Show Job Controls
Bid Cobra

CAMERON SH 48 (0220-05-080)

Items: 136

County: CAMERON
Length: N/A
Highway: SH 48
District: PHARR
Control Number: 0220-05-080
DBE Goal: 650.0%
Project: STP 2024(690)HES
Guaranty: N/A
Time: 201 WORKING DAYS
Engineer's Estimate: $5,830,776.53
Date: 01/05/2024 (2 years ago)
Contract Number: N/A
Type: INSTALL RAISED MEDIAN
Mail/Deliver Bids To: N/A
ANDRES ESPINOZA
GABRIEL VILLARREAL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$5,830,776.53
$4,549,748.76
Over/Under Est: -21.97% -$1,281,027.77
$5,124,087.55
Over/Under Est: -12.12% -$706,688.98
Amt Left: 12.62% $574,338.79
Over/Under Est: 13.35% $778,548.87
Amt Left: 45.27% $2,059,576.64
Delta: -28.99% -$1,485,237.85
Subcontractor Percentage Amount
HIGHWAY BARRICADES AND SERVICES, LLC 6.98% $317,572.46
*AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. 4.44% $202,008.84
LAREDO STRIPING, INC. 2.25% $102,369.35
TEXAS HIGHWAY SYSTEMS, INC. 0.69% $31,393.27
SOIL TECH ADVANCE INC. 0.56% $25,478.59
Total: 14.92% $678,822.51

Bid Items & Bid Tabulations

136 Total 0 of 136
CAMERON  |  SH 48  |  PHARR  |  0220-05-080  |  01/05/2024  |  $5,830,776.53  |  STP 2024(690)HES  |  INSTL RAISED MEDIAN  |  201 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
IOC COMPANY, LLC
FOREMOST PAVING, INC.
TEXAS CORDIA CONSTRUCTION, LLC
PREPARING ROW
STA 199.000 $2,500.000 $1,110.000 $500.000 $725.000
REMOVING CONC (MEDIANS)
SY 258.000 $14.000 $15.000 $50.000 $12.000
REMOVING CONC (FOUNDATIONS)
CY 5.500 $205.000 $250.000 $650.000 $260.000
REMOVING CONC (CURB)
LF 5.000 $30.000 $100.000 $100.000 $180.000
REMOVING CONC (SAWCUT)
LF 5.000 $15.000 $125.000 $100.000 $280.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 1,691.000 $0.280 $0.900 $1.000 $3.000
DRILL SEEDING (TEMP) (WARM)
SY 1,691.000 $0.230 $0.900 $1.000 $2.000
VEGETATIVE WATERING
MG 0.400 $27.640 $350.000 $550.000 $500.000
SPRINKLING (DUST CONTROL)
MG 100.000 $17.000 $35.000 $1.000 $30.000
PLANE ASPH CONC PAV (1.5")
SY 136,694.000 $2.000 $0.500 $2.500 $3.000
FULL - DEPTH REPAIR CRCP (10")
SY 50.000 $200.000 $400.000 $850.000 $1,070.000
STRUCT EXCAV
CY 50.000 $25.000 $150.000 $10.000 $120.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 95.000 $340.000 $348.110 $320.000 $340.000
CL A CONC (COLLAR)
EA 6.000 $1,500.000 $1,500.000 $2,700.000 $4,330.000
RIPRAP (CONC)(CL B)
CY 1,216.000 $475.000 $395.000 $325.000 $705.000
RIPRAP (MOW STRIP)(4 IN)
CY 27.400 $510.000 $600.000 $425.000 $675.000
RC PIPE (CL III)(18 IN)
LF 279.000 $75.000 $120.000 $140.000 $110.000
RC PIPE (CL III)(24 IN)
LF 106.000 $90.000 $170.000 $170.000 $120.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 1.000 $7,300.000 $3,750.000 $5,400.000 $4,160.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 8.000 $1,196.000 $1,100.000 $1,700.000 $1,260.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 1.000 $1,800.000 $2,500.000 $2,300.000 $1,890.000
ADJUSTING MANHOLES (SANITARY)
EA 8.000 $700.000 $2,000.000 $5,300.000 $4,470.000
CLEAN EXIST CULVERTS
EA 5.000 $2,400.000 $1,500.000 $3,000.000 $1,860.000
REMOV STR (SET)
EA 10.000 $450.200 $500.000 $1,000.000 $470.000
REMOV STR (HEADWALL)
EA 1.000 $1,750.000 $3,000.000 $800.000 $4,820.000
REMOV STR (PIPE)
LF 66.000 $20.000 $30.000 $25.000 $30.000
MOBILIZATION
LS 1.000 $560,000.000 $400,000.000 $450,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $10,000.000 $1,500.000 $5,000.000 $5,000.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 1,170.000 $37.000 $40.940 $25.000 $20.000
CONSTRUCTION EXITS (REMOVE)
SY 1,170.000 $10.220 $6.620 $10.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 360.000 $4.000 $4.500 $5.000 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 360.000 $1.200 $1.500 $2.000 $5.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,286.000 $3.900 $5.250 $6.000 $3.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,002.000 $1.000 $1.250 $2.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 716.000 $4.000 $6.000 $6.000 $5.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 8,160.000 $32.500 $15.000 $30.000 $110.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 560.000 $45.000 $15.000 $30.000 $120.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 24,320.000 $7.500 $1.000 $5.000 $10.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 1,280.000 $9.000 $1.000 $5.000 $8.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 8,160.000 $10.000 $5.000 $11.000 $10.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 560.000 $12.000 $5.000 $11.000 $20.000
PERM CTB (F-SHAPE) (TY 1)
LF 750.000 $140.000 $60.000 $85.000 $150.000
PERM CTB (F-SHAPE)(SPL)
LF 5.000 $300.000 $2,250.000 $1,200.000 $1,540.000
CONC CURB (TY II)
LF 7,625.000 $25.000 $10.000 $20.000 $25.000
CONC CURB (MOUNTABLE)
LF 24,885.000 $25.000 $12.750 $11.600 $17.000
DRIVEWAYS (CONC)
SY 530.000 $82.000 $175.000 $200.000 $110.000
DRIVEWAYS (ACP)
SY 61.100 $37.140 $150.000 $200.000 $130.000
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $28.000 $29.210 $35.000 $30.000
MTL W-BEAM GD FEN (STEEL POST)
LF 250.000 $34.000 $35.210 $40.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,420.000 $2,765.210 $2,850.000 $2,560.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,700.000 $1,498.490 $1,500.000 $1,130.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $3.000 $2.490 $3.000 $7.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $270.000 $195.490 $196.000 $220.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 2.000 $196.200 $195.210 $196.000 $230.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,350.000 $3,570.490 $3,600.000 $3,180.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $260.400 $195.210 $200.000 $470.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,075.000 $1,521.490 $1,600.000 $1,800.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $9,500.000 $15,023.230 $12,000.000 $11,210.000
RELOCATE EXISTING MAILBOX
EA 1.000 $405.000 $321.490 $325.000 $1,000.000
CONDT (PVC) (SCH 40) (4")
LF 70.000 $27.000 $30.940 $29.000 $30.000
CONDT (PVC) (SCH 80) (4") (BORE)
LF 182.000 $40.000 $48.630 $45.000 $50.000
ELEC CONDR (NO.8) BARE
LF 662.000 $1.600 $2.210 $2.000 $2.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 437.000 $3.000 $2.540 $2.500 $2.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 37.000 $788.000 $749.210 $750.000 $900.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 18.000 $975.000 $821.490 $850.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 32.000 $108.000 $149.210 $150.000 $120.000
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 28.000 $4.590 $5.000 $5.000 $5.000
WK ZN PAV MRK REMOV (REFL) TY II-C-R
EA 1,696.000 $5.250 $5.000 $5.000 $5.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 16,270.000 $1.250 $0.550 $0.800 $1.000
WK ZN PAV MRK REMOV (W)4"(DOT)
LF 1,190.000 $1.250 $1.200 $1.450 $1.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 64,100.000 $0.800 $0.320 $0.700 $0.320
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 140.000 $1.250 $0.480 $4.000 $0.480
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 374.000 $8.100 $12.000 $11.000 $10.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 61,830.000 $0.700 $0.320 $0.700 $0.320
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 9,500.000 $1.500 $1.640 $1.000 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,000.000 $1.500 $1.710 $1.000 $3.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 7,986.000 $1.100 $0.880 $1.400 $1.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 175.000 $3.180 $5.000 $5.000 $5.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,606.000 $6.850 $8.000 $10.000 $8.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 28.000 $5.500 $5.000 $13.000 $5.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 7,500.000 $0.720 $0.780 $0.800 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 28,914.000 $0.680 $0.780 $0.700 $1.000
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 160.000 $0.690 $0.780 $1.650 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 20,364.000 $0.690 $0.780 $0.650 $1.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 41.000 $230.000 $200.000 $255.000 $200.000
PREFAB PAV MRK TY C (W) (WORD)
EA 41.000 $268.510 $300.000 $285.000 $300.000
PREFAB PAV MRK TY C (W)(BIKE ARROW)
EA 1.000 $140.000 $400.000 $140.000 $400.000
PREFAB PAV MRK TY C (W)(BIKE SYMBOL)
EA 1.000 $210.000 $400.000 $185.000 $400.000
REFL PAV MRKR TY I-C
EA 152.000 $4.450 $5.000 $5.000 $5.000
REFL PAV MRKR TY II-A-A
EA 78.000 $4.400 $5.000 $5.000 $5.000
REFL PAV MRKR TY II-C-R
EA 1,073.000 $4.330 $5.000 $4.000 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 76,910.000 $0.210 $0.400 $0.670 $0.400
ELIM EXT PAV MRK & MRKS (8")
LF 5,267.000 $0.860 $0.650 $0.900 $1.000
ELIM EXT PAV MRK & MRKS (12")
LF 1,723.000 $1.400 $0.850 $2.500 $1.000
ELIM EXT PAV MRK & MRKS (24")
LF 796.000 $3.760 $4.000 $6.000 $4.000
ELIM EXT PAV MRK & MRKS (ARROW)
EA 59.000 $62.000 $70.000 $60.000 $70.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 39.000 $67.000 $70.000 $60.000 $70.000
PAV SURF PREP FOR MRK (4")
LF 3,918.000 $0.130 $0.100 $0.200 $0.100
PAV SURF PREP FOR MRK (6")
LF 5,948.000 $0.100 $0.200 $0.300 $0.200
PAV SURF PREP FOR MRK (8")
LF 4,634.000 $0.200 $0.300 $0.500 $0.300
PAV SURF PREP FOR MRK (24")
LF 160.000 $0.850 $5.000 $1.100 $5.000
PAV SURF PREP FOR MRK (ARROW)
EA 16.000 $22.400 $50.000 $5.250 $50.000
PAV SURF PREP FOR MRK (WORD)
EA 16.000 $24.400 $50.000 $5.000 $50.000
INSTALL HWY TRF SIG (ISOLATED)
EA 4.000 $28,920.000 $6,078.170 $5,500.000 $5,960.000
REMOVING TRAFFIC SIGNALS
EA 4.000 $4,655.000 $1,989.220 $1,800.000 $1,950.000
VEH SIG SEC (12")LED(GRN)
EA 14.000 $295.000 $292.860 $270.000 $290.000
VEH SIG SEC (12")LED(GRN ARW)
EA 6.000 $268.000 $292.860 $270.000 $290.000
VEH SIG SEC (12")LED(YEL)
EA 14.000 $300.000 $292.860 $270.000 $290.000
VEH SIG SEC (12")LED(YEL ARW)
EA 10.000 $320.000 $292.860 $270.000 $290.000
VEH SIG SEC (12")LED(RED)
EA 14.000 $295.000 $292.860 $270.000 $290.000
VEH SIG SEC (12")LED(RED ARW)
EA 4.000 $322.410 $292.860 $270.000 $290.000
BACKPLATE W/REFL BRDR(4 SEC)
EA 4.000 $166.000 $195.610 $180.000 $190.000
BACKPLATE W/REFL BRDR(5 SEC)
EA 2.000 $200.000 $229.870 $210.000 $230.000
BACKPLATE W/REFL BRDR(3 SEC)
EA 12.000 $140.000 $160.240 $150.000 $160.000
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 1,264.000 $2.000 $2.100 $2.000 $2.000
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 2,411.000 $3.000 $2.540 $2.300 $2.000
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 897.000 $3.400 $2.760 $2.500 $3.000
INS TRF SIG PL AM(S)1 ARM(36')
EA 1.000 $13,000.000 $13,371.960 $12,100.000 $13,100.000
INS TRF SIG PL AM(S)1 ARM(40')LUM
EA 1.000 $17,440.000 $16,024.250 $15,000.000 $15,700.000
INS TRF SIG PL AM(S)1 ARM(44')
EA 2.000 $14,482.000 $16,300.540 $15,000.000 $15,970.000
INS TRF SIG PL AM(S)1 ARM(44')LUM
EA 2.000 $17,090.000 $16,411.050 $15,000.000 $16,080.000
CRACK CLEANING AND SEALING (CRCP)
LF 100.000 $25.000 $25.000 $100.000 $30.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 100.000 $100.000 $150.000 $150.000 $190.000
STONE-MTRX-ASPH SMA-F SAC-A PG76-22
TON 10,887.000 $109.840 $155.000 $144.500 $145.000
BONDING COURSE
GAL 8,915.000 $4.250 $1.500 $2.000 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $6,763.000 $100.000 $7,500.000 $1,500.000
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 7,770.000 $1.600 $2.600 $1.850 $3.000
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 2,948.000 $1.900 $3.100 $2.450 $3.000
MULTIPOLYMER PAV MRK (W)(6")(DOT)
LF 102.000 $2.910 $4.100 $4.850 $4.000
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 5,929.000 $3.000 $4.100 $3.800 $4.000
MULTIPOLYMER PAV MRK (W)(24")(SLD)
LF 1,793.000 $11.200 $8.100 $12.850 $8.000
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
LF 7,054.000 $2.000 $2.600 $1.850 $3.000
MULTIYPOLYMER PAV MRK (W) (ARROW)
EA 32.000 $250.000 $325.000 $320.000 $330.000
MULTIPOLYMER PAV MRK (W) (WORD)
EA 30.000 $314.000 $400.000 $320.000 $400.000
TMA (STATIONARY)
DAY 251.000 $100.000 $0.100 $95.000 $50.000
TMA (MOBILE OPERATION)
DAY 201.000 $100.000 $0.100 $1.000 $50.000
Totals: $5,830,776.530 $4,549,748.760 $5,124,087.550 $6,609,325.400