Show Job Controls
Bid Cobra

BOWIE COLLEGE (0919-19-084)

Items: 113

County: BOWIE
Length: 2.2000 MILES
Highway: COLLEGE
District: ATLANTA
Control Number: 0919-19-084
DBE Goal: 0.0%
Project: STP 2023(024)TAPS
Guaranty: $87,000.00
Time: 158 WORKING DAYS
Engineer's Estimate: $4,024,993.95
Date: 10/09/2025 (8 months ago)
Contract Number: 10253216
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Project ID: A00179426
Contract Type: Federal
Project Description: CONSTRUCT SIDEWALKS AND BIKE LANES IN TEXARKANA ALONG COLLEGE DRIVE AND INCLUDE BIKE AND PEDESTRIAN SIGNALIZATION IMPROVEMENTS AT SL 14.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$4,024,993.95
$2,531,388.30
Over/Under Est: -37.11% -$1,493,605.65
Over/Under Est: -28.62% -$1,152,047.86
Amt Left: 13.49% $341,557.79
$3,203,325.00
Over/Under Est: -20.41% -$821,668.95
Amt Left: 26.54% $671,936.70
Delta: -11.50% -$330,378.91
Over/Under Est: -5.57% -$224,253.35
Amt Left: 50.14% $1,269,352.30
Delta: -18.65% -$597,415.60
Over/Under Est: 8.25% $331,885.35
Amt Left: 72.11% $1,825,491.00
Delta: -14.63% -$556,138.70
Over/Under Est: 18.6% $748,603.78
Amt Left: 88.58% $2,242,209.43
Delta: -9.56% -$416,718.43

Bid Items & Bid Tabulations

113 Total 0 of 113
BOWIE  |  COLLEGE  |  ATLANTA  |  0919-19-084  |  10/09/2025  |  $4,024,993.95  |  STP 2023(024)TAPS  |  BICYCLE AND PEDESTRIAN IMPRVS  |  158 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
GARRET SHIELDS INFRASTRUCTURE
TI-ZACK CONCRETE, LLC
GREY SKY CONSTRUCTION LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
EAST TEXAS BRIDGE, INC.
PREP ROW (TREE REMOVE) (0"-12" DIA)
EA 12.000 $750.000 $300.000 $500.000 $330.000 $1,500.000 $250.000 $1,000.000
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 12.000 $1,750.000 $800.000 $1,000.000 $880.000 $2,500.000 $350.000 $2,000.000
PREP ROW (TREE REMOVE) (24"-36" DIA)
EA 1.000 $2,250.000 $2,500.000 $2,500.000 $2,750.000 $3,500.000 $500.000 $5,000.000
REMOV CONC (RIPRAP)
SY 12.000 $68.000 $25.000 $50.000 $76.000 $50.000 $25.000 $100.000
REMOV CONC (DRIVEWAYS)
SY 4,680.000 $28.500 $25.000 $30.000 $24.360 $20.000 $10.000 $50.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 362.000 $25.750 $25.000 $30.000 $25.190 $20.000 $10.000 $50.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 2,460.000 $20.000 $10.000 $10.000 $11.120 $20.000 $10.000 $20.000
REMOV CONC (RAIL)
LF 40.000 $150.000 $50.000 $50.000 $45.600 $100.000 $35.000 $100.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 424.000 $38.000 $15.000 $10.000 $21.510 $20.000 $65.000 $50.000
RMV (6") TRT/UNTRT BASE & ASPH PAV
SY 821.000 $40.000 $15.000 $10.000 $22.220 $20.000 $50.000 $50.000
EXCAV (ROADWAY)
CY 74.000 $157.000 $25.000 $50.000 $65.940 $20.000 $150.000 $100.000
EMBANK (FNL)(DC)(TY B)
CY 9.000 $68.000 $50.000 $50.000 $101.330 $50.000 $60.000 $300.000
FURN & PLACE TOPSOIL (4")
SY 12,635.000 $5.250 $3.000 $5.000 $5.770 $10.000 $12.000 $5.000
BLOCK SODDING
SY 12,671.000 $8.000 $5.000 $8.000 $5.500 $10.000 $8.000 $8.000
VEGETATIVE WATERING
TGL 380.100 $52.000 $100.000 $50.000 $1.100 $15.000 $250.000 $65.000
RDSIDE AMENITY
EA 2.000 $270,000.000 $5,000.000 $500.000 $110,000.000 $25,000.000 $425,000.000 $100,000.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 245.000 $82.500 $350.000 $50.000 $115.500 $80.000 $35.000 $500.000
FLOWABLE BACKFILL
CY 16.000 $634.000 $350.000 $600.000 $110.000 $350.000 $400.000 $650.000
TEMPORARY SPL SHORING
SF 278.000 $64.000 $55.000 $40.000 $49.500 $85.000 $125.000 $150.000
CL A CONC (SEAL)
CY 2.000 $900.000 $500.000 $2,000.000 $871.420 $2,500.000 $400.000 $1,000.000
RETAINING WALL (CAST-IN-PLACE)
SF 3,210.000 $115.000 $55.000 $90.000 $63.530 $100.000 $35.000 $95.000
RIPRAP (CONC)(4 IN)
CY 4.250 $2,500.000 $1,000.000 $600.000 $871.420 $550.000 $1,000.000 $2,000.000
RAIL (TY T552)
LF 40.000 $450.000 $250.000 $200.000 $550.000 $210.000 $140.000 $300.000
RAIL (HANDRAIL)(TY E)
LF 161.000 $200.000 $180.000 $200.000 $253.000 $185.000 $225.000 $300.000
RAIL (HANDRAIL)(TY F)
LF 93.000 $220.000 $100.000 $80.000 $110.000 $185.000 $250.000 $200.000
CONC BOX CULV (6 FT X 3 FT)
LF 6.000 $400.000 $600.000 $1,000.000 $1,100.000 $1,000.000 $1,500.000 $1,500.000
RC PIPE (CL III)(24 IN)
LF 28.000 $400.000 $100.000 $150.000 $165.000 $120.000 $135.000 $100.000
INLET (COMPL)(PCU)(3FT)(LEFT)
EA 1.000 $12,000.000 $10,000.000 $5,000.000 $11,000.000 $12,500.000 $9,500.000 $10,000.000
WINGWALL (PW - 1) (HW=4 FT)
EA 1.000 $30,000.000 $16,000.000 $5,000.000 $27,500.000 $15,000.000 $3,500.000 $14,000.000
CAST-IN-PLACE TRENCH DRAIN
LF 16.000 $800.000 $650.000 $500.000 $605.000 $5,000.000 $1,000.000 $1,000.000
REMOV STR (HEADWALL)
EA 1.000 $1,600.000 $1,000.000 $2,000.000 $165.000 $2,500.000 $1,000.000 $2,000.000
REMOVE STR (RAIL)
LF 8.000 $175.000 $50.000 $100.000 $165.000 $100.000 $100.000 $75.000
REMOV STR (SMALL)
EA 7.000 $3,800.000 $100.000 $1,000.000 $165.000 $500.000 $2,500.000 $3,000.000
REMOV STR (PIPE)
EA 1.000 $631.000 $500.000 $1,000.000 $165.000 $500.000 $500.000 $3,000.000
MOBILIZATION
LS 1.000 $366,000.000 $400,000.000 $300,000.000 $278,866.800 $400,000.000 $450,000.000 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $7,500.000 $2,500.000 $4,000.000 $11,650.000 $40,000.000 $2,500.000 $25,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 493.000 $2.250 $4.000 $6.000 $0.110 $4.000 $6.000 $8.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 493.000 $1.750 $1.000 $1.000 $0.110 $2.000 $3.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,577.000 $9.000 $10.000 $6.000 $0.110 $12.000 $10.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,577.000 $2.750 $1.000 $1.000 $0.110 $8.000 $2.000 $1.000
CONC CURB & GUTTER (TY II)
LF 1,120.000 $60.000 $45.000 $40.000 $57.450 $65.000 $120.000 $75.000
CONC CURB (SLOTTED)
LF 99.000 $60.000 $75.000 $40.000 $57.450 $125.000 $100.000 $100.000
CONC CURB (TY C1)
LF 136.000 $136.000 $150.000 $50.000 $129.940 $65.000 $55.000 $750.000
CONC CURB (TY C2)
LF 30.000 $416.500 $50.000 $40.000 $259.890 $65.000 $200.000 $800.000
DRIVEWAYS (CONC)
SY 2,125.000 $130.000 $100.000 $120.000 $127.810 $100.000 $200.000 $240.000
DRIVEWAYS (CONC) (HES)
SY 427.000 $145.000 $110.000 $150.000 $132.870 $125.000 $200.000 $300.000
CONC SIDEWALKS (4")
SY 5,038.000 $105.000 $75.000 $120.000 $117.690 $75.000 $110.000 $160.000
CONC SIDEWALKS (6")
SY 206.000 $151.000 $85.000 $120.000 $139.460 $85.000 $120.000 $200.000
CURB RAMPS (TY 1)
EA 10.000 $3,200.000 $1,500.000 $3,000.000 $2,640.660 $3,250.000 $5,000.000 $2,000.000
CURB RAMPS (TY 2)
EA 3.000 $3,625.000 $1,800.000 $3,000.000 $2,640.660 $3,250.000 $6,000.000 $2,000.000
CURB RAMPS (TY 3)
EA 5.000 $3,500.000 $1,800.000 $3,000.000 $2,640.660 $3,250.000 $7,000.000 $3,000.000
CURB RAMPS (TY 7)
EA 60.000 $3,500.000 $1,100.000 $3,000.000 $2,640.660 $3,250.000 $4,900.000 $2,000.000
CURB RAMPS (TY 10)
EA 3.000 $3,500.000 $1,100.000 $3,000.000 $2,640.660 $3,250.000 $5,000.000 $3,000.000
CONC SIDEWALKS (SPECIAL)
SY 1,345.000 $225.000 $95.000 $120.000 $177.820 $150.000 $125.000 $250.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 23.000 $375.000 $350.000 $128.000 $605.000 $850.000 $350.000 $400.000
CONDT (PVC) (SCH 40) (2")
LF 63.000 $21.000 $20.000 $30.000 $20.420 $25.000 $40.000 $22.000
ELEC CONDR (NO.6) BARE
LF 105.000 $3.000 $4.000 $5.000 $4.070 $3.000 $4.000 $4.000
ALUMINUM SIGNS (TY A)
SF 8.000 $1,320.000 $45.000 $52.000 $40.810 $50.000 $100.000 $40.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 110.000 $905.000 $1,600.000 $800.000 $495.000 $1,150.000 $850.000 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $950.000 $1,350.000 $800.000 $935.000 $1,150.000 $850.000 $800.000
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
EA 1.000 $350.000 $550.000 $500.000 $495.000 $1,150.000 $500.000 $300.000
REMOVE SM RD SN SUP&AM
EA 46.000 $175.000 $100.000 $100.000 $495.000 $50.000 $125.000 $150.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 578.000 $1.750 $1.500 $1.100 $1.650 $6.000 $2.000 $1.700
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 78.000 $4.500 $5.000 $4.500 $5.500 $12.000 $6.000 $6.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 1,097.000 $11.500 $6.500 $7.000 $7.150 $20.000 $8.000 $7.000
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 23.000 $275.000 $140.000 $180.000 $154.000 $250.000 $165.000 $150.000
REFL PAV MRK TY I(W)(DBL ARROW)(090MIL)
EA 7.000 $235.000 $220.000 $200.000 $242.000 $500.000 $300.000 $250.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 8.000 $300.000 $170.000 $250.000 $187.000 $250.000 $250.000 $200.000
REFL PAV MRK TY I (W)(SYMBOL)(090MIL)
EA 2.000 $500.000 $250.000 $75.000 $275.000 $250.000 $300.000 $280.000
REFL PAV MRK TY I (W)(BIKE ARW)(090MIL)
EA 53.000 $190.000 $120.000 $100.000 $132.000 $250.000 $180.000 $130.000
REFL PAV MRK TY I (W)(BIKE ARW)(100MIL)
EA 2.000 $107.000 $120.000 $100.000 $132.000 $250.000 $180.000 $130.000
REFL PAV MRK TY I(W)(BIKE SYML)(090MIL)
EA 49.000 $175.000 $175.000 $150.000 $192.500 $250.000 $225.000 $200.000
REFL PAV MRK TY I(W)(BIKE SYML)(100MIL)
EA 2.000 $191.000 $175.000 $150.000 $192.500 $250.000 $225.000 $200.000
REFL PAV MRK TY I(W)(BIKE WORD)(090MIL)
EA 4.000 $190.000 $200.000 $250.000 $220.000 $250.000 $250.000 $220.000
REFL PAV MRK TY I (W)(BIKE DOT)(090MIL)
EA 65.000 $6.000 $5.000 $2.000 $5.500 $250.000 $6.000 $6.000
REFL PAV MRK TY I (Y)4"(DOT)(090MIL)
LF 650.000 $6.000 $2.000 $1.500 $2.200 $0.500 $3.000 $2.200
RE PROFILE PM TY I(W)4"(SLD)(090MIL)
LF 19,654.000 $0.800 $1.500 $0.700 $1.650 $0.500 $2.000 $2.000
RE PROFILE PM TY I(Y)4"(SLD)(090MIL)
LF 20,314.000 $0.800 $1.500 $0.700 $1.650 $0.500 $2.000 $2.000
ALL-WTHER PM TY I (W)4"(SLD)(100MIL)
LF 599.000 $1.250 $3.000 $0.700 $3.300 $0.500 $4.000 $3.300
ALL-WTHER PM TY I (Y)4"(SLD)(100MIL)
LF 321.000 $1.500 $3.000 $0.700 $3.300 $0.500 $4.000 $3.300
PAVEMENT SLER 4"
LF 920.000 $0.750 $1.000 $0.500 $1.100 $1.000 $2.500 $1.100
PAVEMENT SLER 12"
LF 78.000 $1.500 $2.000 $0.750 $2.200 $6.000 $3.000 $2.200
PAVEMENT SLER (BIKE ARROW)
EA 2.000 $64.000 $100.000 $15.000 $110.000 $250.000 $135.000 $110.000
PAVEMENT SLER (BIKE SYMBOL)
EA 2.000 $58.000 $100.000 $15.000 $110.000 $250.000 $135.000 $110.000
REFL PAV MRKR TY II-A-A
EA 9.000 $7.000 $10.000 $6.200 $11.000 $6.000 $15.000 $11.000
ELIM EXT PM & MRKS (4")
LF 19,284.000 $0.950 $0.650 $0.900 $0.720 $0.650 $1.000 $0.750
ELIM EXT PM & MRKS (8")
LF 872.000 $1.600 $1.000 $1.300 $1.100 $6.000 $1.500 $1.100
ELIM EXT PM & MRKS (24")
LF 396.000 $5.500 $4.000 $2.800 $4.400 $12.000 $5.000 $4.500
ELIM EXT PM & MRKS (ARROW)
EA 19.000 $100.000 $100.000 $31.000 $110.000 $250.000 $125.000 $110.000
ELIM EXT PM & MRKS (WORD)
EA 3.000 $100.000 $100.000 $31.000 $110.000 $250.000 $125.000 $110.000
PAV SURF PREP FOR MRK (4")
LF 41,538.000 $0.750 $0.050 $0.150 $0.060 $0.500 $0.100 $0.060
PAV SURF PREP FOR MRK (8")
LF 503.000 $0.450 $0.100 $0.250 $0.110 $6.000 $0.100 $0.150
PAV SURF PREP FOR MRK (12")
LF 78.000 $3.000 $0.500 $0.400 $0.550 $10.000 $0.650 $0.550
PAV SURF PREP FOR MRK (24")
LF 1,068.000 $1.750 $1.000 $0.700 $1.100 $12.000 $1.500 $1.100
PAV SURF PREP FOR MRK (ARROW)
EA 22.000 $35.000 $50.000 $6.250 $55.000 $250.000 $55.000 $55.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 7.000 $38.000 $50.000 $6.250 $55.000 $500.000 $55.000 $55.000
PAV SURF PREP FOR MRK (WORD)
EA 8.000 $40.000 $50.000 $6.250 $55.000 $250.000 $55.000 $55.000
PAV SURF PREP FOR MRK (SYMBOL)
EA 2.000 $15.000 $50.000 $6.250 $55.000 $500.000 $55.000 $55.000
PAV SURF PREP FOR MRK (BIKE ARROW)
EA 52.000 $28.000 $50.000 $6.250 $55.000 $500.000 $55.000 $55.000
PAV SURF PREP FOR MRK (BIKE SYMBOL)
EA 51.000 $32.000 $50.000 $6.250 $55.000 $500.000 $55.000 $55.000
PAV SURF PREP FOR MRK (BIKE WORD)
EA 3.000 $40.000 $50.000 $6.250 $55.000 $500.000 $55.000 $55.000
PAV SURF PREP FOR MRK (BIKE DOT)
EA 65.000 $35.000 $1.000 $1.250 $1.100 $500.000 $2.000 $1.100
PAV SURF PREP FOR MRK (RPM)
EA 9.000 $3.000 $1.000 $1.250 $1.100 $50.000 $2.000 $1.100
PED SIG SEC (LED)(COUNTDOWN)
EA 10.000 $1,200.000 $1,254.000 $1,500.000 $1,139.600 $8,500.000 $1,300.000 $1,200.000
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 255.000 $2.800 $4.000 $4.380 $5.340 $3.000 $3.000 $5.000
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 229.000 $3.500 $4.000 $4.560 $5.860 $3.000 $4.000 $6.000
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 1,165.000 $4.250 $4.200 $5.250 $6.190 $3.000 $4.500 $6.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 2.000 $9,000.000 $9,892.000 $12,000.000 $12,826.000 $12,500.000 $12,000.000 $13,000.000
PED POLE ASSEMBLY
EA 6.000 $3,500.000 $4,850.000 $6,000.000 $6,765.000 $6,500.000 $4,000.000 $7,000.000
PEDESTRIAN PUSH BUTTON POLE
EA 1.000 $3,500.000 $1,652.000 $2,065.000 $5,002.800 $3,850.000 $4,000.000 $6,000.000
REMOVE PED POLE ASSEMBLY
EA 1.000 $1,100.000 $2,500.000 $3,125.000 $559.900 $1,500.000 $750.000 $600.000
PED DETECT PUSH BUTTON (STANDARD)
EA 11.000 $700.000 $662.000 $825.000 $1,224.300 $1,850.000 $1,200.000 $1,400.000
REPLACE OF PEDESTRIAN PUSH BUTTONS
EA 1.000 $700.000 $720.000 $900.000 $512.600 $1,150.000 $1,800.000 $500.000
Totals: $4,024,993.950 $2,531,388.300 $2,872,946.090 $3,203,324.995 $3,800,740.600 $4,356,879.300 $4,773,597.730
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
RAILROAD FORCE ACCOUNT WORK (PART) $30,000.00
Total: $60,000.00