BRAZORIA SH0288 (6431-44-001)

Items: 18

County: BRAZORIA
Length: N/A
Highway: SH0288
District: HOUSTON
Control Number: 6431-44-001
DBE Goal: N/A
Project: RMC - 643144001
Guaranty: N/A
Time: 28 W
Engineer's Estimate: $230,463.06
Date: 11/14/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE RAIL UPGRADE OR REPLACEMENT
Mail/Deliver Bids To: N/A
JAMIE HOWELL
ROBERT ETHEREDGE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$230,463.06
$205,770.00
Over/Under Est: -10.71% -$24,693.06
Over/Under Est: -2.8% -$6,448.06
Amt Left: 8.87% $18,245.00
Over/Under Est: 0.25% $571.94
Amt Left: 12.28% $25,265.00
Delta: -3.13% -$7,020.00

Bid Items & Bid Tabulations

18 Total 0 of 18
BRAZORIA  |  SH0288  |  HOUSTON  |  6431-44-001  |  11/14/2023  |  $230,463.06  |  RMC - 643144001  |  BRIDGE RAIL UPGRADE OR REPL  |  28 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
MAIN LANE INDUSTRIES LTD.
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
AAD CONTRACTING INC.
REMOVING CONC (COPING)
LF 25.000 $360.000 $200.000 $125.000 $25.000
EXCAVATION (SPECIAL)
CY 60.000 $60.000 $80.000 $265.000 $20.000
EMBANKMENT (ORIGINAL)(ORD COMP)(TY D)
CY 60.000 $180.000 $100.000 $105.000 $85.000
FULL - DEPTH REPAIR CRCP (10")
SY 9.700 $550.000 $1,700.000 $1,750.000 $400.000
CL C CONC (COPING)
CY 2.000 $200.000 $10,000.000 $1,000.000 $3,000.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 4.000 $112.140 $700.000 $850.000 $275.000
RIPRAP (MOW STRIP)(4 IN)
CY 8.000 $1,050.000 $800.000 $950.000 $1,000.000
MOBILIZATION
LS 1.000 $17,935.000 $35,000.000 $50,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $10,000.000 $20,000.000 $3,500.000 $10,000.000
PTB (MOVE)(TY P&P)
LF 150.000 $15.000 $200.000 $150.000 $250.000
MTL W-BEAM GD FEN (TIM POST)
LF 75.000 $75.000 $75.000 $55.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $2,600.000 $2,500.000 $3,500.000 $1,800.000
REMOVE METAL BEAM GUARD FENCE
LF 75.000 $7.000 $10.000 $35.000 $8.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $700.000 $300.000 $1,250.000 $1,250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $5,000.000 $3,500.000 $4,000.000 $4,300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 3.000 $38.000 $35.000 $155.000 $60.000
CONC RAIL REPAIR(REMOVE AND REPL RAIL)
LF 25.000 $5,000.000 $700.000 $2,750.000 $1,100.000
TMA (STATIONARY)
DAY 45.000 $282.900 $200.000 $100.000 $200.000
Totals: $230,463.060 $205,770.000 $224,015.000 $231,035.000