BOWIE IH0030 (6299-32-001)

Items: 30

County: BOWIE
Length: N/A
Highway: IH0030
District: ATLANTA
Control Number: 6299-32-001
DBE Goal: N/A
Project: BPM - 629932001
Guaranty: N/A
Time: 250 W
Engineer's Estimate: $1,197,405.00
Date: 02/01/2018 (8 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$1,197,405.00
$853,995.00
Over/Under Est: -28.68% -$343,410.00
Over/Under Est: -13.44% -$160,929.00
Amt Left: 21.37% $182,481.00
Over/Under Est: -10.27% -$122,934.00
Amt Left: 25.82% $220,476.00
Delta: -3.67% -$37,995.00
$1,077,777.00
Over/Under Est: -9.99% -$119,628.00
Amt Left: 26.2% $223,782.00
Delta: -0.31% -$3,306.00
$1,084,167.00
Over/Under Est: -9.46% -$113,238.00
Amt Left: 26.95% $230,172.00
Delta: -0.59% -$6,390.00
$1,174,447.00
Over/Under Est: -1.92% -$22,958.00
Amt Left: 37.52% $320,452.00
Delta: -8.33% -$90,280.00
Over/Under Est: 9.85% $117,965.00
Amt Left: 54.03% $461,375.00
Delta: -12.00% -$140,923.00
$1,415,180.00
Over/Under Est: 18.19% $217,775.00
Amt Left: 65.71% $561,185.00
Delta: -7.59% -$99,810.00
$1,482,060.00
Over/Under Est: 23.77% $284,655.00
Amt Left: 73.54% $628,065.00
Delta: -4.73% -$66,880.00
Over/Under Est: 34.72% $415,740.00
Amt Left: 88.89% $759,150.00
Delta: -8.84% -$131,085.00

Bid Items & Bid Tabulations

30 Total 0 of 30
BOWIE  |  IH0030  |  ATLANTA  |  6299-32-001  |  02/01/2018  |  $1,197,405.00  |  BPM - 629932001  |  BRIDGE PREVENT MAINT  |  250 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
CDM HOLDINGS, LLC
STATELINE CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
HARTBEAT CONSTRUCTION
LC JORDAN & SON
PIERCE R & B LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
SJ&J CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
CHAMPION INFRASTRUCTURE, LLC
REMOVING CONC (RIPRAP)
SY 398.000 $15.000 $5.000 $22.000 $22.000 $18.000 $20.000 $22.000 $125.000 $40.000 $30.000 $60.000
REMOVE CONC (WINGWALL)
CY 44.000 $350.000 $110.000 $125.000 $350.000 $250.000 $100.000 $250.000 $180.000 $150.000 $300.000 $1,400.000
REMOVING CONCRETE(MOW STRIP)
LF 960.000 $12.000 $7.000 $12.000 $10.000 $7.000 $20.000 $35.000 $10.000 $10.000 $15.000 $65.000
EXCAVATION (CHANNEL)
CY 650.000 $10.000 $22.000 $14.000 $35.000 $25.000 $15.000 $25.000 $40.000 $18.000 $30.000 $60.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 190.000 $15.000 $27.000 $32.000 $40.000 $29.000 $50.000 $55.000 $40.000 $90.000 $35.000 $50.000
FLOWABLE BACKFILL
CY 145.000 $350.000 $175.000 $200.000 $325.000 $250.000 $215.000 $350.000 $180.000 $200.000 $350.000 $210.000
TEMPORARY SPL SHORING
SF 1,400.000 $50.000 $1.000 $23.000 $30.000 $52.000 $10.000 $52.000 $25.000 $12.000 $45.000 $40.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 260.000 $250.000 $110.000 $110.000 $185.000 $330.000 $160.000 $185.000 $200.000 $190.000 $1,000.000 $210.000
CONC STR REPAIR (STANDARD)
SF 4.000 $500.000 $1,400.000 $500.000 $400.000 $380.000 $400.000 $250.000 $400.000 $100.000 $1,000.000 $300.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,850.000 $200.000 $151.000 $145.000 $150.000 $165.000 $185.000 $165.000 $175.000 $130.000 $185.000 $280.000
BEDDING MATERIAL (6 IN)
CY 617.000 $230.000 $145.000 $110.000 $150.000 $110.000 $176.000 $150.000 $100.000 $35.000 $60.000 $240.000
RIPRAP (MOW STRIP)(4 IN)
CY 150.000 $525.000 $450.000 $410.000 $425.000 $490.000 $500.000 $475.000 $550.000 $700.000 $550.000 $875.000
WINGWALL (FW - 0) (HW=10 FT)
EA 1.000 $23,000.000 $13,000.000 $27,510.000 $23,000.000 $17,280.000 $20,000.000 $35,000.000 $20,000.000 $40,000.000 $20,000.000 $26,000.000
WINGWALL (FW - 0) (HW=12 FT)
EA 2.000 $40,000.000 $25,000.000 $38,865.000 $30,000.000 $32,000.000 $30,000.000 $40,000.000 $35,000.000 $50,000.000 $35,000.000 $29,000.000
WINGWALL (FW - S) (HW=8 FT)
EA 1.000 $16,000.000 $13,000.000 $26,410.000 $20,000.000 $17,200.000 $15,000.000 $30,000.000 $12,000.000 $35,000.000 $20,000.000 $22,000.000
WINGWALL (FW - S) (HW=9 FT)
EA 1.000 $20,000.000 $14,000.000 $33,125.000 $22,000.000 $22,500.000 $16,000.000 $30,000.000 $12,000.000 $38,000.000 $25,600.000 $24,000.000
CLEAN EXIST CULVERTS
EA 5.000 $3,000.000 $6,500.000 $2,000.000 $5,000.000 $4,500.000 $10,000.000 $1,000.000 $20,000.000 $2,000.000 $1,500.000 $1,600.000
MOBILIZATION
LS 1.000 $100,000.000 $70,000.000 $100,000.000 $110,000.000 $104,708.000 $120,000.000 $106,000.000 $115,000.000 $420,000.000 $140,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $2,500.000 $3,600.000 $3,200.000 $5,000.000 $6,000.000 $4,000.000 $5,000.000 $16,000.000 $6,000.000 $9,000.000 $7,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,825.000 $22.000 $17.000 $18.000 $20.000 $8.000 $20.000 $18.500 $30.000 $50.000 $35.000 $25.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 150.000 $30.000 $22.000 $24.000 $25.000 $35.000 $25.000 $24.000 $30.000 $70.000 $35.000 $80.000
MTL THRIE-BEAM GD FEN (TIM POST)
EA 1.000 $1,600.000 $1,650.000 $1,500.000 $1,600.000 $1,400.000 $1,500.000 $1,550.000 $800.000 $1,800.000 $2,850.000 $3,200.000
REMOVE METAL BEAM GUARD FENCE
LF 625.000 $4.000 $4.000 $1.000 $5.000 $3.000 $5.000 $4.500 $2.000 $5.000 $3.000 $20.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $250.000 $300.000 $300.000 $350.000 $190.000 $400.000 $325.000 $400.000 $500.000 $500.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $275.000 $250.000 $300.000 $300.000 $200.000 $400.000 $275.000 $400.000 $500.000 $500.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 13.000 $2,500.000 $2,150.000 $2,350.000 $2,500.000 $2,500.000 $300.000 $2,350.000 $2,500.000 $2,500.000 $2,850.000 $3,600.000
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $300.000 $250.000 $250.000 $300.000 $300.000 $400.000 $375.000 $400.000 $600.000 $850.000 $600.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 3.000 $50.000 $48.000 $50.000 $55.000 $50.000 $65.000 $52.000 $50.000 $90.000 $100.000 $60.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 18.000 $60.000 $42.000 $50.000 $50.000 $40.000 $65.000 $45.000 $50.000 $90.000 $100.000 $60.000
CONCRETE BEAM REPAIR
EA 3.000 $2,500.000 $6,000.000 $40,000.000 $12,000.000 $3,000.000 $12,000.000 $10,000.000 $4,000.000 $10,000.000 $22,000.000 $9,500.000
Totals: $1,197,405.000 $853,995.000 $1,036,476.000 $1,074,471.000 $1,077,777.000 $1,084,167.000 $1,174,447.000 $1,315,370.000 $1,415,180.000 $1,482,060.000 $1,613,145.000