Show Job Controls
Bid Cobra

CAMERON VA (0921-06-269)

Items: 31

County: CAMERON
Length: N/A
Highway: VA
District: PHARR
Control Number: 0921-06-269
DBE Goal: N/A
Project: C 921-6-269
Guaranty: N/A
Time: 56 WORKING DAYS
Engineer's Estimate: $1,708,246.70
Date: 11/01/2023 (2 years ago)
Contract Number: N/A
Type: TRANSPORTATION NON-ROADWAY
Mail/Deliver Bids To: N/A
ANDRES ESPINOZA
GABRIEL VILLARREAL
FRANCISCO J CANTU
DANNY FLORES
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$1,708,246.70
$1,429,710.50
Over/Under Est: -16.31% -$278,536.20
$2,040,655.00
Over/Under Est: 19.46% $332,408.30
Amt Left: 42.73% $610,944.50
Subcontractor Percentage Amount
PAVEMENT MARKINGS INC. 2.92% $49,831.99
HIGHWAY BARRICADES AND SERVICES, LLC 0.61% $10,410.11
SOIL TECH ADVANCE INC. 0.56% $9,556.82
Total: 4.09% $69,798.92

Bid Items & Bid Tabulations

31 Total 0 of 31
CAMERON  |  VA  |  PHARR  |  0921-06-269  |  11/01/2023  |  $1,708,246.70  |  C 921-6-269  |  TRANSPORT NON-ROADWAY  |  56 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CK NEWBERRY, LLC
FOREMOST PAVING, INC.
REMOVING STAB BASE AND ASPH PAV (6")
SY 733.000 $15.000 $25.000 $35.000
REWORK BS MTL (TY D)(SURF)(ORD COMP)
SY 61.000 $4.000 $175.000 $160.000
CEMENT
TON 4.000 $200.000 $2,500.000 $275.000
CEMENT TREAT (NEW BASE) (6")
SY 733.000 $25.000 $55.000 $40.000
PRIME COAT (MC-30)
GAL 9,782.000 $10.000 $3.500 $10.000
AGGR(TY-PB GR-4 SAC-B)
CY 416.000 $258.000 $400.000 $190.000
AGGR (TY-PD GR-4P)(SAC-B)
CY 407.000 $350.000 $500.000 $190.000
ASPH (SPG 79-13)
GAL 31,575.000 $10.000 $10.000 $35.000
PLANE ASPH CONC PAV (1.5")
SY 13,226.000 $6.000 $10.000 $10.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 308.000 $15.750 $45.000 $95.000
RIPRAP (CONC)(5 IN)
CY 1.200 $720.000 $6,000.000 $7,500.000
MOBILIZATION
LS 1.000 $800,000.000 $140,000.000 $110,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $8,000.000 $20,000.000 $16,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,628.000 $5.000 $6.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,628.000 $2.000 $2.000 $5.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 61.000 $9.000 $10.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 61.000 $6.000 $5.000 $5.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 9.000 $1,100.000 $1,045.000 $2,500.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 553.000 $7.000 $5.000 $5.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 155.000 $2.500 $3.000 $3.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 10,618.000 $0.600 $2.250 $2.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 4,722.000 $1.000 $3.000 $3.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 17,819.000 $0.600 $2.000 $2.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $250.000 $225.000 $650.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 2.000 $400.000 $505.000 $1,200.000
PREFAB PAV MRK TY C (W) (WORD)
EA 28.000 $300.000 $400.000 $670.000
PRE PM TY C(ACC PRK)(BL&WH)(W/BORDR)LG
EA 18.000 $700.000 $325.000 $410.000
D-GR HMA TY-D SAC-A PG76-22
TON 6.000 $300.000 $3,000.000 $2,500.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 98.000 $145.000 $1,000.000 $950.000
FRNISH & INSTAL PRECST CONC WHEEL STOPS
EA 12.000 $50.000 $850.000 $150.000
MOVE AND RESET PRECAST CONC WHEEL STOP
EA 98.000 $100.000 $120.000 $80.000
Totals: $1,708,246.700 $1,429,710.500 $2,040,655.000