Show Job Controls
Bid Cobra

BOWIE SH0008 (6499-57-001)

Items: 17

County: BOWIE
Length: 0.0100 MILES
Highway: SH0008
District: ATLANTA
Control Number: 6499-57-001
DBE Goal: 0.0%
Project: BPM - A00220390
Guaranty: $39,000.00
Time: 336 WORKING DAYS
Engineer's Estimate: $1,994,770.00
Date: 06/03/2026 (7 days ago) Changed
Contract Number: 6264206
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00220390
Project Description: BPM FY 2027 ATLANTA DISTRICTTASK# 19I19023
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JASON DUPREE
CHARLOTTE ASLIN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (11)
E
Engineer's Estimate
$1,994,770.00
Over/Under Est: -54.68% -$1,090,744.92
Over/Under Est: -49.78% -$992,950.00
Amt Left: 10.82% $97,794.92
Over/Under Est: -37.39% -$745,872.00
Amt Left: 38.15% $344,872.92
Delta: -24.66% -$247,078.00
Over/Under Est: -30.44% -$607,215.00
Amt Left: 53.49% $483,529.92
Delta: -11.10% -$138,657.00
Over/Under Est: -22.8% -$454,810.00
Amt Left: 70.34% $635,934.92
Delta: -10.98% -$152,405.00
Over/Under Est: -19.5% -$389,029.00
Amt Left: 77.62% $701,715.92
Delta: -4.27% -$65,781.00
$1,690,194.50
Over/Under Est: -15.27% -$304,575.50
Amt Left: 86.96% $786,169.42
Delta: -5.26% -$84,453.50
$1,713,981.00
Over/Under Est: -14.08% -$280,789.00
Amt Left: 89.59% $809,955.92
Delta: -1.41% -$23,786.50
Over/Under Est: 10.27% $204,790.00
Amt Left: 143.31% $1,295,534.92
Delta: -28.33% -$485,579.00
Over/Under Est: 19.51% $389,110.00
Amt Left: 163.7% $1,479,854.92
Delta: -8.38% -$184,320.00
$2,737,130.00
Over/Under Est: 37.22% $742,360.00
Amt Left: 202.77% $1,833,104.92
Delta: -14.82% -$353,250.00

Bid Items & Bid Tabulations

17 Total 0 of 17
BOWIE  |  SH0008  |  ATLANTA  |  6499-57-001  |  06/03/2026  |  $1,994,770.00  |  BPM - A00220390  |  BRIDGE PREVENT MAINT  |  336 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
JACKSON EXCAVATION, LLC
SHALOM SERVICES CORPORATION
PATHFIELD INVESTMENTS LLC
GARRET SHIELDS INFRASTRUCTURE
MACIAS SPECIALTY CONTRACTING LLC
ICOS MANAGEMENT, LLC
REAR CONTRACTORS LLC
CROSS PLUS CONSTRUCTION, LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
EAST TEXAS BRIDGE, INC.
REMOV CONC (RIPRAP)
SY 95.000 $124.000 $25.000 $20.000 $100.000 $200.000 $50.000 $78.000 $105.000 $76.000 $550.000 $75.000 $100.000
EXCAV (CHANNEL)
CY 942.000 $70.000 $20.000 $40.000 $40.000 $80.000 $50.000 $67.000 $63.000 $80.000 $55.000 $65.000 $50.000
EMBANK (FNL)(OC)(TY A)
CY 3,004.000 $258.000 $20.000 $50.000 $40.000 $95.000 $40.000 $27.000 $73.500 $50.000 $55.000 $30.000 $30.000
FLOWABLE BACKFILL
CY 69.000 $310.000 $400.000 $400.000 $450.000 $700.000 $300.000 $317.000 $315.000 $500.000 $1,100.000 $500.000 $600.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 35.000 $103.000 $180.000 $100.000 $1,500.000 $250.000 $150.000 $224.000 $367.500 $350.000 $275.000 $350.000 $250.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 760.000 $103.000 $150.000 $80.000 $200.000 $220.000 $200.000 $161.000 $157.500 $250.000 $275.000 $300.000 $250.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,317.000 $309.000 $170.000 $170.000 $270.000 $250.000 $200.000 $375.000 $231.000 $350.000 $330.000 $325.000 $350.000
BEDDING MATERIAL (6 IN)
CY 331.000 $206.000 $170.000 $100.000 $186.000 $100.000 $200.000 $125.000 $210.000 $300.000 $220.000 $300.000 $350.000
CLEANING AND SEALING EXISTING JOINTS
LF 1,228.000 $11.000 $50.000 $30.000 $50.000 $38.000 $40.000 $22.000 $63.000 $50.000 $82.500 $75.000 $70.000
CLEAN EXIST CULVERTS
CY 2,354.000 $70.000 $30.000 $25.000 $70.000 $75.000 $120.000 $75.000 $147.000 $150.000 $82.500 $225.000 $100.000
MOBILIZATION
LS 1.000 $144,441.000 $82,000.000 $10,000.000 $100,000.000 $120,000.000 $180,000.000 $120,000.000 $146,500.000 $150,000.000 $220,000.000 $300,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
EA 29.000 $2,575.000 $615.520 $5,000.000 $500.000 $1.000 $5,000.000 $3,500.000 $2.000 $1.000 $8,250.000 $2,200.000 $30,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 336.000 $155.000 $100.000 $10.000 $1.000 $1.000 $100.000 $170.000 $210.000 $1.000 $330.000 $55.000 $300.000
TMA (STATIONARY)
DAY 336.000 $155.000 $250.000 $500.000 $1.000 $1.000 $300.000 $350.000 $262.500 $1.000 $330.000 $300.000 $300.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 150.000 $84.000 $20.000 $100.000 $75.000 $86.000 $100.000 $50.000 $157.500 $100.000 $165.000 $130.000 $300.000
CONCRETE BEAM REP (STRAND SPLICE)
EA 2.000 $5,665.000 $10,000.000 $100.000 $15,000.000 $10,000.000 $5,000.000 $15,000.000 $21,000.000 $15,000.000 $33,000.000 $20,000.000 $15,000.000
GEN DEBRIS REMOVE FROM UNDER BRIDGES
CY 370.000 $103.000 $60.000 $70.000 $125.000 $120.000 $120.000 $350.000 $210.000 $200.000 $165.000 $700.000 $150.000
Totals: $1,994,770.000 $904,025.080 $1,001,820.000 $1,248,898.000 $1,387,555.000 $1,539,960.000 $1,605,741.000 $1,690,194.500 $1,713,981.000 $2,199,560.000 $2,383,880.000 $2,737,130.000