Show Job Controls
Bid Cobra

CALLAHAN US 283 (0437-04-034)

Items: 64

County: CALLAHAN
Length: N/A
Highway: US 283
District: ABILENE
Control Number: 0437-04-034
DBE Goal: N/A
Project: BR 2023(912)
Guaranty: N/A
Time: 137 WORKING DAYS
Engineer's Estimate: $3,172,327.14
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
BRYCE TURENTINE
CHAD W CARTER
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$3,172,327.14
$3,377,698.15
Over/Under Est: 6.47% $205,371.01
Over/Under Est: 10.31% $327,082.86
Amt Left: 3.6% $121,711.85
$4,642,822.42
Over/Under Est: 46.35% $1,470,495.28
Amt Left: 37.46% $1,265,124.27
Delta: -32.67% -$1,143,412.42

Bid Items & Bid Tabulations

64 Total 0 of 64
CALLAHAN  |  US 283  |  ABILENE  |  0437-04-034  |  06/02/2023  |  $3,172,327.14  |  BR 2023(912)  |  BRIDGE REPL  |  137 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PROJECT ALLIED RESOURCES, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
ALTUS CONSTRUCTION LLC
PREPARING ROW (TREE) (0" TO 6" DIA)
EA 22.000 $1,200.000 $923.000 $500.000 $1,972.910
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 14.000 $2,500.000 $2,260.000 $2,000.000 $1,972.910
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 2.000 $3,000.000 $3,560.000 $2,000.000 $1,972.910
REMOVING CONC (RIPRAP)
SY 852.000 $120.000 $30.600 $60.000 $15.780
EXCAVATION (ROADWAY)
CY 1,339.000 $30.000 $30.100 $45.000 $25.150
EXCAVATION (CHANNEL)
CY 1,650.000 $40.000 $36.200 $45.000 $39.460
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 12.000 $21.000 $110.000 $100.000 $197.290
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 3,819.000 $0.200 $0.570 $2.000 $1.360
VEGETATIVE WATERING
MG 25.000 $200.000 $74.000 $1.000 $197.290
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 3,819.000 $5.000 $2.950 $3.000 $2.450
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 356.000 $70.000 $113.000 $150.000 $50.000
PRIME COAT (MC-30)
GAL 788.000 $9.000 $20.900 $20.000 $4.750
ASPH (MULTI OPTION)
GAL 1,308.000 $8.000 $16.600 $20.000 $3.360
ASPH (AC-20-5TR)
GAL 1,135.000 $7.000 $14.200 $20.000 $3.620
AGGR(TY-B GR-3 SAC-B)
CY 14.000 $160.000 $418.000 $1,800.000 $154.200
AGGR(TY-B GR-4 SAC-B)
CY 39.000 $180.000 $1,350.000 $1,500.000 $110.900
CEM STABIL BKFL
CY 147.000 $370.000 $509.000 $300.000 $394.580
TEMPORARY SPL SHORING
SF 830.000 $55.000 $117.000 $85.000 $98.650
DRILL SHAFT (36 IN)
LF 438.000 $400.000 $451.000 $300.000 $1,035.650
CL C CONC (ABUT)(HPC)
CY 53.600 $2,600.000 $2,870.000 $2,800.000 $3,760.420
CL C CONC (CAP)(HPC)
CY 41.000 $2,700.000 $2,970.000 $2,800.000 $4,914.490
CL C CONC (COLUMN)(HPC)
CY 24.000 $2,760.000 $3,010.000 $2,800.000 $2,564.780
REINF CONC SLAB
SF 9,890.000 $38.000 $43.700 $55.000 $69.050
APPROACH SLAB
CY 70.600 $1,850.000 $1,280.000 $1,500.000 $1,381.040
PRESTR CONC GIRDER (TX28)
LF 1,281.000 $320.000 $223.000 $325.000 $442.360
SILICONE RESIN PAINT FINISH
SF 1,589.000 $18.000 $18.800 $10.000 $78.820
RIPRAP (STONE PROTECTION)(12 IN)
CY 603.000 $290.000 $342.000 $200.000 $352.690
RIPRAP (MOW STRIP)(4 IN)
CY 80.000 $700.000 $1,290.000 $700.000 $1,282.390
RAIL (TY SSTR)
LF 478.000 $165.000 $163.000 $200.000 $157.830
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 92.000 $280.000 $430.000 $200.000 $386.690
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $260,000.000 $232,000.000 $300,000.000 $155,859.740
MOBILIZATION
LS 1.000 $288,393.380 $384,000.000 $295,000.000 $443,904.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $12,000.000 $6,580.000 $22,000.000 $49,322.700
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 127.000 $45.000 $90.000 $1.000 $35.820
ROCK FILTER DAMS (REMOVE)
LF 127.000 $38.000 $23.300 $1.000 $8.570
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $34.000 $57.000 $1.000 $197.290
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $14.000 $13.800 $1.000 $19.730
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 958.000 $6.000 $10.700 $5.000 $3.900
BIODEG EROSN CONT LOGS (REMOVE)
LF 958.000 $3.500 $3.050 $1.000 $1.160
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 6.000 $6,500.000 $12,100.000 $6,000.000 $3,184.570
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 840.000 $120.000 $114.000 $100.000 $187.430
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 840.000 $15.000 $12.700 $50.000 $29.590
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 840.000 $21.000 $15.200 $50.000 $39.460
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $32.000 $37.000 $30.000 $50.310
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $3,110.000 $2,000.000 $4,143.110
REMOVE METAL BEAM GUARD FENCE
LF 383.000 $5.000 $3.110 $4.000 $3.950
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $300.000 $361.000 $500.000 $394.580
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,700.000 $4,450.000 $3,000.000 $6,855.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $360.000 $404.000 $500.000 $394.580
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,100.000 $1,660.000 $3,000.000 $4,932.270
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,500.000 $1,450.000 $1,000.000 $2,959.360
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $16,700.000 $12,000.000 $13,254.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $950.000 $1,950.000 $1,200.000 $1,471.790
REMOVE SM RD SN SUP&AM
EA 4.000 $140.000 $262.000 $500.000 $246.610
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $50.000 $79.000 $50.000 $49.320
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $40.000 $78.000 $50.000 $49.320
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 24.000 $10.000 $181.000 $25.000 $11.840
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 3,768.000 $0.970 $2.430 $4.000 $1.360
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 1,880.000 $3.000 $2.090 $3.000 $3.260
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 1,880.000 $1.000 $1.970 $3.000 $3.260
REFL PAV MRKR TY II-A-A
EA 24.000 $5.500 $144.000 $25.000 $15.780
ELIM EXT PAV MRK & MRKS (4")
LF 3,760.000 $1.000 $1.110 $2.000 $1.480
TMA (STATIONARY)
DAY 3.000 $260.000 $806.000 $200.000 $354.580
TMA (MOBILE OPERATION)
DAY 3.000 $400.000 $936.000 $200.000 $1,479.680
Totals: $3,172,327.140 $3,377,698.150 $3,499,410.000 $4,642,822.426