Bid Cobra

BRAZOS US0190 (6451-57-001)

Items: 34

County: BRAZOS
Length: N/A
Highway: US0190
District: BRYAN
Control Number: 6451-57-001
DBE Goal: 0.0%
Project: RMC - 645157001
Guaranty: N/A
Time: 44 W
Engineer's Estimate: $5,296,202.92
Date: 05/02/2024 (2 years ago)
Contract Number: N/A
Type: MILL AND INLAY
Mail/Deliver Bids To: N/A
MATTHEW DAWSONMATHUR
MICHAEL ESTILLETTE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$5,296,202.92
$4,330,955.33
Over/Under Est: -18.23% -$965,247.59
Over/Under Est: -13.19% -$698,601.17
Amt Left: 6.16% $266,646.42
Over/Under Est: -1.09% -$57,672.97
Amt Left: 20.96% $907,574.62
Delta: -13.94% -$640,928.20
Over/Under Est: 1.22% $64,640.54
Amt Left: 23.78% $1,029,888.13
Delta: -2.33% -$122,313.51
$5,470,533.69
Over/Under Est: 3.29% $174,330.77
Amt Left: 26.31% $1,139,578.36
Delta: -2.05% -$109,690.23
$7,304,700.40
Over/Under Est: 37.92% $2,008,497.48
Amt Left: 68.66% $2,973,745.07
Delta: -33.53% -$1,834,166.71
Subcontractor Percentage Amount
CEN-TEX SEEDING, INC. 0.00% $0.00
PROFESSIONAL TRAFFIC CONTROL LLC 0.00% $0.00
STRIPE LINES, INC. 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

34 Total 0 of 34
BRAZOS  |  US0190  |  BRYAN  |  6451-57-001  |  05/02/2024  |  $5,296,202.92  |  RMC - 645157001  |  MILL AND INLAY  |  44 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
BRAZOS PAVING, INC.
FNH CONSTRUCTION, LLC
BACKFILL (TY A OR B)
STA 319.070 $356.000 $166.000 $415.000 $300.000 $595.000 $1,260.000 $450.000
PLANE ASPH CONC PAV(0" TO 2")
SY 8,890.000 $5.320 $9.300 $2.660 $3.000 $4.100 $4.250 $10.000
PLANE ASPH CONC PAV (2")
SY 21,270.000 $11.180 $2.450 $2.660 $3.500 $1.000 $6.650 $10.000
MOBILIZATION
LS 1.000 $119,073.960 $67,220.000 $250,000.000 $500,000.000 $175,500.000 $93,000.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $6,858.960 $9,688.000 $5,000.000 $5,000.000 $2,200.000 $15,000.000 $20,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $4.160 $5.000 $5.000 $4.000 $2.700 $6.100 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $1.450 $2.000 $2.000 $1.000 $2.700 $2.450 $2.000
INTERSECTIONS (ACP)
SY 5,855.000 $62.570 $32.500 $31.000 $36.000 $40.000 $30.500 $45.000
DRIVEWAYS (ACP)
SY 320.000 $88.250 $276.000 $60.150 $36.000 $175.400 $37.200 $45.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 64,174.000 $0.630 $0.060 $0.060 $0.300 $0.250 $0.150 $1.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 1,021.500 $0.490 $0.400 $0.380 $0.320 $0.400 $0.500 $3.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 47,726.000 $0.750 $0.400 $0.380 $0.320 $0.400 $0.500 $3.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 7,677.000 $0.660 $0.400 $0.380 $0.320 $0.400 $0.500 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 4,308.000 $1.730 $2.000 $1.000 $2.000 $2.000 $1.850 $5.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 12,264.000 $1.900 $1.200 $1.090 $1.000 $1.100 $2.000 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 48.000 $14.360 $8.700 $7.810 $7.000 $8.000 $9.750 $20.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 106.000 $93.580 $110.000 $99.200 $40.000 $100.000 $53.750 $500.000
PAVEMENT SEALER 6"
LF 6,040.000 $0.690 $0.250 $0.200 $0.200 $0.200 $0.070 $3.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 8,910.000 $0.980 $0.900 $0.810 $0.650 $0.850 $0.850 $3.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 35,462.000 $1.440 $0.900 $0.810 $0.650 $0.850 $0.850 $3.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 35,088.000 $1.530 $0.900 $0.810 $0.650 $0.850 $0.850 $3.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 30.000 $266.630 $286.000 $258.000 $275.000 $260.000 $370.000 $250.000
PREFAB PAV MRK TY C (W) (WORD)
EA 30.000 $327.010 $305.000 $275.000 $320.000 $280.000 $450.000 $500.000
REFL PAV MRKR TY II-C-R
EA 445.000 $6.530 $8.000 $7.200 $7.000 $7.200 $7.350 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 6,040.000 $1.100 $0.500 $0.450 $1.000 $0.470 $0.750 $3.000
PAV SURF PREP FOR MRK (6")
LF 6,040.000 $0.190 $0.250 $0.220 $0.100 $0.230 $0.020 $3.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 17,914.380 $161.560 $138.000 $146.500 $165.000 $174.000 $175.400 $200.000
TACK COAT
GAL 16,285.800 $4.200 $4.200 $3.500 $4.000 $4.200 $5.200 $8.000
TOM-F PG76-22 SAC-A
TON 6,187.793 $159.880 $155.000 $165.000 $170.000 $193.000 $162.600 $200.000
TACK COAT
GAL 14,995.800 $7.160 $4.200 $3.500 $4.000 $4.250 $5.800 $8.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,857.890 $6,200.000 $5,000.000 $5,000.000 $5,000.000 $21,990.000 $16,500.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 108.000 $15.330 $15.000 $14.000 $30.000 $21.430 $28.100 $20.000
TMA (STATIONARY)
DAY 38.000 $324.530 $580.000 $150.000 $250.000 $400.000 $240.000 $250.000
TMA (MOBILE OPERATION)
DAY 6.000 $356.890 $900.000 $150.000 $500.000 $512.000 $570.000 $550.000
Totals: $5,296,202.921 $4,330,955.335 $4,597,601.755 $5,238,529.950 $5,360,843.469 $5,470,533.694 $7,304,700.400