BOWIE US0059 (6363-87-001)

Items: 22

County: BOWIE
Length: N/A
Highway: US0059
District: ATLANTA
Control Number: 6363-87-001
DBE Goal: N/A
Project: RMC - 636387001
Guaranty: N/A
Time: 254 CALENDAR DAYS
Engineer's Estimate: $344,028.80
Date: 03/04/2021 (5 years ago)
Contract Number: N/A
Type: INSTALLATION OF PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$344,028.80
$378,145.86
Over/Under Est: 9.92% $34,117.06
Over/Under Est: 10.87% $37,408.05
Amt Left: 0.87% $3,290.99
$472,619.45
Over/Under Est: 37.38% $128,590.65
Amt Left: 24.98% $94,473.59
Delta: -23.91% -$91,182.60
Over/Under Est: 37.72% $129,771.07
Amt Left: 25.3% $95,654.01
Delta: -0.25% -$1,180.42

Bid Items & Bid Tabulations

22 Total 0 of 22
BOWIE  |  US0059  |  ATLANTA  |  6363-87-001  |  03/04/2021  |  $344,028.80  |  RMC - 636387001  |  INSTL OF PAVMT MRK  |  254 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PMI PAVEMENT MARKING, LLC
TRP CONSTRUCTION GROUP, LLC
STRIPE-A-ZONE, INC.
INTERSTATE BARRICADES & MARKINGS, INC.
MOBILIZATION
LS 1.000 $5,000.000 $10,000.000 $15,000.000 $25,000.000 $10,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $1,000.000 $1,500.000 $1,500.000 $1.000 $5,000.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 380.000 $12.040 $14.250 $15.000 $12.500 $14.500
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 1,898.000 $12.130 $14.250 $15.000 $12.500 $12.500
ELIM EXT PAV MRK & MRKS (4")
LF 115,266.000 $0.370 $0.350 $0.450 $0.560 $0.520
ELIM EXT PAV MRK & MRKS (6")
LF 84,897.000 $0.400 $0.420 $0.550 $0.560 $0.650
ELIM EXT PAV MRK & MRKS (8")
LF 51,163.000 $0.750 $0.710 $1.000 $0.700 $1.000
ELIM EXT PAV MRK & MRKS (10")
LF 11,100.000 $1.000 $1.000 $1.250 $0.830 $2.000
ELIM EXT PAV MRK & MRKS (24")
LF 2,278.000 $0.810 $5.900 $2.700 $2.600 $2.750
MULTIPOLYMER PAV MRK (W)(4")(SLD)
LF 23,445.000 $0.400 $0.510 $0.450 $0.790 $0.650
MULTIPOLYMER PAV MRK (W)(4")(BRK)
LF 21,130.000 $0.550 $0.510 $0.500 $0.790 $0.650
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 38,185.000 $0.550 $0.780 $0.500 $0.890 $0.750
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 11,100.000 $0.650 $0.780 $0.550 $0.890 $0.750
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 21,303.000 $1.000 $0.890 $1.000 $1.100 $0.950
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
LF 85,261.000 $0.400 $0.510 $0.450 $0.790 $0.650
MULTIPOLYMER PAV MRK (Y)(4")(BRK)
LF 14,350.000 $0.640 $0.520 $0.500 $0.790 $0.650
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
LF 45,732.000 $0.580 $0.780 $0.500 $0.890 $0.750
MULTIPOLYMER PAV MRK (Y)(6")(BRK)
LF 980.000 $0.900 $0.780 $0.550 $0.890 $0.750
MULTIPOLYMER PAV MRK (BLK)(4")(BRK)
LF 21,130.000 $0.900 $0.520 $0.600 $0.790 $0.650
MULTIPOLYMER PAV MRK (BLK)(6")(BRK)
LF 11,100.000 $1.000 $0.780 $0.650 $0.890 $0.750
TMA (STATIONARY)
DAY 25.000 $225.000 $225.000 $1.000 $100.000 $200.000
TMA (MOBILE OPERATION)
DAY 34.000 $75.000 $0.950 $1.000 $125.000 $200.000
Totals: $344,028.800 $378,145.860 $381,436.850 $472,619.450 $473,799.870