Show Job Controls
Bid Cobra

CAMERON FM 2556 (2529-02-014)

Items: 75

County: CAMERON
Length: 0.0000 MILES
Highway: FM 2556
District: PHARR
Control Number: 2529-02-014
DBE Goal: 0.0%
Project: F 2026(224)
Guaranty: $100,000.00
Time: 443 WORKING DAYS
Engineer's Estimate: $7,384,758.79
Date: 01/06/2026 (5 months ago)
Contract Number: 1263014
Type: TRANSPORTATION NON-ROADWAY
Project ID: A00197563
Contract Type: Federal
Project Description: CONSTRUCT DRAINAGE FEATURES THAT CONSISTS OF CHANNEL EXCAVATION AND RESHAPING. 200' UPSTREAM AND DOWNSTREAM OF THE CROSSING
Mail/Deliver Bids To: N/A
ANDRES ESPINOZA
GABRIEL VILLARREAL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$7,384,758.79
$6,565,145.66
Over/Under Est: -11.1% -$819,613.13
$6,623,432.76
Over/Under Est: -10.31% -$761,326.03
Amt Left: 0.89% $58,287.10
Over/Under Est: 7.56% $557,963.37
Amt Left: 20.98% $1,377,576.50
Delta: -19.92% -$1,319,289.40
$7,997,844.05
Over/Under Est: 8.3% $613,085.26
Amt Left: 21.82% $1,432,698.39
Delta: -0.69% -$55,121.89
$8,168,536.03
Over/Under Est: 10.61% $783,777.24
Amt Left: 24.42% $1,603,390.37
Delta: -2.13% -$170,691.98
$11,290,746.01
Over/Under Est: 52.89% $3,905,987.22
Amt Left: 71.98% $4,725,600.35
Delta: -38.22% -$3,122,209.98
Over/Under Est: 91.81% $6,779,859.21
Amt Left: 115.75% $7,599,472.34
Delta: -25.45% -$2,873,871.99

Bid Items & Bid Tabulations

75 Total 0 of 75
CAMERON  |  FM 2556  |  PHARR  |  2529-02-014  |  01/06/2026  |  $7,384,758.79  |  F 2026(224)  |  TRANSPORT NON-ROADWAY  |  443 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MOR-WIL, L.L.C.
3LW CIVIL LLC
GO UNDERGROUND, LIMITED LIABILITY COMPANY
CLORE EQUIPMENT LLC
FOREMOST PAVING, INC.
IOC COMPANY, LLC
TEXAS CORDIA CONSTRUCTION, LLC
PREPARING ROW
STA 9.000 $3,500.000 $3,777.780 $2,169.440 $800.000 $75,535.190 $6,500.000 $10,000.000 $2,500.000
REMOV CONC (DRIVEWAYS)
SY 187.000 $20.000 $25.450 $55.670 $12.000 $22.950 $38.700 $30.000 $14.000
EXCAV (ROADWAY)
CY 12,172.000 $11.000 $6.980 $23.930 $8.000 $5.940 $17.700 $15.000 $11.000
EXCAV (CHANNEL)
CY 5,370.000 $20.000 $7.100 $27.900 $12.000 $6.610 $17.700 $20.000 $13.000
EMBANK (FNL)(DC)(TY C)
CY 6,162.000 $6.000 $6.620 $10.500 $12.000 $4.630 $24.500 $15.000 $10.000
FURN & PLACE TOPSOIL (VEH)
CY 50.000 $32.500 $136.000 $175.620 $24.000 $65.180 $24.700 $100.000 $80.000
DRILL SEED (PERM_RURAL_CLAY)
SY 5,267.000 $1.000 $1.030 $0.860 $0.760 $0.830 $0.700 $0.680 $1.000
DRILL SEED (TEMP_WARM)
SY 5,267.000 $0.750 $0.760 $0.620 $0.570 $0.710 $0.600 $0.480 $1.000
HYDRO MULCH SEED (PERM_RURAL_SANDY)
SY 3,350.000 $1.300 $1.200 $1.060 $0.900 $0.710 $0.600 $0.840 $1.000
VEGETATIVE WATERING
TGL 506.140 $11.000 $85.000 $75.000 $54.640 $59.520 $36.000 $26.000 $50.000
SOIL RET BLKT(SL_MOD_CLAY_LONG)
SY 4,388.000 $2.500 $1.840 $1.620 $1.370 $3.530 $2.700 $1.250 $3.000
FL BS (CMP IN PLC)(TY A OR B GR 4)(8")
SY 410.000 $65.000 $43.120 $38.780 $21.150 $20.290 $6.200 $38.500 $54.000
FL BS (RDWY DEL)(TY E GR 4)(FNL POS)
CY 383.000 $40.000 $26.210 $108.170 $74.980 $67.010 $37.700 $166.500 $80.000
GEOGRID BASE REINFORCEMENT (TYPE 2)
SY 1,187.000 $1.320 $8.590 $5.240 $1.770 $2.250 $8.800 $10.000 $6.000
LIME (COM OR QK)(SLURRY)
TON 16.240 $340.000 $504.000 $408.000 $350.000 $355.600 $266.500 $345.000 $350.000
LIME TRT (EXIST MATL)(12")
SY 1,142.000 $2.250 $6.800 $22.000 $6.000 $5.270 $20.200 $30.000 $6.000
CEM TRT(PLNT MX)(CL L)(TY E)(GR 4)(8")
SY 16.040 $27.000 $127.180 $290.700 $80.000 $153.510 $1,373.200 $1,000.000 $300.000
PRIME COAT (MC-30)
GAL 225.000 $5.000 $12.090 $22.800 $12.000 $14.430 $11.500 $15.000 $11.000
ASPH (TIER II)
GAL 338.000 $6.000 $47.600 $22.800 $12.000 $10.930 $131.000 $30.000 $9.000
SP MIXES SP-D SAC-A PG76-22
TON 126.000 $130.000 $194.290 $568.100 $119.750 $167.820 $446.300 $600.000 $230.000
STRUCT EXCAV (SPECIAL)
CY 595.000 $91.300 $3.430 $64.990 $85.000 $73.530 $196.000 $120.120 $110.000
CUT & RESTORE ASPH PAVING
SY 911.000 $100.000 $59.710 $131.910 $55.000 $40.870 $91.500 $117.000 $91.000
CUT AND RESTORE PAV (FLEX BASE)
SY 245.000 $90.000 $55.510 $131.180 $55.000 $30.070 $30.000 $49.180 $78.000
CEM STABIL BKFL
CY 368.000 $120.000 $68.000 $290.660 $55.000 $46.600 $127.400 $101.050 $80.000
FLOWABLE BACKFILL
CY 463.000 $100.000 $217.370 $395.740 $150.000 $165.890 $220.500 $306.000 $230.000
TRENCH EXCAVATION PROTECTION
LF 1,382.000 $3.500 $19.680 $7.060 $30.000 $5.000 $0.100 $5.940 $100.000
TEMPORARY SPL SHORING
SF 6,000.000 $20.000 $6.800 $5.060 $40.000 $5.000 $0.100 $97.000 $36.000
RIPRAP (CONC)(CL B)(5 IN)
CY 786.000 $550.000 $652.800 $547.345 $480.000 $317.410 $784.000 $515.000 $800.000
RIPRAP (CONC)(DISSIPATER)
CY 13.000 $600.000 $748.000 $792.110 $2,633.850 $798.610 $882.000 $4,652.920 $2,500.000
RIPRAP (MOW STRIP)(4 IN)
CY 16.000 $600.000 $680.000 $762.260 $480.000 $432.280 $1,862.000 $1,218.790 $860.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 595.000 $200.000 $81.600 $443.080 $157.860 $187.810 $196.000 $290.000 $230.000
CONC BOX CULV (9 FT X 5 FT)
LF 84.000 $1,374.200 $939.050 $1,653.720 $1,593.620 $1,150.550 $2,058.000 $3,235.000 $7,000.000
CONC BOX CULV (9 FT X 9 FT)
LF 752.000 $1,500.000 $1,401.600 $1,543.620 $1,828.790 $1,461.910 $1,526.900 $1,700.000 $4,010.000
CONC BOX CULV (10 FT X 9 FT)
LF 992.000 $2,500.000 $1,604.030 $1,858.820 $1,851.880 $1,547.880 $2,087.400 $2,070.000 $4,575.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 84.000 $600.000 $728.570 $640.780 $386.820 $460.780 $1,274.000 $970.180 $3,500.000
RC PIPE (CL III)(18 IN)
LF 50.000 $80.000 $68.000 $139.850 $74.080 $82.970 $98.000 $274.510 $120.000
WINGWALL (FW - 0) (HW=10 FT)
EA 2.000 $25,000.000 $30,600.000 $17,429.270 $44,000.000 $30,699.210 $39,200.000 $83,500.000 $32,310.000
WINGWALL (FW - S) (HW=10 FT)
EA 2.000 $35,000.000 $30,600.000 $17,309.470 $44,000.000 $58,880.390 $49,000.000 $83,500.000 $32,310.000
WINGWALL (SW - 0) (HW=10 FT)
EA 4.000 $30,000.000 $15,300.000 $17,309.160 $44,000.000 $36,850.230 $43,120.000 $83,500.000 $32,310.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 2.000 $1,000.000 $3,400.000 $2,850.000 $2,000.000 $1,742.330 $1,176.000 $2,970.850 $1,930.000
REMOV STR (WINGWALL)
EA 3.000 $5,810.000 $4,533.330 $3,654.160 $3,200.000 $2,072.400 $3,430.000 $3,335.460 $8,180.000
REMOV STR (HEADWALL)
EA 6.000 $24,000.000 $4,080.000 $1,827.080 $3,200.000 $2,072.410 $3,430.000 $2,854.700 $7,950.000
REMOV STR (PIPE)
LF 558.000 $20.000 $36.560 $78.050 $12.000 $19.150 $147.000 $105.980 $35.000
REMOV STR (BOX CULVERT)
LF 120.000 $650.000 $136.000 $225.210 $22.000 $44.520 $147.000 $108.640 $240.000
REMOVE CONC. WELL & GATE
EA 1.000 $360,000.000 $13,600.000 $7,881.250 $2,250.000 $8,148.880 $9,800.000 $7,080.280 $21,260.000
MOBILIZATION
LS 1.000 $120,361.680 $118,000.000 $722,808.010 $480,000.000 $759,795.180 $500,000.000 $970,000.000 $1,100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 28.000 $5,000.000 $680.000 $649.500 $4,200.000 $3,647.040 $2,200.000 $3,662.400 $500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 443.000 $80.000 $147.360 $78.000 $25.000 $109.960 $48.700 $267.090 $23.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 546.000 $70.000 $62.270 $33.600 $28.000 $13.260 $40.900 $53.950 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 546.000 $28.000 $29.410 $10.200 $1.000 $1.940 $24.100 $20.290 $9.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 735.000 $5.500 $5.440 $4.800 $8.000 $7.410 $4.500 $3.750 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 735.000 $2.500 $2.720 $2.400 $1.000 $2.330 $2.000 $1.750 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,450.000 $5.000 $7.820 $6.900 $8.000 $4.250 $6.700 $5.500 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,450.000 $2.000 $1.700 $1.500 $1.000 $1.180 $2.000 $1.150 $2.000
DRIVEWAYS (CONC)
SY 187.000 $120.000 $145.450 $109.800 $80.000 $95.950 $88.600 $219.330 $150.000
MTL W-BEAM GD FEN (TIM POST)
LF 445.000 $29.000 $67.320 $36.090 $24.440 $53.090 $29.100 $31.010 $35.000
REMOVE METAL BEAM GUARD FENCE
LF 350.000 $12.000 $13.600 $6.510 $1.000 $9.640 $3.000 $16.120 $12.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $5,712.000 $4,410.800 $2,114.000 $4,094.960 $3,217.400 $3,570.830 $4,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $320.000 $952.000 $585.400 $1.000 $694.360 $323.400 $537.450 $250.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 2.000 $1,250.000 $1,740.800 $1,536.000 $1,200.000 $1,055.440 $970.200 $1,022.200 $1,560.000
REMOVE SM RD SN SUP&AM
EA 2.000 $200.000 $1,332.800 $1,176.000 $1.000 $405.940 $107.800 $98.180 $700.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 4.000 $45.000 $306.000 $35.400 $822.000 $48.710 $57.900 $213.680 $450.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 4.000 $85.000 $272.000 $35.220 $822.000 $48.710 $63.700 $231.010 $450.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 2.000 $15.000 $612.000 $540.000 $300.000 $27.070 $17.700 $57.750 $700.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 44.000 $0.650 $16.320 $14.400 $18.180 $10.830 $1.100 $13.020 $5.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 548.000 $0.650 $2.040 $1.800 $1.100 $2.710 $3.200 $1.500 $5.000
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 78.000 $5.000 $2.040 $1.800 $5.000 $2.710 $3.200 $1.500 $10.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 601.000 $0.750 $2.040 $1.800 $1.000 $2.710 $3.200 $1.500 $5.000
REFL PAV MRKR TY II-A-A (CALLOUT)
EA 14.000 $100.000 $13.600 $12.000 $250.000 $8.120 $9.700 $10.000 $100.000
ELIM EXT PM & MRKS (4")
LF 5,687.000 $0.350 $1.360 $1.200 $0.600 $1.620 $0.600 $1.000 $1.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 350.000 $7.000 $13.600 $66.000 $12.000 $23.470 $44.100 $85.910 $95.000
BONDING COURSE
GAL 338.000 $4.000 $10.060 $22.800 $10.000 $16.810 $2.300 $31.570 $10.000
INSTALL VERTICAL AXIAL OR MX FLOW PUMP
EA 1.000 $414,000.000 $1,418,425.600 $90,000.000 $1,700,000.000 $950,391.700 $862,400.000 $1,312,000.000 $1,500,000.000
INSTALL STAINLESS STEEL SLIDE GATES
EA 1.000 $180,000.000 $409,162.800 $90,000.000 $335,000.000 $746,925.000 $686,000.000 $1,350,983.000 $400,000.000
INSTALL PRE-ENGINEERED METAL CANOPY
EA 1.000 $360,000.000 $61,200.000 $48,000.000 $60,000.000 $568,312.500 $39,200.000 $410,000.000 $200,000.000
Totals: $7,384,758.790 $6,565,145.657 $6,623,432.758 $7,942,722.160 $7,997,844.057 $8,168,536.028 $11,290,746.010 $14,164,618.000