PREPARING ROW
|
STA
|
403.000
|
$2,000.000
|
$2,735.000
|
$1,110.000
|
$1,450.000
|
$2,500.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
31,754.000
|
$4.000
|
$4.000
|
$7.400
|
$10.000
|
$15.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
812.000
|
$8.440
|
$12.000
|
$12.500
|
$8.000
|
$15.000
|
|
|
REMOVING STAB BASE & ASPH PAV (12"-14")
|
SY
|
147,117.000
|
$2.730
|
$3.500
|
$5.400
|
$5.000
|
$8.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
8,410.000
|
$4.220
|
$7.000
|
$6.800
|
$9.000
|
$8.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
8,216.000
|
$4.670
|
$4.000
|
$6.050
|
$12.000
|
$5.000
|
|
|
BACKFILL (TY A)
|
STA
|
403.000
|
$196.500
|
$125.000
|
$325.000
|
$320.000
|
$275.000
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
169,219.000
|
$0.120
|
$0.350
|
$0.250
|
$0.400
|
$0.350
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
169,219.000
|
$0.120
|
$0.350
|
$0.250
|
$0.400
|
$0.350
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
AC
|
34.110
|
$607.320
|
$1,400.000
|
$2,500.000
|
$1,400.000
|
$1,400.000
|
|
|
VEGETATIVE WATERING
|
MG
|
24.400
|
$30.130
|
$100.000
|
$38.000
|
$115.000
|
$180.000
|
|
|
SPRINKLING (DUST CONTROL)
|
MG
|
403.000
|
$2.490
|
$1.000
|
$33.750
|
$27.000
|
$1.000
|
|
|
PROOF ROLLING
|
HR
|
15.120
|
$50.380
|
$80.000
|
$61.500
|
$61.000
|
$50.000
|
|
|
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
|
CY
|
65,573.000
|
$26.000
|
$44.500
|
$48.500
|
$50.000
|
$60.000
|
|
|
LIME TRT (EXST MATL) (12")
|
SY
|
198,674.000
|
$3.000
|
$2.250
|
$2.200
|
$3.000
|
$2.000
|
|
|
LIME (HYD, COM OR QK)(SLURRY)
|
TON
|
5,893.000
|
$202.710
|
$260.000
|
$340.000
|
$300.000
|
$225.000
|
|
|
CEMENT
|
TON
|
2,473.000
|
$198.180
|
$190.000
|
$229.000
|
$200.000
|
$200.000
|
|
|
CEMENT TREAT (NEW BASE)(12")
|
SY
|
196,691.000
|
$3.500
|
$2.000
|
$2.800
|
$3.000
|
$3.750
|
|
|
ASPH (TIER II)
|
GAL
|
55,704.000
|
$4.170
|
$6.000
|
$4.150
|
$5.000
|
$5.350
|
|
|
AGGR (TY-D GR-4P)(SAC-B)
|
CY
|
1,560.000
|
$63.820
|
$65.000
|
$102.000
|
$130.000
|
$145.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
370.000
|
$1.510
|
$18.000
|
$5.950
|
$7.000
|
$5.000
|
|
|
PLANE ASPH CONC PAV (1.5")
|
SY
|
457.000
|
$1.350
|
$18.000
|
$7.000
|
$6.000
|
$5.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
1,749.000
|
$132.990
|
$240.000
|
$171.000
|
$180.000
|
$225.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
157.000
|
$340.470
|
$1,000.000
|
$429.000
|
$560.000
|
$625.000
|
|
|
RIPRAP (MOW STRIP)(5 IN)
|
CY
|
135.000
|
$327.620
|
$750.000
|
$414.000
|
$600.000
|
$700.000
|
|
|
RAIL (TY SSTR)
|
LF
|
190.000
|
$145.000
|
$250.000
|
$146.000
|
$270.000
|
$200.000
|
|
|
RETROFIT RAIL (TY SSTR)
|
LF
|
134.000
|
$168.680
|
$315.000
|
$237.000
|
$360.000
|
$200.000
|
|
|
CONC BOX CULV (8 FT X 5 FT)
|
LF
|
98.000
|
$900.000
|
$1,600.000
|
$1,460.000
|
$1,820.000
|
$1,000.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
686.000
|
$38.470
|
$92.000
|
$78.000
|
$91.000
|
$150.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
38.000
|
$953.610
|
$1,400.000
|
$1,130.000
|
$1,300.000
|
$1,250.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
21.000
|
$1,558.820
|
$7,000.000
|
$3,270.000
|
$6,000.000
|
$1,000.000
|
|
|
REMOV STR (SET)
|
EA
|
11.000
|
$236.480
|
$500.000
|
$374.000
|
$360.000
|
$600.000
|
|
|
REMOV STR (PIPE)
|
LF
|
546.000
|
$6.060
|
$20.000
|
$14.750
|
$11.000
|
$10.000
|
|
|
REMOVE STR (RAIL)
|
LF
|
209.000
|
$24.560
|
$20.000
|
$27.500
|
$290.000
|
$15.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,250,000.000
|
$950,000.000
|
$900,000.000
|
$1,085,000.000
|
$2,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
20.000
|
$2,602.370
|
$5,000.000
|
$4,330.000
|
$8,000.000
|
$3,750.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
312.000
|
$26.490
|
$48.000
|
$24.500
|
$18.000
|
$33.610
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
446.000
|
$8.070
|
$12.000
|
$7.500
|
$9.000
|
$14.660
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
430.000
|
$3.350
|
$4.000
|
$3.500
|
$5.000
|
$4.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
430.000
|
$1.300
|
$1.000
|
$1.050
|
$2.000
|
$2.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
30,195.000
|
$4.050
|
$4.000
|
$3.350
|
$5.000
|
$5.350
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
30,195.000
|
$0.930
|
$1.000
|
$1.000
|
$1.000
|
$1.300
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
570.000
|
$65.000
|
$20.000
|
$16.750
|
$42.000
|
$75.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
1,165.000
|
$5.000
|
$10.000
|
$4.550
|
$25.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
570.000
|
$10.000
|
$10.000
|
$14.250
|
$27.000
|
$15.000
|
|
|
CONCRETE CURB (SPECIAL)
|
LF
|
214.000
|
$15.110
|
$50.000
|
$55.500
|
$49.000
|
$75.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
12,472.000
|
$45.130
|
$30.000
|
$35.250
|
$31.000
|
$67.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,175.000
|
$33.500
|
$36.000
|
$38.250
|
$33.000
|
$32.550
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$2,104.800
|
$2,800.000
|
$2,750.000
|
$2,350.000
|
$2,345.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,050.000
|
$2.090
|
$2.500
|
$6.900
|
$3.000
|
$3.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
2.000
|
$195.210
|
$200.000
|
$331.000
|
$230.000
|
$225.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$222.770
|
$200.000
|
$264.000
|
$230.000
|
$225.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
11.000
|
$3,299.490
|
$3,600.000
|
$4,160.000
|
$3,550.000
|
$3,545.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
10.000
|
$248.980
|
$200.000
|
$323.000
|
$280.000
|
$275.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
6.000
|
$1,044.880
|
$3,100.000
|
$1,500.000
|
$1,100.000
|
$1,100.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$806.240
|
$1,525.000
|
$847.000
|
$930.000
|
$925.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$10,000.000
|
$10,900.000
|
$10,100.000
|
$8,630.000
|
$8,625.000
|
|
|
CRASH CUSHION ATTEN (INSTALL) (QUAD)(N)
|
EA
|
1.000
|
$38,255.500
|
$31,500.000
|
$30,900.000
|
$26,280.000
|
$26,275.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
1.000
|
$317.000
|
$625.000
|
$646.000
|
$760.000
|
$1,141.080
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
134.000
|
$220.770
|
$260.000
|
$217.000
|
$440.000
|
$185.000
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
5.000
|
$254.640
|
$300.000
|
$247.000
|
$430.000
|
$521.890
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
136.000
|
$26.500
|
$40.000
|
$28.750
|
$45.000
|
$22.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
12.000
|
$651.280
|
$725.000
|
$763.000
|
$900.000
|
$650.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
78.000
|
$700.000
|
$780.000
|
$781.000
|
$890.000
|
$665.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
18.000
|
$925.160
|
$825.000
|
$969.000
|
$1,070.000
|
$825.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
6.000
|
$1,114.950
|
$1,000.000
|
$1,140.000
|
$1,140.000
|
$975.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
88.000
|
$108.420
|
$80.000
|
$100.000
|
$100.000
|
$70.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
15.000
|
$25.420
|
$10.000
|
$21.250
|
$10.000
|
$18.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
22.000
|
$49.500
|
$30.000
|
$71.500
|
$100.000
|
$85.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
19.000
|
$100.000
|
$50.000
|
$75.000
|
$100.000
|
$85.000
|
|
|
INS DEL ASSM(D-SW)SZ 1(WFLX)GF2(BI)
|
EA
|
32.000
|
$150.000
|
$55.000
|
$45.250
|
$100.000
|
$35.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
81,000.000
|
$0.560
|
$0.300
|
$0.300
|
$0.300
|
$0.280
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
81,000.000
|
$0.370
|
$0.300
|
$0.300
|
$0.300
|
$0.280
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
4,050.000
|
$0.870
|
$1.000
|
$1.900
|
$3.000
|
$1.540
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
4,050.000
|
$0.190
|
$1.000
|
$2.000
|
$3.000
|
$1.670
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
602.000
|
$1.150
|
$1.000
|
$1.050
|
$0.900
|
$0.900
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
567.000
|
$6.860
|
$9.000
|
$10.500
|
$9.000
|
$9.000
|
|
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
|
LF
|
1,364.000
|
$3.220
|
$9.000
|
$10.500
|
$9.000
|
$9.000
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
79,405.000
|
$0.280
|
$0.650
|
$0.700
|
$0.600
|
$0.620
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
7,880.000
|
$0.350
|
$0.650
|
$0.700
|
$0.600
|
$0.620
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
24,466.000
|
$0.340
|
$0.650
|
$0.700
|
$0.600
|
$0.620
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
79,405.000
|
$0.500
|
$0.750
|
$0.900
|
$0.700
|
$0.800
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
5.000
|
$227.870
|
$200.000
|
$235.000
|
$200.000
|
$200.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
5.000
|
$253.540
|
$275.000
|
$323.000
|
$280.000
|
$275.000
|
|
PREFAB PAV MRK TY C (W) (RR XING)
|
EA
|
2.000
|
$598.330
|
$500.000
|
$587.000
|
$500.000
|
$500.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
951.000
|
$3.420
|
$4.000
|
$4.500
|
$4.000
|
$3.850
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
960.000
|
$3.120
|
$4.000
|
$4.500
|
$4.000
|
$3.850
|
|
|
TREE TRIMMING / BRUSH REMOVAL
|
MI
|
1.000
|
$8,315.640
|
$5,000.000
|
$4,240.000
|
$5,000.000
|
$5,000.000
|
|
|
TREE REMOVAL (12" - 18" DIA)
|
EA
|
12.000
|
$1,275.260
|
$1,500.000
|
$969.000
|
$1,500.000
|
$330.070
|
|
|
DITCH CLEANING AND RESHAPING (FOOT)
|
LF
|
80,872.000
|
$5.000
|
$1.000
|
$1.600
|
$6.000
|
$6.000
|
|
|
SP MIXES SP-D SAC-A PG76-22
|
TON
|
31,199.000
|
$114.240
|
$114.000
|
$138.000
|
$130.000
|
$137.750
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
|
TON
|
39.070
|
$122.790
|
$200.000
|
$231.000
|
$240.000
|
$250.000
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
198,674.000
|
$1.430
|
$1.000
|
$1.150
|
$2.000
|
$2.250
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$4,859.880
|
$5,000.000
|
$16,300.000
|
$8,000.000
|
$20,000.000
|
|
|
PREFORMED CENTERLINE RUMBLE STRIP
|
LF
|
39,150.000
|
$0.180
|
$3.070
|
$5.850
|
$0.500
|
$5.500
|
|
|
TMA (STATIONARY)
|
DAY
|
347.000
|
$250.000
|
$25.000
|
$294.000
|
$25.000
|
$1.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
200.000
|
$25.000
|
$0.010
|
$129.000
|
$25.000
|
$10.000
|
|
Totals: |
$14,086,164.148
|
$15,675,730.800
|
$17,112,917.500
|
$17,925,284.220
|
$20,633,048.520
|