BRAZOS SH 6 (0050-02-111)

Items: 25

County: BRAZOS
Length: N/A
Highway: SH 6
District: BRYAN
Control Number: 0050-02-111
DBE Goal: N/A
Project: NH 2020(081)
Guaranty: N/A
Time: 40 WORKING DAYS
Engineer's Estimate: $5,307,939.28
Date: 10/02/2019 (6 years ago)
Contract Number: N/A
Type: ASPHALT RUBBER SEAL COAT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$5,307,939.28
$4,675,136.43
Over/Under Est: -11.92% -$632,802.85
Over/Under Est: 18.06% $958,828.26
Amt Left: 34.04% $1,591,631.11
Over/Under Est: 25.68% $1,362,931.48
Amt Left: 42.69% $1,995,734.33
Delta: -6.45% -$404,103.22

Bid Items & Bid Tabulations

25 Total 0 of 25
BRAZOS  |  SH 6  |  BRYAN  |  0050-02-111  |  10/02/2019  |  $5,307,939.28  |  NH 2020(081)  |  ASPH RUBBER SEAL COAT  |  40 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
COX PAVING OF TEXAS, INC.
ANGEL BROTHERS HOLDINGS CORP.
BRANNAN PAVING CO., LTD.
ASPH (A-R TYPE II)
GAL 879,118.000 $2.800 $2.750 $3.500 $3.960
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 15,630.000 $116.000 $99.000 $136.500 $127.720
MOBILIZATION
LS 1.000 $500,000.000 $200,000.000 $395,000.000 $612,999.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,000.000 $14,000.000 $17,000.000 $25,000.000
INTERSECTIONS (SURF TREAT)
SY 24,640.000 $1.650 $3.000 $4.300 $4.050
DRIVEWAYS (SURF TREAT)
SY 3,763.000 $1.650 $4.000 $7.300 $3.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 27,394.000 $0.500 $0.500 $1.000 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 14,297.000 $0.500 $0.500 $1.000 $0.400
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 60,692.000 $0.900 $0.850 $0.800 $0.750
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 7,423.000 $5.050 $7.000 $7.100 $4.900
REFL PAV MRK TY II (W) 4" (BRK)
LF 71,089.000 $0.220 $0.110 $0.160 $0.120
REFL PAV MRK TY II (W) 4" (SLD)
LF 567,658.000 $0.150 $0.110 $0.110 $0.100
REFL PAV MRK TY II (Y) 4" (BRK)
LF 46,480.000 $0.200 $0.110 $0.140 $0.120
REFL PAV MRK TY II (Y) 4" (SLD)
LF 397,876.000 $0.160 $0.110 $0.120 $0.100
PREFAB PAV MRK TY C (W) (ARROW)
EA 207.000 $242.000 $185.000 $185.000 $180.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 3.000 $402.000 $400.000 $310.000 $420.000
PREFAB PAV MRK TY C (W) (WORD)
EA 174.000 $375.000 $200.000 $265.000 $240.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 2.000 $800.000 $500.000 $700.000 $580.000
REFL PAV MRKR TY I-C
EA 6,596.000 $2.590 $2.750 $2.600 $2.400
REFL PAV MRKR TY II-A-A
EA 7,660.000 $2.590 $2.750 $2.600 $2.800
REFL PAV MRKR TY II-C-R
EA 1,750.000 $2.590 $2.750 $3.100 $2.900
ELIM EXT PAV MRK & MRKS (4")
LF 46,238.000 $0.250 $0.300 $0.400 $0.400
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 160.000 $15.000 $15.000 $25.000 $32.000
TMA (STATIONARY)
DAY 27.000 $200.000 $1.000 $500.000 $500.000
TMA (MOBILE OPERATION)
DAY 74.000 $200.000 $1.000 $550.000 $300.000
Totals: $5,307,939.280 $4,675,136.430 $6,266,767.540 $6,670,870.760