BRAZOS HOLLEMAN DR (0917-29-148)
Items: 43
County: BRAZOS
Length: 0.0000 MILES
Highway: HOLLEMAN DR
District: BRYAN
Control Number: 0917-29-148
DBE Goal: 0.0%
Project: STP 2025(890)VRUG
Guaranty: $2,000.00
Time: 39 WORKING DAYS
Engineer's Estimate: $100,612.19
Date: 07/01/2025 (11 months ago)
Contract Number: 7253037
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00209975
Contract Type: Federal Waived
Project Description: INSTALL PEDESTRIAN CROSSWALK
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ROBBINS
JOSEPH GREIVE
BRAZOS HOLLEMAN DR (0917-29-148)
Project Name: N/A
Project: STP 2025(890)VRUG
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.1 MI W OF BS 6R
Limits To: 0.2 MI W OF BS 6R
Project Description: INSTALL PEDESTRIAN CROSSWALK
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$100,612.19 | |||
| $89,847.71 |
-10.7%
-$10,764.48
|
|||
| $129,882.94 |
29.09%
$29,270.75
|
44.56%
$40,035.23
|
||
| $141,519.00 |
40.66%
$40,906.81
|
57.51%
$51,671.29
|
-8.96%
-$11,636.06
|
|
| $141,917.00 |
41.05%
$41,304.81
|
57.95%
$52,069.29
|
-0.28%
-$398.00
|
E
Engineer's Estimate
$100,612.19
1
$89,847.71
Over/Under Est:
-10.7%
-$10,764.48
$129,882.94
Over/Under Est:
29.09%
$29,270.75
Amt Left:
44.56%
$40,035.23
$141,519.00
Over/Under Est:
40.66%
$40,906.81
Amt Left:
57.51%
$51,671.29
Delta:
-8.96%
-$11,636.06
$141,917.00
Over/Under Est:
41.05%
$41,304.81
Amt Left:
57.95%
$52,069.29
Delta:
-0.28%
-$398.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRAFFIC SIGNS & LINES, LLC | 28.70% | $25,786.29 |
| THIRD COAST SERVICES LLC | 27.82% | $24,995.63 |
| Total: | 56.52% | $50,781.92 |
Bid Items & Bid Tabulations
43
Total
0 of 43
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $5,000.00 |