $315.000 $200.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,700.000 $2,110.000 $1,750.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 2.000 $20,000.000 $26,365.000 $21,625.000
PIPE UNDERDRAINS (TY 6) (6")
LF 401.000 $40.000 $34.400 $114.480
REMOVE RD IL ASM (TRANS-BASE)
EA 9.000 $1,100.000 $530.000 $750.000
IN RD IL (TY AL) 40T-8 (250W EQ) LED
EA 18.000 $5,000.000 $4,745.000 $3,750.000
CONDT (PVC) (SCH 40) (2")
LF 3,445.000 $9.000 $5.300 $6.500
ELEC CONDR (NO.2) BARE
LF 3,995.000 $3.000 $2.650 $3.000
ELEC CONDR (NO.2) INSULATED
LF 7,990.000 $3.000 $3.150 $3.000
GROUND BOX TY A (122311)W/APRON
EA 2.000 $1,000.000 $1,160.000 $750.000
ELC SRV TY A 240/480 100(NS)SS(E)TP(O)
EA 1.000 $7,000.000 $6,330.000 $6,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 12.000 $1,000.000 $790.000 $475.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 1.000 $1,000.000 $790.000 $900.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 19.000 $1,000.000 $845.000 $460.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,050.000 $870.000 $950.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,400.000 $1,080.000 $1,150.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 5.000 $1,000.000 $1,240.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $1,600.000 $1,355.000 $2,150.000
REMOVE SM RD SN SUP&AM
EA 28.000 $120.000 $105.000 $50.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $25.000 $21.000 $24.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $25.000 $37.000 $29.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 75.000 $9.000 $42.000 $40.000
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL)
EA 17.000 $30.000 $105.000 $100.000
PAVEMENT SEALER 4"
LF 600.000 $1.000 $3.150 $3.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 12,839.000 $2.000 $0.790 $0.750
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 660.000 $2.000 $0.790 $0.750
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 7,485.000 $2.000 $0.790 $0.750
REFL PAV MRKR TY II-C-R
EA 72.000 $7.000 $26.350 $25.000
PAV SURF PREP FOR MRK (4")
LF 600.000 $0.740 $3.160 $3.000
ANTI - GRAFFITI COATNG(PERMNENT-TY III)
SF 5,466.000 $1.000 $2.150 $1.200
REMOVE CONDUCTOR
LF 1,981.000 $2.000 $0.550 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $24,100.000 $15,000.000
TMA (STATIONARY)
DAY 300.000 $180.000 $675.000 $315.000
TMA (MOBILE OPERATION)
HR 425.000 $50.000 $67.500 $95.000
Totals: $4,863,893.500 $5,732,295.930 $5,959,892.880