Bid Cobra

BRAZOS FM 974 (0540-03-037)

Items: 169

County: BRAZOS
Length: 0.0000 MILES
Highway: FM 974
District: BRYAN
Control Number: 0540-03-037
DBE Goal: 5.0%
Project: STP 2025(932)VRU
Guaranty: $72,000.00
Time: 203 WORKING DAYS
Engineer's Estimate: $2,824,745.82
Date: 08/07/2025 (10 months ago)
Contract Number: 8253018
Type: ADDING TWLT AND ADDING RIGHT TURN LANE
Project ID: A00192967
Contract Type: Federal
Project Description: ADD TWLT, ADD RIGHT TURN LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES ROBBINS
JOSEPH GREIVE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$2,824,745.82
$2,808,685.15
Over/Under Est: -0.57% -$16,060.67
Over/Under Est: 5.96% $168,318.07
Amt Left: 6.56% $184,378.74
Over/Under Est: 9.52% $268,839.46
Amt Left: 10.14% $284,900.13
Delta: -3.36% -$100,521.39
Over/Under Est: 22.72% $641,917.37
Amt Left: 23.43% $657,978.04
Delta: -12.06% -$373,077.91
$3,721,478.41
Over/Under Est: 31.75% $896,732.59
Amt Left: 32.5% $912,793.26
Delta: -7.35% -$254,815.22
Subcontractor Percentage Amount
CEN TEX HYDROSEED, INC. 2.10% $58,982.39
WILLOW CITY SIGN & RAIL, INC. 1.45% $40,725.93
LINEAR TRAFFIC MARKINGS LLC 1.31% $36,793.78
AWP SAFETY 0.92% $25,839.90
CEN-TREE SOLUTIONS LLC 0.21% $5,898.24
Total: 5.99% $168,240.24

Bid Items & Bid Tabulations

169 Total 0 of 169
BRAZOS  |  FM 974  |  BRYAN  |  0540-03-037  |  08/07/2025  |  $2,824,745.82  |  STP 2025(932)VRU  |  ADDING TWLT AND ADDING RIGHT TURN LA...  |  203 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LARRY YOUNG PAVING, INC.
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
BRAZOS PAVING, INC.
PREPARING ROW
STA 29.000 $375.000 $64.000 $877.000 $700.000 $400.000 $4,084.000
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 5.000 $1,000.000 $1,100.000 $967.000 $1,200.000 $1,250.000 $386.350
TREE PROTECTION (INSTALL)
EA 11.000 $200.000 $700.000 $600.000 $600.000 $550.000 $710.000
TREE PROTECTION (REMOVE)
EA 11.000 $130.000 $190.000 $163.000 $150.000 $150.000 $200.000
REMOV CONC (PAV)
SY 426.000 $15.000 $20.000 $26.000 $20.000 $42.500 $26.250
REMOV CONC (RIPRAP)
SY 93.000 $30.000 $20.000 $17.700 $15.000 $30.000 $44.250
REMOV CONC (MEDIANS)
SY 112.000 $15.000 $20.000 $33.000 $20.000 $30.000 $46.850
REMOV CONC (CURB & GUTTER)
LF 434.000 $10.000 $9.500 $39.000 $17.000 $15.000 $13.000
REMOV CONC (FLUME)
SY 79.000 $50.000 $20.000 $18.000 $17.000 $30.000 $52.400
RMV (0"-6") TRT/UNTRT BASE & ASPH PAV
SY 1,279.000 $15.000 $7.500 $4.870 $9.000 $30.000 $12.500
REMOVE STAB BASE AND ASPH PAV (6"-20")
SY 3,553.000 $10.000 $12.000 $10.540 $14.000 $32.650 $16.350
EXCAV (ROADWAY)
CY 2,986.000 $18.000 $26.000 $36.480 $26.000 $30.000 $29.300
EMBANK (FNL)(DC)(TY C)
CY 892.000 $25.000 $22.000 $10.350 $26.000 $22.000 $49.100
FURN & PLACE TOPSOIL (4")
SY 9,161.000 $0.500 $1.500 $1.570 $3.000 $1.000 $4.650
BLOCK SODDING
SY 210.000 $7.500 $7.750 $6.520 $6.600 $6.000 $7.750
BROADCAST SEED (PERM_URBAN_SAND)
SY 8,266.000 $1.250 $0.500 $0.380 $0.400 $0.350 $0.450
BROADCAST SEED (TEMP_WARM)
SY 343.000 $1.000 $0.500 $0.330 $0.330 $0.300 $0.400
BROADCAST SEED (TEMP_COOL)
SY 343.000 $1.000 $0.500 $0.330 $0.330 $0.300 $0.400
VEGETATIVE WATERING
TGL 91.700 $100.000 $42.000 $44.000 $20.000 $50.000 $148.300
PROOF ROLLING
HR 10.000 $250.000 $93.000 $95.000 $250.000 $250.000 $149.500
FL BS (CMP IN PLC)(TY A GR 1-2) (11")
SY 5,587.000 $35.000 $35.000 $28.280 $40.000 $45.000 $25.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 61.000 $350.000 $750.000 $338.000 $375.000 $350.000 $425.000
LIME TRT (EXIST MATL)(8")
SY 5,765.000 $6.500 $6.500 $8.990 $6.000 $7.750 $17.000
CEMENT
TON 61.000 $250.000 $170.000 $215.000 $250.000 $350.000 $362.000
CEMENT TREAT (SUBGRADE) (8")
SY 5,765.000 $5.500 $2.000 $3.470 $6.000 $4.000 $10.900
PRIME COAT(MC-30 OR AE-P)
GAL 1,440.000 $4.500 $7.750 $6.600 $7.000 $6.000 $12.500
SP MIXES SP-B SAC-B PG64-22
TON 1,155.000 $110.000 $130.000 $121.000 $130.000 $140.000 $141.500
TACK COAT
GAL 1,595.000 $4.500 $7.250 $4.000 $6.500 $5.000 $7.400
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 1,751.000 $190.000 $140.000 $125.000 $160.000 $146.000 $199.300
PLANE ASPH CONC PAV(2")
SY 10,763.000 $3.500 $1.750 $2.000 $2.500 $4.000 $5.000
PLANE ASPH CONC PAV(6")
SY 365.000 $5.000 $3.250 $68.000 $10.000 $24.650 $23.100
CUT & RESTORING PAV
SY 18.000 $100.000 $250.000 $144.500 $190.000 $250.000 $185.600
CEM STABIL BKFL
CY 18.000 $200.000 $100.000 $122.000 $200.000 $200.000 $129.500
TRENCH EXCAVATION PROTECTION
LF 571.000 $5.000 $1.250 $25.000 $15.000 $12.000 $8.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 22.000 $200.000 $240.000 $208.000 $300.000 $192.000 $246.500
DRILL SHAFT (TRF SIG POLE) (30 IN)
LF 48.000 $200.000 $290.000 $204.000 $275.000 $188.000 $241.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 28.000 $280.000 $320.000 $250.000 $310.000 $231.000 $296.400
RIPRAP (CONC)(4 IN)
CY 40.000 $800.000 $750.000 $684.000 $750.000 $800.000 $1,020.000
RIPRAP (CONC) (CL B) (4 IN)
CY 8.000 $550.000 $880.000 $1,055.000 $750.000 $800.000 $1,055.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 709.000 $225.000 $160.000 $158.000 $175.000 $150.000 $350.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 260.000 $200.000 $150.000 $157.000 $200.000 $240.000 $350.000
CONC BOX CULV (3 FT X 2 FT)
LF 94.000 $350.000 $360.000 $317.000 $450.000 $700.000 $417.000
CONC BOX CULV (4 FT X 3 FT)
LF 50.000 $425.000 $510.000 $524.000 $475.000 $750.000 $495.650
RC PIPE (CL III)(18 IN)
LF 43.000 $70.000 $99.000 $143.000 $85.000 $62.000 $211.300
RC PIPE (CL III)(42 IN)
LF 494.000 $220.000 $190.000 $191.000 $225.000 $300.000 $275.900
JCTBOX(COMPL)(PJB)(5FTX5FT)
EA 1.000 $7,500.000 $7,500.000 $6,460.000 $8,000.000 $5,500.000 $7,783.000
INLET (COMPL)(PCO)(3FT)(RIGHT)
EA 3.000 $6,500.000 $14,000.000 $7,949.000 $7,750.000 $5,500.000 $7,140.000
INLET (COMPL)(PSL)(RC)(5FTX5FT)
EA 1.000 $11,500.000 $15,000.000 $6,970.000 $9,000.000 $7,000.000 $8,390.000
INLET(COMPL)(PAZD)(FG)(5FTX5FT-4FTX4FT)
EA 3.000 $10,000.000 $8,800.000 $7,584.000 $10,500.000 $7,000.000 $9,112.000
INLET (COMPL)(TY SIDEWALK BRIDGE)(MOD)
EA 6.000 $10,000.000 $18,000.000 $36,997.000 $25,000.000 $35,500.000 $22,134.000
WINGWALL (FW - S) (HW=4 FT)
EA 1.000 $12,000.000 $9,600.000 $17,450.000 $16,500.000 $9,000.000 $17,380.000
WINGWALL (SW - 0) (HW=3 FT)
EA 1.000 $6,500.000 $8,300.000 $17,900.000 $12,000.000 $3,500.000 $13,420.000
SET (TY I)(S= 3 FT)(HW= 3 FT)(6:1)(P)
EA 3.000 $12,500.000 $4,300.000 $6,945.000 $16,000.000 $9,500.000 $9,600.000
SET (TY II) (42 IN) (RCP) (3: 1) (C)
EA 1.000 $6,000.000 $9,500.000 $4,377.000 $8,500.000 $6,500.000 $5,950.000
ADJUSTING MANHOLES
EA 2.000 $2,000.000 $1,600.000 $2,810.000 $4,500.000 $1,200.000 $1,300.000
CLEAN EXIST CULVERTS
EA 1.000 $2,000.000 $6,300.000 $4,000.000 $3,600.000 $1,500.000 $5,000.000
REMOV STR (INLET)
EA 1.000 $1,300.000 $1,700.000 $456.000 $1,200.000 $1,200.000 $912.000
REMOV STR (WINGWALL)
EA 4.000 $2,000.000 $1,200.000 $2,638.000 $3,000.000 $1,500.000 $1,675.000
REMOV STR (PIPE)
LF 53.000 $25.000 $32.000 $21.000 $17.500 $30.000 $74.400
REMOVE STR (DRIVEWAY CULVERT)
EA 3.000 $500.000 $1,700.000 $1,100.000 $425.000 $1,200.000 $2,635.000
MOBILIZATION
LS 1.000 $270,845.170 $270,000.000 $244,300.000 $200,000.000 $220,000.000 $210,850.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $3,700.000 $2,600.000 $5,200.000 $2,500.000 $6,500.000 $8,175.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $1,200.000 $13,000.000 $15,000.000 $18,000.000 $18,385.000
TMA (STATIONARY)
DAY 135.000 $200.000 $250.000 $500.000 $300.000 $150.000 $386.000
TMA (MOBILE OPERATION)
DAY 6.000 $250.000 $1,200.000 $900.000 $600.000 $150.000 $800.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 692.000 $45.000 $45.000 $38.000 $40.000 $35.000 $45.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 25.000 $75.000 $96.000 $81.000 $85.000 $75.000 $96.500
ROCK FILTER DAMS (REMOVE)
LF 717.000 $10.000 $13.000 $11.000 $10.000 $10.000 $13.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $20.000 $41.000 $35.000 $35.000 $32.000 $41.200
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $10.000 $15.000 $13.000 $12.000 $12.000 $15.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 203.000 $4.000 $5.750 $4.890 $5.000 $4.500 $5.800
TEMP SEDMT CONT FENCE (REMOVE)
LF 203.000 $1.000 $1.250 $1.000 $1.000 $1.000 $1.300
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 459.000 $6.000 $6.000 $5.160 $5.500 $4.750 $6.150
BIODEG EROSN CONT LOGS (REMOVE)
LF 459.000 $1.500 $1.250 $1.000 $1.000 $1.000 $1.300
CONSTRUCTING DETOURS
SY 496.000 $60.000 $120.000 $131.650 $100.000 $155.000 $78.850
COLORED TEXTURED CONC (4")
SY 158.000 $125.000 $140.000 $160.890 $150.000 $260.000 $147.400
CONC CURB (TY II)
LF 57.000 $25.000 $11.000 $66.400 $55.000 $60.000 $17.800
CONC CURB & GUTTER (TY II)
LF 1,372.000 $45.000 $41.000 $34.240 $65.000 $85.000 $27.600
DRIVEWAYS (CONC)
SY 109.000 $100.000 $120.000 $133.000 $130.000 $200.000 $116.000
DRIVEWAYS (ACP)
SY 120.000 $50.000 $65.000 $127.000 $75.000 $190.000 $140.700
CONC SIDEWALKS (5")
SY 877.000 $150.000 $80.000 $81.430 $120.000 $180.000 $116.000
CURB RAMPS (TY 7)
EA 5.000 $2,750.000 $2,500.000 $1,950.000 $3,300.000 $4,000.000 $2,030.000
CURB RAMPS (TY 21)
EA 1.000 $5,500.000 $4,300.000 $2,000.000 $4,600.000 $4,000.000 $2,525.000
RELOCATE EXISTING MAILBOX
EA 2.000 $500.000 $480.000 $215.000 $250.000 $100.000 $450.000
IN RD IL (TY SA) 20T-8 (150W EQ) LED
EA 2.000 $1,800.000 $5,300.000 $5,290.000 $6,100.000 $4,900.000 $6,260.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 1.000 $4,600.000 $6,000.000 $6,215.000 $6,600.000 $5,720.000 $7,356.000
CONDT (PVC) (SCH 80) (2")
LF 1,935.000 $15.000 $10.000 $14.590 $8.750 $14.000 $17.300
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,595.000 $20.000 $18.000 $20.380 $10.150 $19.000 $24.150
CONDT (PVC) (SCH 80) (4")
LF 815.000 $15.000 $14.000 $18.210 $15.750 $17.000 $21.550
CONDT (PVC) (SCH 80) (4") (BORE)
LF 665.000 $25.000 $22.000 $26.900 $21.000 $25.000 $31.850
ELEC CONDR (NO.8) INSULATED
LF 6,780.000 $2.000 $1.250 $2.790 $1.850 $3.000 $3.300
ELEC CONDR (NO.6) BARE
LF 4,475.000 $2.200 $1.250 $2.230 $2.100 $2.250 $2.650
ELEC CONDR (NO.6) INSULATED
LF 535.000 $2.000 $1.500 $2.480 $2.550 $2.500 $2.950
ELEC CONDR (NO.4) BARE
LF 395.000 $2.750 $2.250 $3.520 $3.600 $3.250 $4.200
ELEC CONDR (NO.4) INSULATED
LF 790.000 $3.100 $2.750 $4.150 $4.150 $4.000 $4.900
GROUND BOX TY D (162922)
EA 2.000 $1,200.000 $1,600.000 $1,092.000 $1,075.000 $1,006.000 $1,293.000
GROUND BOX TY D (162922)W/APRON
EA 12.000 $1,100.000 $1,800.000 $1,324.000 $1,475.000 $1,220.000 $1,567.000
REMOVE GROUND BOX
EA 10.000 $300.000 $470.000 $116.000 $525.000 $110.000 $137.300
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $7,500.000 $8,600.000 $9,619.000 $11,000.000 $8,900.000 $11,386.000
ALUMINUM SIGNS (TY A)
SF 66.000 $30.000 $110.000 $33.150 $80.000 $31.000 $39.200
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 36.000 $550.000 $720.000 $614.000 $575.000 $720.000 $925.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $700.000 $860.000 $734.000 $700.000 $725.000 $1,027.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 6.000 $785.000 $980.000 $832.000 $775.000 $800.000 $1,240.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,000.000 $1,100.000 $950.000 $900.000 $1,150.000 $1,475.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 2.000 $1,100.000 $1,500.000 $1,300.000 $1,225.000 $1,350.000 $1,707.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 2.000 $100.000 $110.000 $93.000 $90.000 $122.500 $157.600
INSTL OM ASSM (OM-4)(TWT)WAP
EA 35.000 $100.000 $400.000 $350.000 $320.000 $418.000 $540.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 541.000 $0.300 $0.500 $0.570 $0.500 $0.520 $0.700
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 6,262.000 $0.300 $0.500 $0.570 $0.450 $0.520 $0.700
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 261.000 $0.500 $0.750 $1.130 $0.600 $1.040 $1.350
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 7,128.000 $0.300 $0.500 $0.570 $0.450 $0.520 $0.700
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 591.000 $1.500 $0.500 $1.500 $1.500 $1.000 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 75.000 $1.000 $0.500 $1.500 $1.500 $1.000 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 334.000 $1.500 $0.500 $1.500 $1.500 $1.000 $2.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 105.000 $2.000 $2.000 $2.720 $1.750 $2.500 $3.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 957.000 $1.300 $1.500 $2.170 $1.500 $2.000 $2.600
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 350.000 $12.000 $11.000 $8.420 $9.500 $7.750 $10.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 14.000 $150.000 $180.000 $288.000 $150.000 $265.000 $341.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 10.000 $215.000 $200.000 $310.000 $160.000 $285.000 $367.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 14.000 $50.000 $45.000 $52.000 $40.000 $48.000 $61.100
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 200.000 $5.000 $9.000 $9.000 $7.500 $8.000 $10.000
PAVEMENT SLER 6"
LF 540.000 $1.000 $0.250 $0.200 $0.300 $0.180 $0.250
PAVEMENT SLER 8"
LF 135.000 $1.250 $0.500 $0.260 $0.350 $0.240 $0.300
PAVEMENT SLER 24"
LF 24.000 $4.000 $2.500 $0.780 $2.250 $0.720 $1.000
PAVEMENT SLER (ARROW)
EA 3.000 $40.000 $26.000 $6.000 $25.000 $5.000 $6.500
PAVEMENT SLER (WORD)
EA 1.000 $45.000 $26.000 $6.000 $25.000 $5.000 $6.500
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 590.000 $1.000 $1.250 $0.850 $1.150 $0.800 $1.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 3,770.000 $1.000 $1.250 $0.850 $1.100 $0.800 $1.000
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 260.000 $1.000 $1.250 $0.850 $1.150 $0.800 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 6,001.000 $1.000 $1.250 $0.850 $1.100 $0.800 $1.000
REFL PAV MRKR TY I-C
EA 73.000 $9.000 $6.000 $7.000 $5.500 $6.000 $7.750
REFL PAV MRKR TY II-A-A
EA 117.000 $7.000 $6.000 $7.000 $5.500 $6.000 $7.750
REFL PAV MRKR TY II-C-R
EA 18.000 $6.000 $6.000 $7.000 $5.500 $6.000 $7.750
ELIM EXT PM & MRKS (6")
LF 10,343.000 $0.750 $1.000 $0.530 $0.850 $0.500 $0.650
ELIM EXT PM & MRKS (8")
LF 151.000 $1.000 $1.250 $2.000 $1.000 $1.000 $1.250
ELIM EXT PM & MRKS (24")
LF 40.000 $3.500 $3.250 $3.000 $2.750 $2.100 $2.700
ELIM EXT PM & MRKS (ARROW)
EA 1.000 $60.000 $96.000 $77.000 $80.000 $70.000 $90.000
ELIM EXT PM & MRKS (DBL ARROW)
EA 5.000 $80.000 $130.000 $77.000 $125.000 $70.000 $90.000
ELIM EXT PM & MRKS (WORD)
EA 1.000 $60.000 $96.000 $77.000 $100.000 $70.000 $90.000
PAV SURF PREP FOR MRK (6")
LF 540.000 $1.250 $0.250 $0.260 $0.300 $0.240 $0.300
PAV SURF PREP FOR MRK (8")
LF 135.000 $1.250 $0.250 $0.350 $0.350 $0.350 $0.400
PAV SURF PREP FOR MRK (24")
LF 24.000 $4.000 $2.500 $2.000 $2.500 $1.000 $1.250
PAV SURF PREP FOR MRK (ARROW)
EA 3.000 $20.000 $26.000 $27.000 $30.000 $25.000 $32.150
PAV SURF PREP FOR MRK (WORD)
EA 1.000 $25.000 $38.000 $27.000 $40.000 $25.000 $32.150
INSTALL HWY TRF SIG (SYSTEM)
EA 1.000 $28,000.000 $70,000.000 $35,200.000 $46,500.000 $33,000.000 $41,640.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $5,000.000 $11,000.000 $2,941.000 $9,500.000 $2,800.000 $3,485.000
VEH SIG SEC (12")LED(GRN)
EA 12.000 $225.000 $250.000 $271.000 $400.000 $250.000 $321.000
VEH SIG SEC (12")LED(GRN ARW)
EA 3.000 $250.000 $250.000 $288.000 $405.000 $275.000 $341.000
VEH SIG SEC (12")LED(YEL)
EA 12.000 $225.000 $250.000 $275.000 $400.000 $260.000 $325.000
VEH SIG SEC (12")LED(YEL ARW)
EA 4.000 $250.000 $250.000 $280.000 $405.000 $260.000 $330.000
VEH SIG SEC (12")LED(RED)
EA 12.000 $250.000 $250.000 $271.000 $400.000 $250.000 $321.000
VEH SIG SEC (12")LED(RED ARW)
EA 3.000 $250.000 $250.000 $280.000 $405.000 $260.000 $330.000
PED SIG SEC (LED)(COUNTDOWN)
EA 4.000 $590.000 $560.000 $835.000 $915.000 $780.000 $990.000
BACKPLATE W/REFL BRDR(3 SEC)ALUM
EA 14.000 $170.000 $170.000 $149.000 $215.000 $140.000 $176.000
BACKPLATE W/REFL BRDR(4 SEC)ALUM
EA 1.000 $220.000 $230.000 $225.000 $305.000 $210.000 $265.000
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 6,695.000 $2.250 $2.000 $3.000 $3.150 $2.800 $3.550
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 485.000 $3.000 $2.250 $3.520 $3.700 $3.500 $4.200
TRF SIG CBL (TY C)(12 AWG)(2 CONDR)
LF 25.000 $2.000 $1.500 $2.820 $2.850 $3.000 $3.350
INS TRF SIG PL AM(S)1 ARM(28')LUM
EA 1.000 $14,000.000 $13,000.000 $13,750.000 $16,250.000 $15,000.000 $16,275.000
INS TRF SIG PL AM(S)1 ARM(32')LUM
EA 3.000 $14,000.000 $13,000.000 $14,980.000 $16,800.000 $16,000.000 $17,730.000
INS TRF SIG PL AM(S)1 ARM(40')LUM
EA 2.000 $15,000.000 $16,000.000 $17,500.000 $19,500.000 $18,000.000 $20,665.000
PED POLE ASSEMBLY
EA 3.000 $2,750.000 $5,300.000 $2,850.000 $3,750.000 $3,500.000 $3,370.000
PED DETECT PUSH BUTTON (APS)
EA 4.000 $1,000.000 $1,000.000 $1,774.000 $1,175.000 $2,000.000 $2,100.000
BBU SYSTEM (EXTERNAL BATTERY CABINET)
EA 1.000 $9,000.000 $8,400.000 $9,537.000 $11,750.000 $10,000.000 $11,300.000
VDS PROSR SYS
EA 2.000 $12,000.000 $12,000.000 $13,330.000 $15,100.000 $15,000.000 $15,777.000
VIVDS CAM ASSY VAR LNS
EA 8.000 $3,500.000 $5,900.000 $6,353.000 $7,800.000 $6,000.000 $7,520.000
VDS CNTRL SOFTWARE
EA 1.000 $400.000 $840.000 $1,300.000 $1,350.000 $1,200.000 $1,520.000
VDS ATSPM
EA 1.000 $4,050.000 $250.000 $13,960.000 $15,500.000 $15,000.000 $16,515.000
VDS CABLING
LF 4,955.000 $2.000 $3.250 $6.600 $1.200 $7.000 $7.800
Totals: $2,824,745.820 $2,808,685.150 $2,993,063.890 $3,093,585.280 $3,466,663.190 $3,721,478.410
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $4,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $8,127.65
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $59,585.94
Total: $71,713.59