BROOKS US 281 (0255-04-101)

Items: 12

County: BROOKS
Length: N/A
Highway: US 281
District: PHARR
Control Number: 0255-04-101
DBE Goal: N/A
Project: F 2B23(060)
Guaranty: N/A
Time: 128 WORKING DAYS
Engineer's Estimate: $753,202.50
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
FRANCISCO J CANTU
DANNY FLORES
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$753,202.50
$660,180.00
Over/Under Est: -12.35% -$93,022.50
Over/Under Est: 6.64% $50,006.30
Amt Left: 21.67% $143,028.80

Bid Items & Bid Tabulations

12 Total 0 of 12
BROOKS  |  US 281  |  PHARR  |  0255-04-101  |  08/02/2023  |  $753,202.50  |  F 2B23(060)  |  HAZARD ELIM & SAFETY  |  128 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MASSANA CONSTRUCTION INC.
SCR CIVIL CONSTRUCTION, LLC
RIPRAP (MOW STRIP)(4 IN)
CY 482.000 $559.000 $400.000 $656.000
MOBILIZATION
LS 1.000 $70,000.000 $94,092.000 $78,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $8,000.000 $3,500.000 $6,000.000
FRNT END LOADER WORK (ERSN & SEDM CONT)
HR 2.000 $131.000 $225.000 $100.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,880.000 $4.500 $5.000 $5.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,880.000 $1.500 $1.400 $1.550
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,880.000 $5.500 $7.000 $6.600
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,880.000 $2.500 $1.500 $1.550
CABLE BARRIER SYSTEM (TL-4)
LF 12,085.500 $15.000 $12.000 $17.600
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 18.000 $4,050.000 $7,500.000 $3,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $8,500.000 $2,500.000 $4,900.000
TMA (MOBILE OPERATION)
DAY 140.000 $150.000 $85.000 $200.000
Totals: $753,202.500 $660,180.000 $803,208.800