BURNET SH 29 (0150-05-047)
Items: 89
County: BURNET
Length: N/A
Highway: SH 29
District: AUSTIN
Control Number: 0150-05-047
DBE Goal: N/A
Project: STP 1702(547)HES
Guaranty: N/A
Time: 97 WORKING DAYS
Engineer's Estimate: $1,047,034.43
Date: 07/11/2017 (8 years ago)
Contract Number: N/A
Type: INSTALL CONTINUOUS TURN LANE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,047,034.43 | |||
| $1,003,924.50 |
-4.12%
-$43,109.93
|
|||
| $1,090,448.17 |
4.15%
$43,413.74
|
8.62%
$86,523.67
|
||
| $1,136,921.66 |
8.58%
$89,887.23
|
13.25%
$132,997.16
|
-4.26%
-$46,473.49
|
|
| $1,169,741.25 |
11.72%
$122,706.82
|
16.52%
$165,816.75
|
-2.89%
-$32,819.59
|
|
| $1,199,827.24 |
14.59%
$152,792.81
|
19.51%
$195,902.74
|
-2.57%
-$30,085.99
|
|
| $1,235,574.90 |
18.01%
$188,540.47
|
23.07%
$231,650.40
|
-2.98%
-$35,747.66
|
|
| $1,278,142.42 |
22.07%
$231,107.99
|
27.31%
$274,217.92
|
-3.45%
-$42,567.52
|
|
| $1,654,509.40 |
58.02%
$607,474.97
|
64.8%
$650,584.90
|
-29.45%
-$376,366.98
|
|
| $1,792,072.10 |
71.16%
$745,037.67
|
78.51%
$788,147.60
|
-8.31%
-$137,562.70
|
E
Engineer's Estimate
$1,047,034.43
1
Awarded
$1,003,924.50
Over/Under Est:
-4.12%
-$43,109.93
$1,090,448.17
Over/Under Est:
4.15%
$43,413.74
Amt Left:
8.62%
$86,523.67
$1,136,921.66
Over/Under Est:
8.58%
$89,887.23
Amt Left:
13.25%
$132,997.16
Delta:
-4.26%
-$46,473.49
$1,169,741.25
Over/Under Est:
11.72%
$122,706.82
Amt Left:
16.52%
$165,816.75
Delta:
-2.89%
-$32,819.59
$1,199,827.24
Over/Under Est:
14.59%
$152,792.81
Amt Left:
19.51%
$195,902.74
Delta:
-2.57%
-$30,085.99
$1,235,574.90
Over/Under Est:
18.01%
$188,540.47
Amt Left:
23.07%
$231,650.40
Delta:
-2.98%
-$35,747.66
$1,278,142.42
Over/Under Est:
22.07%
$231,107.99
Amt Left:
27.31%
$274,217.92
Delta:
-3.45%
-$42,567.52
$1,654,509.40
Over/Under Est:
58.02%
$607,474.97
Amt Left:
64.8%
$650,584.90
Delta:
-29.45%
-$376,366.98
$1,792,072.10
Over/Under Est:
71.16%
$745,037.67
Amt Left:
78.51%
$788,147.60
Delta:
-8.31%
-$137,562.70
Bid Items & Bid Tabulations
89
Total
0 of 89