BOWIE IH 30 (0610-06-080)

Items: 20

County: BOWIE
Length: N/A
Highway: IH 30
District: ATLANTA
Control Number: 0610-06-080
DBE Goal: N/A
Project: STP 1702(398)HES
Guaranty: N/A
Time: 96 WORKING DAYS
Engineer's Estimate: $678,003.70
Date: 06/06/2017 (9 years ago)
Contract Number: N/A
Type: INSTALL SAFETY LIGHTING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$678,003.70
$640,525.98
Over/Under Est: -5.53% -$37,477.72
Over/Under Est: 3.11% $21,115.72
Amt Left: 9.15% $58,593.44
Over/Under Est: 7.61% $51,584.80
Amt Left: 13.9% $89,062.52
Delta: -4.36% -$30,469.08
Over/Under Est: 37.55% $254,584.30
Amt Left: 45.6% $292,062.02
Delta: -27.82% -$202,999.50

Bid Items & Bid Tabulations

20 Total 0 of 20
BOWIE  |  IH 30  |  ATLANTA  |  0610-06-080  |  06/06/2017  |  $678,003.70  |  STP 1702(398)HES  |  INSTL SAFETY LIGHTING  |  96 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SOUTH TEXAS ILLUMINATION, LLC
AMERICAN LIGHTING AND SIGNALIZATION, INC.
CROSS PLUS CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 2.000 $1,121.000 $1,074.000 $1,508.330 $800.000 $1,000.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 150.000 $548.000 $500.000 $531.740 $678.000 $800.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 20.000 $188.000 $190.000 $177.930 $400.000 $210.000
RIPRAP (CONC)(CL B)
CY 19.000 $390.000 $412.000 $917.220 $600.000 $650.000
MOBILIZATION
LS 1.000 $44,343.600 $64,818.000 $65,804.940 $70,000.000 $93,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $7,800.000 $4,500.000 $5,550.680 $10,000.000 $15,000.000
REMOVE RD IL ASM (TRANS-BASE)
EA 22.000 $540.000 $514.000 $619.520 $900.000 $1,000.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 2.000 $3,270.000 $3,310.000 $3,305.580 $3,500.000 $4,000.000
HI MST IL POLE (150 FT)( 80 MPH)
EA 6.000 $22,000.000 $23,651.000 $24,140.400 $34,000.000 $25,000.000
CONDT (PVC) (SCH 40) (2")
LF 5,870.000 $7.700 $7.500 $9.050 $4.000 $15.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 1,137.000 $15.000 $9.000 $19.560 $25.000 $30.000
ELEC CONDR (NO.6) BARE
LF 7,007.000 $1.300 $1.200 $1.120 $1.500 $2.000
ELEC CONDR (NO.6) INSULATED
LF 15,982.000 $1.500 $1.190 $1.120 $1.500 $2.000
GROUND BOX TY A (122311)
EA 6.000 $722.000 $515.000 $744.840 $600.000 $650.000
GROUND BOX TY A (122311)W/APRON
EA 24.000 $840.000 $580.000 $849.490 $600.000 $750.000
REMOVE ELECTRICAL SERVICES
EA 1.000 $500.000 $385.000 $1,377.740 $1,200.000 $1,000.000
ELC SRV TY A 120/240 060(SS)SS(E)SP(O)
EA 1.000 $5,100.000 $5,200.000 $5,628.120 $3,500.000 $5,000.000
ELC SRV TY A 240/480 060(SS)SS(E)SP(O)
EA 2.000 $5,500.000 $5,429.000 $5,741.870 $3,500.000 $5,000.000
LED HI MST IL ASM (6 FIXT)(ASYM)(TY A)
EA 6.000 $30,100.000 $26,800.000 $26,845.000 $15,000.000 $30,000.000
REPLC LED HI MST IL(6 FIXT)(ASYM)(TY A)
EA 2.000 $8,000.000 $9,830.000 $10,042.990 $15,000.000 $15,000.000
Totals: $678,003.700 $640,525.980 $699,119.420 $729,588.500 $932,588.000