BRAZOS VARIOUS (0917-00-069)

Items: 25

County: BRAZOS
Length: 0.0000 MILES
Highway: VARIOUS
District: BRYAN
Control Number: 0917-00-069
DBE Goal: 0.0%
Project: C 917-00-69
Guaranty: $11,000.00
Time: 66 WORKING DAYS
Engineer's Estimate: $550,286.00
Date: 05/02/2025 (1 year ago)
Contract Number: 5253231
Type: BRIDGE MAINTENANCE
Project ID: A00188032
Project Description: BRIDGE REPAIRS CONSISTING OF SUPERSTRUCTURE RUST, JOINT, AND EROSION REPAIRS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DELMY REYES
MATT HENSARLING
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$550,286.00
$590,567.00
Over/Under Est: 7.32% $40,281.00
Over/Under Est: 32.42% $178,379.00
Amt Left: 23.38% $138,098.00
Over/Under Est: 35.94% $197,764.00
Amt Left: 26.67% $157,483.00
Delta: -2.66% -$19,385.00
Over/Under Est: 41.21% $226,781.00
Amt Left: 31.58% $186,500.00
Delta: -3.88% -$29,017.00
Over/Under Est: 51.59% $283,917.00
Amt Left: 41.25% $243,636.00
Delta: -7.35% -$57,136.00
Over/Under Est: 107.01% $588,884.00
Amt Left: 92.89% $548,603.00
Delta: -36.56% -$304,967.00
Subcontractor Percentage Amount
REAR CONTRACTORS LLC 7.74% $54,005.06
JOSEY'S CONTRACTING LLC 7.67% $53,516.64
RAILPROS FIELD SERVICES, INC. 5.59% $39,003.65
Total: 21.00% $146,525.35

Bid Items & Bid Tabulations

25 Total 0 of 25
BRAZOS  |  VARIOUS  |  BRYAN  |  0917-00-069  |  05/02/2025  |  $550,286.00  |  C 917-00-69  |  BRIDGE MAINT  |  66 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PREMIER CONTRACTORS LLC
BK FIELD OPERATIONS LLC
BLACKSMITH VENTURES LLC
GARRET SHIELDS INFRASTRUCTURE
BECK-REIT & SONS, LTD.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 2.000 $500.000 $100.000 $1,500.000 $2,000.000 $1,000.000 $500.000 $2,500.000
REMOV CONC (RIPRAP)
SY 307.000 $50.000 $60.000 $55.000 $100.000 $50.000 $50.000 $100.000
CEM STABIL BKFL
CY 85.000 $200.000 $300.000 $300.000 $75.000 $300.000 $500.000 $500.000
FLOWABLE BACKFILL
CY 106.000 $300.000 $350.000 $550.000 $500.000 $500.000 $500.000 $400.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 2,223.000 $15.000 $30.000 $30.000 $50.000 $40.000 $35.000 $35.000
RIPRAP (CONC)(CL B)(5 IN)
CY 70.000 $650.000 $1,000.000 $600.000 $500.000 $1,000.000 $650.000 $1,200.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 111.000 $250.000 $250.000 $220.000 $225.000 $200.000 $250.000 $350.000
CLEANING AND SEALING EXISTING JOINTS
LF 314.000 $50.000 $60.000 $50.000 $75.000 $50.000 $75.000 $75.000
CLEAN & PAINT EXIST STR (SYSTEM II)
LS 2.000 $20,000.000 $50,000.000 $110,000.000 $95,000.000 $100,000.000 $120,000.000 $143,000.000
HEADER TYPE EXPANSION JOINT
CF 264.000 $400.000 $400.000 $390.000 $250.000 $550.000 $550.000 $650.000
GABIONS (PVC)( 3FT X 3 FT)
CY 50.000 $350.000 $400.000 $300.000 $300.000 $300.000 $375.000 $450.000
CLEAN EXIST CULVERTS
EA 1.000 $30,000.000 $3,000.000 $8,000.000 $5,000.000 $5,000.000 $12,500.000 $75,000.000
MOBILIZATION
LS 1.000 $54,000.000 $50,000.000 $75,000.000 $50,000.000 $50,000.000 $70,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $1.000 $3,000.000 $5,000.000 $5,000.000 $5,500.000 $5,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $4,250.000 $1.000 $5,000.000 $15,000.000 $1,000.000 $2,500.000 $5,000.000
TMA (STATIONARY)
DAY 60.000 $500.000 $1.000 $1.000 $400.000 $300.000 $100.000 $300.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 72.000 $95.000 $80.000 $50.000 $50.000 $10.000 $15.000 $100.000
ROCK FILTER DAMS (REMOVE)
LF 72.000 $10.000 $15.000 $20.000 $1.000 $2.000 $1.000 $25.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 858.000 $30.000 $15.000 $15.000 $25.000 $10.000 $10.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 858.000 $10.000 $15.000 $5.000 $5.000 $5.000 $1.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,317.000 $5.000 $3.000 $4.000 $15.000 $5.000 $5.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,317.000 $1.000 $3.000 $1.000 $1.000 $1.000 $1.000 $5.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 51.000 $6.000 $15.000 $10.000 $15.000 $10.000 $5.000 $25.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 51.000 $3.000 $3.000 $5.000 $1.000 $1.000 $1.000 $5.000
BENT CAP/ABUTMENT CAP CLEANING
EA 2.000 $1,000.000 $3,000.000 $300.000 $1,500.000 $1,000.000 $2,000.000 $1,000.000
Totals: $550,286.000 $590,567.000 $728,665.000 $748,050.000 $777,067.000 $834,203.000 $1,139,170.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $16,800.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
Total: $22,800.00