Show Job Controls
Bid Cobra

CALLAHAN IH 20 (0007-02-051)

Items: 45

County: CALLAHAN
Length: N/A
Highway: IH 20
District: ABILENE
Control Number: 0007-02-051
DBE Goal: 0.0%
Project: C 7-2-51
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $9,406,067.55
Date: 05/02/2024 (2 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
BRYCE TURENTINE
CHAD W CARTER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$9,406,067.55
$10,411,766.90
Over/Under Est: 10.69% $1,005,699.35
Subcontractor Percentage Amount
HJC FARMS, INC. 12.50% $1,305,782.11
FLAT LINE, INC. 2.57% $268,468.80
CHEROKEE SERVICES 0.84% $87,748.56
CONTRACTORS SERVICE, LTD. 0.36% $37,606.52
PROFESSIONAL TRAFFIC CONTROL LLC 0.21% $21,937.14
AWP SAFETY 0.20% $20,892.51
Total: 16.68% $1,742,435.64

Bid Items & Bid Tabulations

45 Total 0 of 45
CALLAHAN  |  IH 20  |  ABILENE  |  0007-02-051  |  05/02/2024  |  $9,406,067.55  |  C 7-2-51  |  PREVENT MAINT  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
BACKFILL (TY B)
STA 904.300 $230.000 $350.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 1,734.000 $65.000 $66.000
PLANE ASPH CONC PAV (1")
SY 402,940.000 $1.500 $1.600
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 2,791.000 $4.000 $6.250
DRILL SHAFT (SIGN MTS) (12 IN)
LF 35.000 $120.000 $210.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 52.000 $350.000 $270.000
RIPRAP (MOW STRIP)(4 IN)
CY 738.000 $750.000 $815.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 2,438.000 $55.000 $43.200
MOBILIZATION
LS 1.000 $700,000.000 $1,100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $15,000.000 $20,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,568.000 $8.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,568.000 $2.500 $2.000
RUMBLE STRIPS (SHOULDER)
LF 172,470.000 $0.250 $0.160
MTL W-BEAM GD FEN (TIM POST)
LF 12,075.000 $30.000 $28.200
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 49.000 $2,500.000 $2,820.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 12.000 $1,600.000 $2,600.000
REMOVE METAL BEAM GUARD FENCE
LF 11,700.000 $3.500 $2.200
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 12.000 $400.000 $360.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 49.000 $350.000 $360.000
GUARDRAIL END TREATMENT (INSTALL)
EA 45.000 $3,400.000 $3,960.000
GUARDRAIL END TREATMENT (REMOVE)
EA 45.000 $330.000 $300.000
ALUMINUM SIGNS (TY G)
SF 631.000 $36.500 $38.000
REPLACE EXISTING ALUMINUM SIGNS(TY G)
SF 503.000 $36.500 $38.000
INSTALL LRSS (STRUCT STEEL)
LB 3,424.800 $7.500 $11.700
REMOVE LRSA
EA 8.000 $1,850.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 85.000 $50.000 $104.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 70.000 $23.000 $72.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 22.000 $75.000 $108.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 235.000 $21.000 $54.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 207,374.000 $0.600 $0.360
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 186,760.000 $0.600 $0.360
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 12,156.000 $3.000 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 4,670.000 $3.000 $3.500
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 23,370.000 $0.850 $0.650
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 94,160.000 $0.850 $0.650
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 93,907.000 $0.950 $0.650
PREFAB PAV MRK TY C (W) (8") (SLD)
LF 9,157.000 $6.500 $1.500
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 2,122.000 $9.000 $9.600
REFL PAV MRKR TY II-C-R
EA 1,897.000 $5.500 $5.100
D-GR HMA TY-D SAC-B PG70-22
TON 8,789.100 $125.000 $140.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 24,609.300 $165.000 $185.000
TACK COAT
GAL 40,483.000 $5.500 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,000.000 $18,000.000
TMA (STATIONARY)
DAY 135.000 $250.000 $250.000
TMA (MOBILE OPERATION)
DAY 15.000 $500.000 $500.000
Totals: $9,406,067.550 $10,411,766.900