BURNET RM1431 (6419-34-001)

Items: 9

County: BURNET
Length: N/A
Highway: RM1431
District: AUSTIN
Control Number: 6419-34-001
DBE Goal: N/A
Project: RMC - 641934001
Guaranty: N/A
Time: 32 W
Engineer's Estimate: $189,442.60
Date: 10/12/2022 (3 years ago)
Contract Number: N/A
Type: REMOVE AND REPLACE CURB AND GUTTER
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$189,442.60
$139,042.00
Over/Under Est: -26.6% -$50,400.60
Over/Under Est: 3.12% $5,906.40
Amt Left: 40.5% $56,307.00
Over/Under Est: 7.31% $13,844.40
Amt Left: 46.21% $64,245.00
Delta: -4.06% -$7,938.00
Over/Under Est: 13.11% $24,836.40
Amt Left: 54.11% $75,237.00
Delta: -5.41% -$10,992.00
Over/Under Est: 38.17% $72,317.40
Amt Left: 88.26% $122,718.00
Delta: -22.16% -$47,481.00
Over/Under Est: 89.3% $169,167.40
Amt Left: 157.91% $219,568.00
Delta: -37.00% -$96,850.00

Bid Items & Bid Tabulations

9 Total 0 of 9
BURNET  |  RM1431  |  AUSTIN  |  6419-34-001  |  10/12/2022  |  $189,442.60  |  RMC - 641934001  |  REMOVE AND REPLACE CURB AND GUTTER  |  32 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
DIGG COMMERCIAL, LLC
TALBRAN ENTERPRISES LLC
AARON CONCRETE CONTRACTORS, L.P.
AUSTIN UNDERGROUND INCORPORATED
COX COMMERCIAL CONSTRUCTION LLC
GARRET SHIELDS INFRASTRUCTURE
REMOVING CONC (CURB AND GUTTER)
LF 2,721.000 $10.000 $1.000 $17.000 $13.000 $15.000 $20.000 $40.000
MOBILIZATION
LS 1.000 $16,767.600 $50,000.000 $2,000.000 $20,000.000 $20,000.000 $25,000.000 $20,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $5,000.000 $5,000.000 $500.000 $1,500.000 $2,000.000 $10,000.000 $5,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $2.750 $5.000 $6.000 $10.000 $4.000 $10.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $1.500 $2.000 $3.000 $4.000 $1.500 $5.000 $2.000
CONC CURB & GUTTER (TY II)
LF 2,721.000 $40.000 $1.000 $36.000 $34.000 $34.000 $40.000 $70.000
D-GR HMA TY-B PG64-22
TON 158.000 $150.000 $50.000 $242.000 $300.000 $300.000 $250.000 $150.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 10.000 $75.000 $3,500.000 $400.000 $110.000 $500.000 $500.000 $200.000
TMA (STATIONARY)
DAY 10.000 $175.000 $3,000.000 $500.000 $250.000 $400.000 $750.000 $300.000
Totals: $189,442.600 $139,042.000 $195,349.000 $203,287.000 $214,279.000 $261,760.000 $358,610.000