BROWN US0084 (6350-81-001)

Items: 13

County: BROWN
Length: N/A
Highway: US0084
District: BROWNWOOD
Control Number: 6350-81-001
DBE Goal: N/A
Project: RMC - 635081001
Guaranty: N/A
Time: 45 W
Engineer's Estimate: $1,983,782.56
Date: 02/06/2020 (6 years ago)
Contract Number: N/A
Type: MILL & INLAY (CALL-OUT)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,983,782.56
$1,576,676.90
Over/Under Est: -20.52% -$407,105.66
Over/Under Est: 0.33% $6,514.74
Amt Left: 26.23% $413,620.40
Over/Under Est: 6.86% $135,988.44
Amt Left: 34.45% $543,094.10
Delta: -6.51% -$129,473.70
Over/Under Est: 15.33% $304,176.44
Amt Left: 45.11% $711,282.10
Delta: -7.93% -$168,188.00
Over/Under Est: 151.41% $3,003,720.44
Amt Left: 216.33% $3,410,826.10
Delta: -117.99% -$2,699,544.00

Bid Items & Bid Tabulations

13 Total 0 of 13
BROWN  |  US0084  |  BROWNWOOD  |  6350-81-001  |  02/06/2020  |  $1,983,782.56  |  RMC - 635081001  |  MILL & INLAY (CALL-OUT)  |  45 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
BICK'S CONSTRUCTION, INC.
LONE STAR PAVING COMPANY
BIG CREEK CONSTRUCTION, LTD.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
D-GR HMA TY-B PG64-22
TON 13,300.000 $112.000 $91.650 $112.000 $103.000 $135.000 $295.000
PLAN & TEXT ASPH CONC PAV(0" TO 6")
SY 39,581.000 $6.300 $6.200 $6.800 $8.000 $6.000 $5.000
MOBILIZATION
LS 1.000 $179,435.000 $39,000.000 $136,862.000 $250,000.000 $188,000.000 $450,000.000
MOBILIZATION (CALLOUT)
EA 1.000 $10,000.000 $5,500.000 $18,000.000 $63,000.000 $15,000.000 $60,000.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,775.000 $1.060 $0.900 $1.500 $1.000 $1.000 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,548.000 $0.870 $0.900 $1.500 $1.000 $1.000 $1.000
TMA (STATIONARY)
DAY 60.000 $238.000 $205.000 $200.000 $125.000 $250.000 $500.000
LANE CLOSURE (SETUP AND REMOV)(TY 1)
EA 12.000 $741.000 $795.000 $100.000 $1,500.000 $250.000 $5,000.000
LANE CLOSURE (SETUP AND REMOV)(TY 3)
EA 17.000 $603.000 $695.000 $100.000 $1,800.000 $250.000 $5,000.000
LANE CLOSURE (MAINTENANCE) (TY 1)
HR 96.000 $60.000 $110.000 $205.000 $150.000 $50.000 $500.000
LANE CLOSURE (MAINTENANCE) (TY 3)
HR 96.000 $48.000 $110.000 $205.000 $150.000 $50.000 $500.000
LANE CLOSURE (SETUP AND REMOV)(TY 22)
HR 72.000 $49.000 $42.000 $109.000 $200.000 $50.000 $500.000
LANE CLOSURE (SETUP AND REMOV)(TY 23)
HR 88.000 $55.000 $80.000 $109.000 $200.000 $150.000 $500.000
Totals: $1,983,782.560 $1,576,676.900 $1,990,297.300 $2,119,771.000 $2,287,959.000 $4,987,503.000