BRAZOS FM 1179 (1316-01-081)
Items: 73
County: BRAZOS
Length: N/A
Highway: FM 1179
District: BRYAN
Control Number: 1316-01-081
DBE Goal: N/A
Project: STP 2022(731)TAPS
Guaranty: N/A
Time: 223 WORKING DAYS
Engineer's Estimate: $4,124,936.15
Date: 06/27/2023 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
JAMES ROBBINS
JOSEPH GREIVE
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,124,936.15 | |||
| $4,034,958.95 |
-2.18%
-$89,977.20
|
|||
| $4,592,733.12 |
11.34%
$467,796.97
|
13.82%
$557,774.17
|
||
| $4,802,969.00 |
16.44%
$678,032.85
|
19.03%
$768,010.05
|
-4.58%
-$210,235.88
|
|
| $4,881,458.12 |
18.34%
$756,521.97
|
20.98%
$846,499.17
|
-1.63%
-$78,489.12
|
|
| $5,399,603.20 |
30.9%
$1,274,667.05
|
33.82%
$1,364,644.25
|
-10.61%
-$518,145.08
|
|
| $5,473,921.04 |
32.7%
$1,348,984.89
|
35.66%
$1,438,962.09
|
-1.38%
-$74,317.84
|
|
| $5,650,686.00 |
36.99%
$1,525,749.85
|
40.04%
$1,615,727.05
|
-3.23%
-$176,764.96
|
|
| $5,964,743.14 |
44.6%
$1,839,806.99
|
47.83%
$1,929,784.19
|
-5.56%
-$314,057.14
|
|
| $5,994,954.45 |
45.33%
$1,870,018.30
|
48.58%
$1,959,995.50
|
-0.51%
-$30,211.31
|
E
Engineer's Estimate
$4,124,936.15
1
Awarded
$4,034,958.95
Over/Under Est:
-2.18%
-$89,977.20
$4,592,733.12
Over/Under Est:
11.34%
$467,796.97
Amt Left:
13.82%
$557,774.17
$4,802,969.00
Over/Under Est:
16.44%
$678,032.85
Amt Left:
19.03%
$768,010.05
Delta:
-4.58%
-$210,235.88
$4,881,458.12
Over/Under Est:
18.34%
$756,521.97
Amt Left:
20.98%
$846,499.17
Delta:
-1.63%
-$78,489.12
$5,399,603.20
Over/Under Est:
30.9%
$1,274,667.05
Amt Left:
33.82%
$1,364,644.25
Delta:
-10.61%
-$518,145.08
$5,473,921.04
Over/Under Est:
32.7%
$1,348,984.89
Amt Left:
35.66%
$1,438,962.09
Delta:
-1.38%
-$74,317.84
$5,650,686.00
Over/Under Est:
36.99%
$1,525,749.85
Amt Left:
40.04%
$1,615,727.05
Delta:
-3.23%
-$176,764.96
$5,964,743.14
Over/Under Est:
44.6%
$1,839,806.99
Amt Left:
47.83%
$1,929,784.19
Delta:
-5.56%
-$314,057.14
$5,994,954.45
Over/Under Est:
45.33%
$1,870,018.30
Amt Left:
48.58%
$1,959,995.50
Delta:
-0.51%
-$30,211.31
| Subcontractor | Percentage | Amount |
|---|---|---|
| BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. | 13.87% | $596,109.75 |
| QMF STEEL, INC. | 2.23% | $95,841.73 |
| CEN-TREE SOLUTIONS LLC | 1.38% | $59,310.13 |
| CEN TEX HYDROSEED, INC. | 1.26% | $54,152.72 |
| TRP CONSTRUCTION GROUP, LLC | 0.82% | $35,242.25 |
| KING GEORGE TRAFFIC SOLUTIONS LLC | 0.65% | $27,935.93 |
| HIGHWAY TRAFFIC CONTROL & SERVICES, LLC | 0.55% | $23,638.09 |
| Total: | 20.76% | $892,230.60 |
Bid Items & Bid Tabulations
73
Total
0 of 73