Show Job Controls
Bid Cobra

BREWSTER US 67 (0021-01-053)

Items: 67

County: BREWSTER
Length: N/A
Highway: US 67
District: EL PASO
Control Number: 0021-01-053
DBE Goal: N/A
Project: NH 2017(324)
Guaranty: N/A
Time: 140 WORKING DAYS
Engineer's Estimate: $4,287,971.83
Date: 01/04/2017 (9 years ago)
Contract Number: N/A
Type: ROADWAY REHABILITATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$4,287,971.83
$4,010,557.70
Over/Under Est: -6.47% -$277,414.13
$4,766,686.79
Over/Under Est: 11.16% $478,714.96
Amt Left: 18.85% $756,129.09
$4,934,981.16
Over/Under Est: 15.09% $647,009.33
Amt Left: 23.05% $924,423.46
Delta: -3.53% -$168,294.37
$5,014,384.52
Over/Under Est: 16.94% $726,412.69
Amt Left: 25.03% $1,003,826.82
Delta: -1.61% -$79,403.36
$5,227,376.03
Over/Under Est: 21.91% $939,404.20
Amt Left: 30.34% $1,216,818.33
Delta: -4.25% -$212,991.51
Over/Under Est: 25.82% $1,107,224.96
Amt Left: 34.52% $1,384,639.09
Delta: -3.21% -$167,820.76

Bid Items & Bid Tabulations

67 Total 0 of 67
BREWSTER  |  US 67  |  EL PASO  |  0021-01-053  |  01/04/2017  |  $4,287,971.83  |  NH 2017(324)  |  ROADWAY REHAB  |  140 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
REECE ALBERT, INC.
GILVIN-TERRILL, LTD.
ALLEN KELLER COMPANY
FNF CONSTRUCTION, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
REMOVING CONC (RIPRAP)
SY 1,500.000 $11.000 $11.000 $38.440 $10.000 $27.000 $19.000 $10.660
REMOVING CONC (CURB)
LF 15,085.000 $3.000 $1.300 $0.800 $3.000 $6.000 $7.000 $4.220
REMOVING CONC (FLUME)
SY 193.000 $18.000 $11.000 $13.490 $75.000 $40.000 $76.500 $27.120
EXCAVATION (CHANNEL)
CY 5,643.000 $15.000 $20.000 $26.040 $15.000 $10.000 $8.500 $22.640
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 4,309.000 $20.000 $30.000 $49.720 $60.000 $17.000 $7.750 $45.930
BACKFILLING PAVEMENT EDGES
CY 280.000 $50.000 $40.000 $17.500 $100.000 $32.000 $86.000 $25.390
BLADING
HR 80.000 $130.000 $100.000 $162.620 $100.000 $250.000 $145.000 $177.720
BULLDOZER WORK
HR 160.000 $55.000 $120.000 $172.930 $150.000 $235.000 $141.000 $210.720
FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS
CY 120.000 $232.000 $45.000 $45.200 $180.000 $95.000 $65.000 $124.680
CEMENT
TON 679.000 $185.000 $180.000 $201.090 $180.000 $275.000 $200.000 $214.920
CEMENT TREAT (EXIST MATL) (6")
SY 215,696.000 $1.800 $1.700 $2.430 $3.600 $2.020 $3.880 $1.720
PRIME COAT (MC-30)
GAL 43,302.000 $4.000 $4.000 $3.980 $4.000 $5.000 $4.450 $3.970
ASPH (TIER I)
GAL 155,799.000 $3.250 $2.800 $3.390 $2.600 $3.600 $2.700 $2.800
AGGR(TY-PB GR-4 SAC-A)
CY 1,973.000 $100.000 $120.000 $107.010 $100.000 $103.000 $127.000 $197.210
AGGR (TY-B GR-3)
CY 2,402.000 $90.000 $110.000 $71.210 $70.000 $164.000 $120.000 $135.600
FLOWABLE BACKFILL
CY 10.000 $140.830 $200.000 $517.430 $100.000 $212.000 $220.000 $181.290
TRENCH EXCAVATION PROTECTION
LF 100.000 $3.470 $50.000 $429.950 $100.000 $3.200 $97.000 $22.850
SHEET PILING (PZC - 18)
SF 10,096.000 $55.000 $35.000 $35.290 $42.000 $43.000 $45.700 $38.560
CL A CONC (FLUME)
CY 22.000 $1,120.000 $800.000 $1,147.600 $1,500.000 $850.000 $1,100.000 $1,183.220
CL C CONC (WINGWALLS)
CY 58.000 $1,040.340 $1,200.000 $1,633.490 $1,000.000 $1,200.000 $1,700.000 $2,201.110
CL C CONC (RETAINING WALL)
CY 90.000 $1,033.470 $1,200.000 $1,076.660 $1,000.000 $1,300.000 $2,110.000 $2,287.140
RIPRAP (CONC)(5 IN)
CY 24.000 $433.480 $600.000 $585.240 $1,000.000 $640.000 $870.000 $1,053.660
RIPRAP CONC (8 IN)
CY 480.000 $600.000 $600.000 $839.880 $1,000.000 $830.000 $720.000 $545.350
RIPRAP (CONC)(DISSIPATER)
CY 77.000 $1,500.000 $850.000 $1,474.780 $1,250.000 $640.000 $1,200.000 $1,335.530
RIPRAP (MOW STRIP)(4 IN)
CY 176.000 $700.000 $650.000 $491.960 $500.000 $480.000 $390.000 $459.050
RETROFIT RAIL (TY T552)(HPC)
LF 386.000 $100.000 $100.000 $202.250 $150.000 $200.000 $172.000 $255.010
RETROFIT RAIL (TY T631)
LF 826.000 $110.000 $60.000 $103.860 $80.000 $90.000 $162.000 $110.110
MOBILIZATION
LS 1.000 $315,000.000 $335,000.000 $464,861.390 $490,000.000 $320,000.000 $520,367.880 $907,700.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $15,000.000 $20,000.000 $25,688.250 $16,400.000 $36,000.000 $5,000.000 $7,350.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 300.000 $47.450 $18.000 $33.460 $40.000 $80.000 $57.000 $36.410
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 20.000 $23.550 $60.000 $24.070 $100.000 $125.000 $58.000 $57.770
CONSTRUCTION EXITS (REMOVE)
SY 20.000 $7.040 $20.000 $3.180 $35.000 $53.000 $12.000 $21.020
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 320.000 $5.000 $5.000 $9.190 $6.000 $10.600 $6.000 $12.930
BIODEG EROSN CONT LOGS (REMOVE)
LF 320.000 $2.000 $1.500 $2.130 $2.000 $2.100 $3.000 $2.950
CONSTRUCTING DETOURS
SY 362.000 $28.240 $50.000 $18.860 $45.000 $58.000 $28.000 $97.960
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 7.000 $4,000.000 $5,500.000 $799.020 $5,000.000 $8,400.000 $2,000.000 $5,985.860
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 2,110.000 $10.000 $6.000 $13.690 $15.000 $25.500 $12.000 $14.850
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 2,110.000 $10.000 $6.000 $13.690 $15.000 $25.500 $12.000 $14.230
CONC CURB (MONO) (TY II)
LF 15,085.000 $10.000 $8.000 $6.560 $10.000 $13.300 $21.000 $12.750
INTRSCT, DRVWAYS, & TURNOUT(SURF TREAT)
SY 2,032.000 $30.000 $28.000 $34.080 $10.000 $28.400 $10.000 $24.310
MTL W-BEAM GD FEN (TIM POST)
LF 2,598.000 $20.000 $22.000 $20.220 $19.000 $20.000 $21.000 $26.660
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,945.000 $1,650.000 $1,585.200 $1,900.000 $2,000.000 $2,100.000 $1,916.360
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 226.000 $45.000 $55.000 $60.130 $51.000 $58.000 $60.000 $53.430
REMOVE METAL BEAM GUARD FENCE
LF 470.000 $3.150 $2.000 $1.910 $2.500 $2.600 $3.000 $2.320
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $255.000 $155.000 $147.590 $300.000 $320.000 $310.000 $288.860
GUARDRAIL END TREATMENT (INSTALL)
EA 28.000 $2,370.000 $1,400.000 $2,432.460 $2,400.000 $2,550.000 $2,500.000 $2,362.710
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $420.000 $200.000 $218.650 $300.000 $320.000 $320.000 $538.180
CRASH CUSH ATTEN (INSTL)
EA 4.000 $12,370.000 $6,500.000 $10,338.550 $10,200.000 $10,800.000 $15,000.000 $13,466.360
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $1,600.000 $1,200.000 $1,596.100 $3,000.000 $3,200.000 $300.000 $1,916.360
CRASH CUSH ATTEN (STKPL)
EA 4.000 $1,500.000 $900.000 $714.820 $1,500.000 $1,600.000 $400.000 $2,021.360
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $540.000 $600.000 $601.280 $1,000.000 $1,060.000 $1,100.000 $535.340
REMOVE SM RD SN SUP&AM
EA 2.000 $165.000 $50.000 $80.660 $200.000 $210.000 $210.000 $168.040
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 200.000 $0.450 $1.200 $0.210 $13.000 $14.000 $4.000 $4.730
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 400.000 $0.500 $1.200 $0.210 $13.000 $14.000 $4.000 $4.460
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 465.000 $0.750 $2.000 $1.560 $1.000 $1.100 $2.500 $1.970
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,915.000 $1.000 $2.000 $1.600 $1.000 $1.100 $2.500 $1.220
REFL PAV MRK TY II (W) 4" (BRK)
LF 1,551.000 $0.140 $0.200 $0.210 $0.190 $0.200 $0.180 $0.220
REFL PAV MRK TY II (W) 4" (SLD)
LF 83,759.000 $0.100 $0.200 $0.210 $0.190 $0.200 $0.180 $0.160
REFL PAV MRK TY II (W) 8" (SLD)
LF 100.000 $0.280 $0.300 $0.420 $0.380 $0.400 $0.350 $1.420
REFL PAV MRK TY II (W) (ARROW)
EA 2.000 $38.000 $25.000 $60.130 $55.000 $60.000 $30.000 $178.710
REFL PAV MRK TY II (Y) 4" (BRK)
LF 8,446.000 $0.120 $0.200 $0.210 $0.190 $0.200 $0.180 $0.160
REFL PAV MRK TY II (Y) 4" (SLD)
LF 28,608.000 $0.100 $0.200 $0.210 $0.190 $0.200 $0.180 $0.160
REFL PAV MRK TY II (Y) 24" (SLD)
LF 803.000 $1.300 $2.000 $2.730 $2.500 $3.000 $2.000 $4.330
REFL PAV MRKR TY I-C
EA 131.000 $2.750 $2.500 $4.370 $4.000 $4.200 $3.000 $3.950
REFL PAV MRKR TY II-A-A
EA 977.000 $2.500 $2.500 $3.830 $3.500 $3.700 $3.000 $3.260
ELIM EXT PAV MRK & MRKS (4")
LF 530.000 $0.250 $0.500 $0.640 $1.400 $1.500 $0.500 $1.250
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $13,000.000 $12,000.000 $1,398.280 $6,000.000 $10,000.000 $22,500.000 $17,433.000
Totals: $4,287,971.830 $4,010,557.700 $4,766,686.790 $4,934,981.160 $5,014,384.520 $5,227,376.030 $5,395,196.790