BOWIE SH 8 (0061-02-033)

Items: 24

County: BOWIE
Length: N/A
Highway: SH 8
District: ATLANTA
Control Number: 0061-02-033
DBE Goal: 0.0%
Project: STP 2B24(043)HES
Guaranty: N/A
Time: 210 WORKING DAYS
Engineer's Estimate: $1,308,802.40
Date: 06/05/2024 (2 years ago)
Contract Number: N/A
Type: INSTALL ILLUMINATION
Mail/Deliver Bids To: N/A
CHRISTINA TROWLER
KENNETH BURNS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,308,802.40
$1,359,816.40
Over/Under Est: 3.9% $51,014.00
Over/Under Est: 10.89% $142,561.10
Amt Left: 6.73% $91,547.10
$1,634,526.70
Over/Under Est: 24.89% $325,724.30
Amt Left: 20.2% $274,710.30
Delta: -12.62% -$183,163.20
$1,962,317.50
Over/Under Est: 49.93% $653,515.10
Amt Left: 44.31% $602,501.10
Delta: -20.05% -$327,790.80
Subcontractor Percentage Amount
SAFETEX,INC. 5.40% $73,430.09
Total: 5.40% $73,430.09

Bid Items & Bid Tabulations

24 Total 0 of 24
BOWIE  |  SH 8  |  ATLANTA  |  0061-02-033  |  06/05/2024  |  $1,308,802.40  |  STP 2B24(043)HES  |  INSTL ILLUM  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VACA UNDERGROUND UTILITIES INC
WG ENGINEERING & CONSTRUCTION, LLC
YUNEX LLC
FNH CONSTRUCTION, LLC
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 640.000 $240.000 $325.000 $298.000 $343.400 $400.000
RIPRAP (CONC)(CL B)
CY 32.000 $750.000 $700.000 $1,200.000 $1,417.600 $1,000.000
MOBILIZATION
LS 1.000 $120,000.000 $130,000.000 $105,000.000 $195,637.100 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $5,200.000 $2,500.000 $4,658.000 $6,966.500 $12,500.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 64.000 $5,200.000 $6,500.000 $5,759.000 $5,092.600 $8,000.000
CONDT (PVC) (SCH 40) (2")
LF 7,865.000 $10.500 $12.000 $16.500 $17.400 $17.500
CONDT (PVC) (SCH 40) (2") (BORE)
LF 4,637.000 $25.000 $17.000 $30.000 $25.400 $35.000
ELEC CONDR (NO.6) BARE
LF 13,147.000 $1.900 $2.000 $2.000 $2.400 $3.000
ELEC CONDR (NO.6) INSULATED
LF 26,918.000 $2.200 $2.300 $2.000 $2.800 $3.000
GROUND BOX TY A (122311)W/APRON
EA 53.000 $1,200.000 $1,200.000 $1,120.000 $1,772.000 $1,150.000
ELC SRV TY A 120/240 060(NS)AL(E)SP(O)
EA 11.000 $6,300.000 $8,500.000 $7,010.000 $9,540.200 $9,000.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 22.000 $965.000 $900.000 $1,200.000 $1,353.800 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $1,100.000 $1,200.000 $1,316.000 $1,391.800 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SB(P)
EA 1.000 $1,000.000 $1,800.000 $1,379.000 $1,423.700 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 30.000 $620.000 $750.000 $785.000 $840.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 43.000 $250.000 $300.000 $250.000 $154.600 $100.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 567.000 $18.000 $12.000 $30.000 $24.600 $20.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 20.000 $370.000 $290.000 $280.000 $269.800 $250.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 2.000 $420.000 $410.000 $420.000 $429.200 $350.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 2.000 $500.000 $410.000 $500.000 $490.500 $350.000
PREFAB PAV MRK TY C (W) (WORD)
EA 26.000 $400.000 $410.000 $330.000 $367.900 $350.000
REMOVING TRAFFIC SIGNALS
EA 7.000 $4,000.000 $5,000.000 $5,000.000 $5,150.300 $8,500.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 160.000 $12.000 $50.000 $20.000 $36.800 $10.000
TMA (STATIONARY)
DAY 198.000 $375.000 $1.000 $300.000 $245.300 $250.000
Totals: $1,308,802.400 $1,359,816.400 $1,451,363.500 $1,634,526.700 $1,962,317.500