Show Job Controls
Bid Cobra

BRAZOS SH0006 (6350-18-001)

Items: 11

County: BRAZOS
Length: N/A
Highway: SH0006
District: BRYAN
Control Number: 6350-18-001
DBE Goal: N/A
Project: BPM - 635018001
Guaranty: N/A
Time: 8 W
Engineer's Estimate: $108,806.00
Date: 10/08/2019 (6 years ago)
Contract Number: N/A
Type: STONE RIP RAP AND SCOUR COUNTERMEASURES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$108,806.00
Over/Under Est: 15.6% $16,971.00
Over/Under Est: 39.57% $43,054.00
Amt Left: 20.74% $26,083.00
Over/Under Est: 43% $46,784.00
Amt Left: 23.7% $29,813.00
Delta: -2.46% -$3,730.00
Over/Under Est: 45.95% $49,991.87
Amt Left: 26.25% $33,020.87
Delta: -2.06% -$3,207.87
Over/Under Est: 71.86% $78,183.00
Amt Left: 48.67% $61,212.00
Delta: -17.75% -$28,191.13
Over/Under Est: 79.99% $87,039.00
Amt Left: 55.71% $70,068.00
Delta: -4.74% -$8,856.00

Bid Items & Bid Tabulations

11 Total 0 of 11
BRAZOS  |  SH0006  |  BRYAN  |  6350-18-001  |  10/08/2019  |  $108,806.00  |  BPM - 635018001  |  STONE RIP RAP AND SCOUR COUNTERMEASU...  |  8 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
SKILLED CONSTRUCTION SUBS UNLIMITED LLC
CHAMPION INFRASTRUCTURE, LLC
FNH CONSTRUCTION, LLC
FUQUA CONSTRUCTION CO., INC.
KNIFE RIVER CORPORATION - SOUTH
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
PREPARING ROW
AC 1.000 $3,000.000 $1,900.000 $3,500.000 $15,000.000 $9,000.000 $24,300.000 $8,505.000
REMOVING CONC (RIPRAP)
SY 155.000 $25.000 $26.000 $40.000 $100.000 $27.000 $59.000 $60.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 102.000 $150.000 $40.000 $150.000 $85.000 $75.000 $310.000 $108.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 352.000 $150.000 $230.000 $260.000 $185.000 $232.288 $188.000 $269.000
RIPRAP (STONE COMMON)(GROUT)(12 IN)
CY 52.000 $250.000 $206.000 $320.000 $200.000 $187.500 $244.000 $525.000
MOBILIZATION
LS 1.000 $5,181.000 $7,195.000 $5,000.000 $15,000.000 $23,400.000 $16,800.000 $21,488.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $2,000.000 $5,500.000 $2,500.000 $8,500.000 $6,247.500 $4,900.000 $3,412.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 250.000 $35.000 $30.000 $20.000 $40.000 $30.000 $68.000 $46.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $3.500 $2.000 $5.000 $4.000 $6.000 $3.720 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $1.500 $1.000 $1.000 $2.000 $3.000 $1.000 $1.000
TMA (STATIONARY)
DAY 8.000 $300.000 $300.000 $400.000 $550.000 $600.000 $250.000 $892.000
Totals: $108,806.000 $125,777.000 $151,860.000 $155,590.000 $158,797.876 $186,989.000 $195,845.000