BOWIE US 82 (0046-05-048)

Items: 68

County: BOWIE
Length: 16.2670 MILES
Highway: US 82
District: ATLANTA
Control Number: 0046-05-048
DBE Goal: 0.0%
Project: F 2026(135)
Guaranty: $200,000.00
Time: 312 WORKING DAYS
Engineer's Estimate: $10,155,546.50
Date: 12/02/2025 (6 months ago)
Contract Number: 12253010
Type: CEMENT TRT,FL BS,SURF & PAV MARKS
Project ID: A00058984
Contract Type: Federal
Project Description: REHABILITATE EXISTING 2-LANE ROADWAY
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$10,155,546.50
$10,382,445.26
Over/Under Est: 2.23% $226,898.76
$10,874,696.60
Over/Under Est: 7.08% $719,150.10
Amt Left: 4.74% $492,251.34
$11,276,580.62
Over/Under Est: 11.04% $1,121,034.12
Amt Left: 8.61% $894,135.36
Delta: -3.70% -$401,884.02
Over/Under Est: 22.1% $2,244,178.41
Amt Left: 19.43% $2,017,279.65
Delta: -9.96% -$1,123,144.29
$12,650,763.34
Over/Under Est: 24.57% $2,495,216.84
Amt Left: 21.85% $2,268,318.08
Delta: -2.02% -$251,038.43

Bid Items & Bid Tabulations

68 Total 0 of 68
BOWIE  |  US 82  |  ATLANTA  |  0046-05-048  |  12/02/2025  |  $10,155,546.50  |  F 2026(135)  |  CEMENT TRT,FL BS,SURF & PAV MARKS  |  312 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRUE ROADS CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
RK HALL, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
CDM HOLDINGS
PREPARING ROW
STA 55.000 $1,500.000 $1,950.000 $2,500.000 $1,751.000 $4,500.000 $2,000.000
RMV (12") TRT/UNTRT BASE & ASPH PAV
SY 30,681.000 $6.400 $7.250 $15.400 $13.150 $10.000 $22.500
BACKFILL (TY B)
STA 547.760 $175.000 $180.000 $375.000 $134.010 $350.000 $150.000
BLADING
STA 205.000 $150.000 $275.000 $200.000 $371.210 $200.000 $200.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 121,927.000 $0.600 $0.620 $0.600 $0.570 $0.600 $0.860
BOND FBR MTRX SEED (TEMP)(WARM)
SY 60,964.000 $0.300 $0.600 $0.600 $0.570 $0.500 $0.830
BOND FBR MTRX SEED (TEMP)(COOL)
SY 60,964.000 $0.300 $0.600 $0.600 $0.570 $0.600 $0.830
VEGETATIVE WATERING
TGL 2,031.000 $20.000 $6.000 $6.000 $29.180 $14.500 $75.000
PROOF ROLLING
HR 350.000 $100.000 $70.000 $70.000 $144.230 $50.000 $100.000
FL BS (CMP IN PLACE)(TY A GR 4)(IN VEH)
CY 7,670.000 $106.000 $85.000 $136.000 $92.040 $160.000 $122.500
SP MIXES SP-C PG70-22
TON 15,791.000 $136.000 $147.000 $136.000 $149.630 $150.000 $143.000
SP MIXES SP-D SAC-A PG76-22
TON 18,583.000 $140.000 $144.000 $138.000 $140.320 $148.000 $145.000
TACK COAT
GAL 39,211.000 $3.000 $4.850 $4.750 $6.210 $4.500 $3.000
FLEX PAVEMENT STRUCTURE REPAIR (4"-6")
SY 17,489.000 $42.000 $62.000 $55.000 $56.380 $75.000 $55.000
PLANE ASPH CONC PAV (1.5")
SY 204,032.000 $1.700 $1.750 $2.200 $1.760 $2.500 $7.500
ASPH BINDER(PG 64-22)
GAL 18,636.000 $3.500 $5.750 $4.250 $5.750 $5.000 $3.500
FABRIC
SY 93,179.000 $3.000 $1.000 $1.150 $3.000 $1.300 $1.750
FLOWABLE BACKFILL
CY 1,215.000 $212.000 $275.000 $325.000 $257.500 $235.000 $350.000
RC PIPE (CL III)(18 IN)
LF 388.000 $54.000 $70.000 $80.000 $61.800 $60.000 $100.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 7.000 $770.000 $1,290.000 $1,000.000 $978.500 $1,250.000 $2,000.000
REMOV STR (SET)
EA 7.000 $275.000 $430.000 $225.000 $257.500 $350.000 $500.000
MOBILIZATION
LS 1.000 $865,000.000 $650,000.000 $500,000.000 $690,000.000 $1,250,000.000 $965,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $5,000.000 $7,000.000 $10,000.000 $8,137.300 $10,000.000 $7,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $13,000.000 $18,000.000 $15,000.000 $2,605.190 $20,000.000 $22,500.000
TMA (STATIONARY)
DAY 820.000 $100.000 $70.000 $150.000 $100.000 $120.000 $100.000
TMA (MOBILE OPERATION)
DAY 112.000 $150.000 $145.000 $150.000 $200.000 $180.000 $100.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 108.000 $50.000 $44.000 $45.000 $40.170 $66.000 $65.000
ROCK FILTER DAMS (REMOVE)
LF 108.000 $27.000 $13.000 $13.000 $13.390 $20.000 $17.750
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $4.000 $4.600 $5.000 $4.120 $5.500 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $1.200 $2.300 $2.000 $2.060 $2.000 $1.750
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 12.000 $7,500.000 $5,500.000 $5,000.000 $6,180.000 $4,100.000 $7,500.000
TURNOUTS (ACP)
SY 1,768.000 $100.000 $60.000 $60.000 $128.910 $60.000 $85.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 81,816.000 $0.500 $0.220 $0.350 $0.330 $0.250 $0.130
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 5.000 $700.000 $630.000 $775.000 $566.500 $605.000 $550.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 61.000 $390.000 $265.000 $380.000 $236.900 $250.000 $230.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 4.000 $675.000 $290.000 $420.000 $257.500 $275.000 $250.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $702.000 $775.000 $825.000 $695.250 $750.000 $6,375.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 6.000 $812.000 $860.000 $950.000 $772.500 $825.000 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $970.000 $920.000 $1,020.000 $824.000 $900.000 $800.000
IN SM RD SN SUP&AM TYS80(1)SB(U-1EXT)
EA 1.000 $1,200.000 $1,140.000 $1,300.000 $1,019.700 $1,100.000 $990.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 74.000 $486.000 $540.000 $555.000 $484.100 $520.000 $470.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $620.000 $575.000 $650.000 $515.000 $550.000 $500.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 18.000 $425.000 $402.000 $460.000 $360.500 $400.000 $350.000
REMOVE SM RD SN SUP&AM
EA 109.000 $108.000 $115.000 $100.000 $103.000 $110.000 $100.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 2.000 $285.000 $57.000 $100.000 $51.500 $55.000 $50.000
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 3,007.000 $6.000 $4.700 $4.450 $4.220 $4.500 $4.100
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 7,031.000 $5.000 $4.700 $4.450 $4.220 $4.500 $4.100
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 5,860.000 $5.000 $4.000 $3.800 $3.610 $3.900 $3.500
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 16,364.000 $5.000 $4.000 $3.800 $3.610 $3.900 $3.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 1,200.000 $7.600 $8.000 $7.550 $7.210 $7.750 $7.000
WK ZN PAV MRK SHT TERM RMV (W)(6")
LF 107,330.000 $1.000 $1.150 $1.500 $3.260 $1.300 $0.600
WK ZN PAV MRK SHT TERM RMV (Y)(6")
LF 77,538.000 $1.000 $1.150 $1.500 $3.260 $1.300 $0.600
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 100.000 $1.000 $2.300 $2.200 $2.060 $2.200 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,252.000 $1.300 $1.150 $1.100 $1.030 $1.100 $1.000
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 107,267.000 $1.000 $1.000 $0.920 $0.880 $0.950 $0.850
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 2,187.000 $1.000 $1.150 $1.100 $1.030 $1.100 $1.000
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 72,646.000 $1.000 $1.000 $0.920 $0.880 $0.950 $0.850
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 21,174.000 $1.000 $0.900 $0.860 $0.820 $0.900 $0.800
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 7,989.000 $3.500 $4.900 $4.650 $4.430 $4.750 $4.300
PREFAB PM TY C (W)(12")(SLD)
LF 675.000 $28.000 $9.200 $8.650 $8.240 $9.000 $8.000
PREFAB PM TY C (W)(24")(SLD)
LF 328.000 $17.000 $15.000 $14.650 $13.910 $15.000 $13.500
PREFAB PM TY C (W)(ARROW)
EA 31.000 $150.000 $245.000 $235.000 $221.450 $240.000 $215.000
PREFAB PM TY C (W)(WORD)
EA 14.000 $155.000 $275.000 $260.000 $247.200 $265.000 $240.000
PREFAB PM TY C (W)(RR XING)
EA 4.000 $500.000 $690.000 $650.000 $618.000 $675.000 $600.000
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 6,721.000 $3.500 $4.950 $4.650 $4.430 $4.750 $4.300
REFL PAV MRKR TY I-C
EA 102.000 $5.500 $5.750 $5.500 $5.150 $5.500 $5.000
REFL PAV MRKR TY II-A-A
EA 1,835.000 $5.500 $4.600 $4.350 $4.120 $4.500 $4.000
ELIM EXT PM & MRKS (6")
LF 40,908.000 $0.750 $0.750 $0.700 $0.670 $0.720 $0.650
Totals: $10,155,546.500 $10,382,445.260 $10,874,696.600 $11,276,580.618 $12,399,724.910 $12,650,763.340