BRAZORIA CR (0912-31-221)

Items: 68

County: BRAZORIA
Length: N/A
Highway: CR
District: HOUSTON
Control Number: 0912-31-221
DBE Goal: N/A
Project: BR 2008(795)
Guaranty: N/A
Time: 80 WORKING DAYS
Engineer's Estimate: $568,799.70
Date: 08/09/2017 (8 years ago)
Contract Number: N/A
Type: CONSTRUCTION OF BRIDGE REPLACEMENT AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$568,799.70
Over/Under Est: 5.91% $33,589.05
$731,870.10
Over/Under Est: 28.67% $163,070.40
Amt Left: 21.49% $129,481.35
Over/Under Est: 34.75% $197,668.09
Amt Left: 27.24% $164,079.04
Delta: -4.73% -$34,597.69
Over/Under Est: 36.32% $206,564.56
Amt Left: 28.71% $172,975.51
Delta: -1.16% -$8,896.47

Bid Items & Bid Tabulations

68 Total 0 of 68
BRAZORIA  |  CR  |  HOUSTON  |  0912-31-221  |  08/09/2017  |  $568,799.70  |  BR 2008(795)  |  CONSTRUCTION OF BRIDGE REPL AND APPR...  |  80 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ARANDA BROTHERS CONSTRUCTION CO., INC.
TREVWAY, INC.
PROJECT ALLIED RESOURCES, LLC
STRUCTURAL ASSURANCE, LLC
PREPARING ROW
STA 5.000 $2,000.000 $4,500.000 $1,514.000 $3,320.000 $3,573.000
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 20.000 $500.000 $250.000 $694.000 $749.000 $469.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 836.000 $3.000 $10.000 $17.920 $8.200 $5.000
EXCAVATION (ROADWAY)
CY 200.000 $10.500 $8.000 $23.080 $15.900 $11.000
EXCAVATION (CHANNEL)
CY 380.000 $19.000 $8.000 $7.830 $21.300 $8.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,700.000 $15.300 $9.000 $20.590 $19.600 $7.000
BACKFILL (TY B)
LF 1,000.000 $1.500 $11.000 $5.950 $3.110 $4.000
BLOCK SODDING
SY 1,293.000 $3.500 $5.000 $2.000 $5.400 $6.000
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 1,293.000 $0.500 $0.250 $2.000 $0.780 $1.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 1,293.000 $0.200 $0.200 $2.000 $1.170 $1.000
FERTILIZER
AC 0.540 $430.000 $1,750.000 $2,000.000 $1,810.000 $1,110.000
VEGETATIVE WATERING
MG 32.060 $20.000 $40.000 $77.000 $6.000 $31.000
FL BS (CMP IN PLC)(TYA GR1-2) (6")
SY 1,350.000 $13.250 $18.000 $18.210 $17.500 $53.000
LIME TRT (NEW BASE) (6")
SY 1,350.000 $2.500 $4.000 $7.310 $8.900 $5.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 17.750 $160.000 $170.000 $241.630 $213.000 $194.000
CEMENT TREAT (NEW BASE) (6")
SY 166.500 $3.000 $20.000 $56.210 $7.500 $4.000
ASPHALT STAB BASE (GR 2)(PG 64)
TON 435.000 $72.000 $105.000 $133.860 $112.000 $59.000
D-GR HMA(SQ) TY-D SAC-B PG70-22
TON 137.000 $87.000 $125.000 $136.420 $138.000 $172.000
CEM STABIL BKFL
CY 95.000 $75.000 $55.000 $100.000 $140.000 $136.000
TRENCH EXCAVATION PROTECTION
LF 30.000 $15.000 $2.000 $84.140 $15.600 $36.000
TEMPORARY SPL SHORING
SF 400.000 $40.000 $30.000 $33.000 $24.800 $42.000
PRESTR CONC PIL (18 IN SQ)
LF 420.000 $100.000 $105.000 $183.000 $170.000 $90.000
CL C CONC (ABUT)
CY 25.800 $900.000 $900.000 $500.000 $1,090.000 $790.000
REINF CONC SLAB (BOX BEAM)
SF 1,810.000 $15.000 $11.500 $40.000 $20.400 $17.000
APPROACH SLAB
CY 51.500 $418.000 $400.000 $196.050 $597.000 $555.000
SHEAR KEY
CY 8.000 $30.000 $300.000 $297.970 $413.000 $506.000
PRESTR CONC BOX BEAM (5B20)
LF 357.000 $185.000 $200.000 $187.000 $199.000 $215.000
RIPRAP (CONC)(5 IN)
CY 47.000 $430.000 $305.000 $342.640 $527.000 $377.000
RAIL (TY T223)
LF 144.000 $120.000 $145.000 $54.690 $140.000 $119.000
CONC BOX CULV (6 FT X 3 FT)
LF 64.000 $330.000 $300.000 $405.920 $381.000 $343.000
WINGWALL (FW - 0) (HW=5 FT)
EA 1.000 $7,100.000 $15,000.000 $7,000.000 $9,680.000 $14,502.000
REMOV STR (PIPE)
LF 60.000 $22.000 $10.000 $12.000 $27.400 $50.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $15,000.000 $20,000.000 $15,000.000 $22,900.000 $24,276.000
MOBILIZATION
LS 1.000 $60,000.000 $54,050.000 $70,000.000 $73,000.000 $133,562.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $2,250.000 $4,500.000 $5,460.000 $5,345.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 45.000 $32.000 $20.000 $45.160 $73.000 $37.000
ROCK FILTER DAMS (REMOVE)
LF 45.000 $9.000 $10.000 $28.050 $16.400 $12.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $23.000 $20.000 $8.800 $42.100 $36.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $8.000 $10.000 $5.010 $14.400 $13.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 425.000 $3.000 $5.000 $1.840 $6.400 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 425.000 $1.000 $1.000 $1.830 $1.260 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 30.000 $5.000 $8.000 $30.950 $8.700 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 30.000 $2.000 $1.000 $5.210 $2.090 $1.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 120.000 $11.000 $20.000 $43.940 $14.600 $34.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 40.000 $11.000 $20.000 $49.890 $20.900 $43.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 120.000 $11.000 $20.000 $42.100 $14.400 $34.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 40.000 $11.000 $20.000 $63.000 $18.800 $43.000
DRIVEWAYS (ACP)
SY 169.000 $33.000 $30.000 $53.680 $56.000 $72.000
MTL W-BEAM GD FEN (TIM POST)
LF 180.000 $22.000 $20.000 $22.880 $32.400 $26.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,500.000 $1,650.000 $706.000 $1,270.000 $1,221.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 8.000 $750.000 $1,400.000 $649.000 $1,040.000 $999.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,400.000 $1,350.000 $1,740.000 $3,010.000 $2,886.000
WIRE FENCE (TY C)
LF 480.000 $20.000 $5.000 $9.570 $14.900 $13.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $540.000 $350.000 $176.000 $694.000 $666.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $575.000 $450.000 $120.000 $926.000 $888.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 10.000 $70.000 $65.000 $3.790 $11.600 $11.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 24.000 $30.000 $65.000 $7.580 $20.800 $20.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 2,040.000 $0.200 $1.000 $1.260 $1.740 $1.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 48.000 $2.000 $8.000 $9.350 $5.800 $2.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 200.000 $0.200 $1.000 $0.800 $1.740 $1.000
REFL PAV MRK TY II (W) 6" (SLD)
LF 1,000.000 $0.250 $3.000 $1.260 $2.310 $1.000
REFL PAV MRK TY II (Y) 6" (SLD)
LF 1,000.000 $0.250 $3.000 $1.260 $2.310 $1.000
REFL PAV MRKR TY II-A-A
EA 14.000 $2.750 $55.000 $19.000 $11.600 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 2,240.000 $0.250 $1.000 $1.260 $0.580 $1.000
ELIM EXT PAV MRK & MRKS (24")
LF 48.000 $1.500 $3.000 $3.000 $5.800 $2.000
PAV SURF PREP FOR MRK (6")
LF 2,000.000 $0.030 $0.600 $1.260 $0.010 $1.000
PAV SURF PREP FOR MRK (24")
LF 48.000 $0.150 $0.500 $1.260 $0.060 $1.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 250.000 $5.000 $15.000 $25.000 $12.200 $10.000
Totals: $568,799.700 $602,388.750 $731,870.112 $766,467.790 $775,364.260