CALHOUN CR (0913-19-028)
Items: 36
County: CALHOUN
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-19-028
DBE Goal: N/A
Project: BR 2012(730)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $473,543.00
Date: 01/04/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$473,543.00 | |||
| $416,186.67 |
-12.11%
-$57,356.33
|
|||
| $421,834.00 |
-10.92%
-$51,709.00
|
1.36%
$5,647.33
|
||
| $474,995.42 |
0.31%
$1,452.42
|
14.13%
$58,808.75
|
-12.60%
-$53,161.42
|
|
| $477,816.43 |
0.9%
$4,273.43
|
14.81%
$61,629.76
|
-0.59%
-$2,821.01
|
|
| $496,272.00 |
4.8%
$22,729.00
|
19.24%
$80,085.33
|
-3.86%
-$18,455.57
|
|
| $529,878.13 |
11.9%
$56,335.13
|
27.32%
$113,691.46
|
-6.77%
-$33,606.13
|
|
| $694,266.00 |
46.61%
$220,723.00
|
66.82%
$278,079.33
|
-31.02%
-$164,387.87
|
E
Engineer's Estimate
$473,543.00
1
$416,186.67
Over/Under Est:
-12.11%
-$57,356.33
$421,834.00
Over/Under Est:
-10.92%
-$51,709.00
Amt Left:
1.36%
$5,647.33
$474,995.42
Over/Under Est:
0.31%
$1,452.42
Amt Left:
14.13%
$58,808.75
Delta:
-12.60%
-$53,161.42
$477,816.43
Over/Under Est:
0.9%
$4,273.43
Amt Left:
14.81%
$61,629.76
Delta:
-0.59%
-$2,821.01
$496,272.00
Over/Under Est:
4.8%
$22,729.00
Amt Left:
19.24%
$80,085.33
Delta:
-3.86%
-$18,455.57
$529,878.13
Over/Under Est:
11.9%
$56,335.13
Amt Left:
27.32%
$113,691.46
Delta:
-6.77%
-$33,606.13
$694,266.00
Over/Under Est:
46.61%
$220,723.00
Amt Left:
66.82%
$278,079.33
Delta:
-31.02%
-$164,387.87
Bid Items & Bid Tabulations
36
Total
0 of 36