Show Job Controls
Bid Cobra

CAMERON FM1419 (6295-90-001)

Items: 27

County: CAMERON
Length: N/A
Highway: FM1419
District: PHARR
Control Number: 6295-90-001
DBE Goal: N/A
Project: BPM - 629590001
Guaranty: N/A
Time: 120 W
Engineer's Estimate: $475,030.50
Date: 03/08/2017 (9 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$475,030.50
Over/Under Est: -4.08% -$19,357.50
Over/Under Est: -1.29% -$6,142.50
Amt Left: 2.9% $13,215.00
Over/Under Est: -0.21% -$981.50
Amt Left: 4.03% $18,376.00
Delta: -1.10% -$5,161.00

Bid Items & Bid Tabulations

27 Total 0 of 27
CAMERON  |  FM1419  |  PHARR  |  6295-90-001  |  03/08/2017  |  $475,030.50  |  BPM - 629590001  |  BRIDGE PREVENT MAINT  |  120 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
ARANDA BROTHERS CONSTRUCTION CO., INC.
VALLEY INFRASTRUCTURE, INC.
SJ&J CONSTRUCTION, LLC
PREPARING ROW
STA 1.000 $2,000.000 $10,000.000 $3,900.000 $1,500.000
REMOVING CONC (RIPRAP)
SY 273.000 $30.000 $15.000 $25.000 $30.000
EXCAVATION (CHANNEL)
CY 157.000 $15.000 $15.000 $30.000 $15.000
CUT & RESTORING PAV
SY 308.000 $110.000 $100.000 $75.000 $100.000
FLOWABLE BACKFILL
CY 8.000 $250.000 $350.000 $510.000 $200.000
CL C CONC (PILE ENCASEMENT)
CY 7.200 $5,000.000 $1,850.000 $2,500.000 $1,000.000
RIPRAP (CONC)(5 IN)
CY 370.400 $425.000 $355.000 $585.000 $500.000
RIPRAP (CONC)(FLUME)
CY 25.100 $400.000 $300.000 $550.000 $800.000
RETROFIT RAIL (TY T223)
LF 100.000 $200.000 $150.000 $165.000 $200.000
GABION MATTRESSES (PVC)(12 IN)
SY 192.000 $100.000 $75.000 $130.000 $120.000
RC PIPE (CL III)(18 IN)
LF 8.000 $125.000 $50.000 $125.000 $90.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1.000 $1,000.000 $750.000 $1,100.000 $1,900.000
REMOV STR (PIPE)
LF 8.000 $37.500 $30.000 $13.000 $40.000
MOBILIZATION
LS 1.000 $50,000.000 $80,000.000 $25,000.000 $80,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $3,500.000 $3,750.000 $4,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 70.000 $100.000 $50.000 $45.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 70.000 $10.000 $10.000 $20.000 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,111.000 $2.500 $3.000 $3.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,111.000 $0.500 $1.000 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 60.000 $4.000 $10.000 $5.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 60.000 $2.000 $1.000 $1.000 $3.000
CONC CURB (MONO) (TY II)
LF 831.000 $15.000 $7.000 $15.000 $15.000
REMOVE METAL BEAM GUARD FENCE
LF 87.000 $12.500 $10.000 $3.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $250.000 $250.000 $220.000 $300.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 2.000 $2,500.000 $1,750.000 $2,250.000 $2,500.000
CRASH CUSHION ATTEN (INSTALL) (QUAD)(N)
EA 4.000 $17,500.000 $25,000.000 $14,300.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 6.000 $200.000 $250.000 $400.000 $100.000
Totals: $475,030.500 $455,673.000 $468,888.000 $474,049.000