BRAZOS SH 6 (0049-12-105)
Items: 40
County: BRAZOS
Length: N/A
Highway: SH 6
District: BRYAN
Control Number: 0049-12-105
DBE Goal: N/A
Project: BR 2020(085)
Guaranty: N/A
Time: 152 WORKING DAYS
Engineer's Estimate: $1,187,901.00
Date: 10/02/2019 (6 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACH RAILING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,187,901.00 | |||
| $1,471,134.30 |
23.84%
$283,233.30
|
|||
| $1,484,868.00 |
25%
$296,967.00
|
0.93%
$13,733.70
|
||
| $1,541,658.00 |
29.78%
$353,757.00
|
4.79%
$70,523.70
|
-3.82%
-$56,790.00
|
|
| $1,802,930.00 |
51.77%
$615,029.00
|
22.55%
$331,795.70
|
-16.95%
-$261,272.00
|
|
| $1,923,822.90 |
61.95%
$735,921.90
|
30.77%
$452,688.60
|
-6.71%
-$120,892.90
|
E
Engineer's Estimate
$1,187,901.00
1
Awarded
$1,471,134.30
Over/Under Est:
23.84%
$283,233.30
$1,484,868.00
Over/Under Est:
25%
$296,967.00
Amt Left:
0.93%
$13,733.70
$1,541,658.00
Over/Under Est:
29.78%
$353,757.00
Amt Left:
4.79%
$70,523.70
Delta:
-3.82%
-$56,790.00
$1,802,930.00
Over/Under Est:
51.77%
$615,029.00
Amt Left:
22.55%
$331,795.70
Delta:
-16.95%
-$261,272.00
$1,923,822.90
Over/Under Est:
61.95%
$735,921.90
Amt Left:
30.77%
$452,688.60
Delta:
-6.71%
-$120,892.90
Bid Items & Bid Tabulations
40
Total
0 of 40