Show Job Controls
Bid Cobra

BURLESON CR (0917-30-057)

Items: 51

County: BURLESON
Length: N/A
Highway: CR
District: BRYAN
Control Number: 0917-30-057
DBE Goal: N/A
Project: BR 1702(439)
Guaranty: N/A
Time: 122 WORKING DAYS
Engineer's Estimate: $1,013,297.90
Date: 04/07/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$1,013,297.90
1
$1,449,786.48
Over/Under Est: 43.08% $436,488.58
Over/Under Est: 46.17% $467,865.75
Amt Left: 2.16% $31,377.17
Over/Under Est: 50.25% $509,228.34
Amt Left: 5.02% $72,739.76
Delta: -2.79% -$41,362.59
$1,560,898.50
Over/Under Est: 54.04% $547,600.60
Amt Left: 7.66% $111,112.02
Delta: -2.52% -$38,372.26
Subcontractor Percentage Amount
HEMPHILL WBE PILE DRIVING CO. 7.61% $111,788.01
HODGES AND SON CONSTRUCTION COMPANY, INC. 3.43% $50,385.40
LONESTAR TRAFFIC SAFETY, LLC 0.41% $6,022.74
TORO BRAVO CONSTRUCTION, LLC 0.20% $2,937.92
Total: 11.65% $171,134.07

Bid Items & Bid Tabulations

51 Total 0 of 51
BURLESON  |  CR  |  BRYAN  |  0917-30-057  |  04/07/2022  |  $1,013,297.90  |  BR 1702(439)  |  BRIDGE REPL  |  122 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TREVWAY, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
KNIFE RIVER CORPORATION - SOUTH
EARTH BUILDERS, L.P.
PREPARING ROW
STA 6.700 $9,000.000 $2,000.000 $10,000.000 $15,500.000 $12,500.000
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 8.000 $1,000.000 $1,400.000 $3,000.000 $10.000 $5,000.000
EXCAVATION (ROADWAY)
CY 254.000 $10.000 $17.860 $50.000 $30.000 $20.000
EXCAVATION (CHANNEL)
CY 218.000 $10.000 $20.800 $50.000 $72.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 236.000 $15.000 $47.470 $50.000 $47.000 $40.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,019.000 $1.000 $11.460 $8.000 $10.000 $2.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 1,019.000 $0.200 $5.140 $4.000 $2.200 $0.500
CELL FBR MLCH SEED(TEMP)(WARM)
SY 510.000 $0.200 $4.620 $4.000 $2.200 $0.500
CELL FBR MLCH SEED(TEMP)(COOL)
SY 510.000 $0.200 $4.620 $4.000 $2.200 $0.500
VEGETATIVE WATERING
MG 10.200 $100.000 $200.000 $1.000 $50.000 $100.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 1,473.000 $25.000 $41.000 $45.000 $25.000 $50.000
CEM STABIL BKFL
CY 157.000 $100.000 $200.000 $250.000 $154.000 $300.000
SHEET PILING (PZ - 27)
SF 3,146.000 $70.000 $105.410 $95.000 $91.630 $120.000
DRILL SHAFT (24 IN)
LF 210.000 $70.000 $370.000 $260.000 $359.000 $400.000
CL C CONC (ABUT)
CY 63.100 $925.000 $600.000 $1,500.000 $1,605.000 $1,500.000
REINF CONC SLAB (BOX BEAM)
SF 1,570.000 $20.000 $25.000 $28.000 $52.700 $20.000
REINF CONC SLAB (SLAB BEAM)
SF 1,300.000 $20.000 $25.000 $28.000 $37.400 $20.000
SHEAR KEY
CY 8.000 $350.000 $372.000 $1,000.000 $500.000 $1,500.000
PRESTR CONC BOX BEAM (4B20)
LF 237.910 $210.000 $277.000 $355.000 $291.000 $300.000
PRESTR CONC BOX BEAM (5B20)
LF 118.950 $210.000 $287.000 $355.000 $375.500 $300.000
PRESTR CONC SLAB BEAM (5SB15)
LF 247.110 $350.000 $266.000 $365.000 $293.000 $300.000
RIPRAP (CONC)(4 IN)
CY 14.000 $460.000 $400.000 $600.000 $800.000 $800.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 444.000 $125.000 $255.000 $135.000 $180.000 $150.000
RAIL (TY T223)
LF 181.000 $110.000 $159.720 $135.000 $189.000 $150.000
RAIL (TY T631)
LF 188.000 $80.000 $191.000 $100.000 $105.000 $125.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $20,000.000 $25,000.000 $20,000.000 $21,300.000 $25,000.000
REMOV STR (SMALL FENCE)
LF 147.000 $32.000 $8.730 $50.000 $3.000 $5.000
REMOVE STR (RAIL)
LF 60.000 $32.000 $78.000 $5.000 $22.000 $25.000
MOBILIZATION
LS 1.000 $92,000.000 $140,000.000 $125,000.000 $215,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $5,500.000 $1,000.000 $5,000.000 $1,370.000 $2,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 83.000 $35.000 $25.000 $30.000 $39.000 $35.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 54.000 $55.000 $25.000 $30.000 $72.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 137.000 $10.000 $9.000 $20.000 $16.600 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 805.000 $5.000 $2.000 $5.000 $4.400 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 805.000 $1.500 $1.590 $2.000 $1.000 $1.000
CONSTRUCTING DETOURS
SY 199.000 $60.000 $500.000 $200.000 $67.000 $150.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 20.000 $35.000 $196.000 $250.000 $131.000 $60.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $50.000 $196.000 $250.000 $131.000 $60.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 20.000 $10.000 $63.000 $250.000 $45.000 $30.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $10.000 $87.000 $250.000 $25.000 $30.000
MTL W-BEAM GD FEN (TIM POST)
LF 350.000 $25.000 $30.450 $28.000 $32.000 $30.000
MTL BEAM GD FEN TRANS (TL2)
EA 3.000 $1,400.000 $1,690.000 $1,500.000 $1,500.000 $2,500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,500.000 $3,593.000 $1,500.000 $1,805.000 $1,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,600.000 $3,000.000 $3,500.000 $3,400.000 $4,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 1.000 $20,000.000 $34,000.000 $24,000.000 $22,200.000 $27,500.000
WIRE FENCE (TY A)
LF 114.000 $20.000 $40.000 $20.000 $14.000 $20.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 8.000 $650.000 $1,200.000 $800.000 $650.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 4.000 $100.000 $100.000 $100.000 $100.000 $150.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 2.000 $24.000 $28.000 $30.000 $28.000 $50.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 10.000 $24.000 $28.000 $30.000 $28.000 $50.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $100.000 $315.000 $200.000 $110.000 $500.000
Totals: $1,013,297.900 $1,449,786.480 $1,481,163.650 $1,522,526.245 $1,560,898.500