BOWIE FM 991 (0010-19-010)
Items: 28
County: BOWIE
Length: N/A
Highway: FM 991
District: ATLANTA
Control Number: 0010-19-010
DBE Goal: N/A
Project: STP 2018(037)HESG
Guaranty: N/A
Time: 137 WORKING DAYS
Engineer's Estimate: $2,925,668.42
Date: 09/07/2017 (8 years ago)
Contract Number: N/A
Type: PROFILE CENTERLINE & EDGELINE MRKS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,925,668.42 | |||
| $2,282,446.78 |
-21.99%
-$643,221.64
|
|||
| $2,316,705.41 |
-20.81%
-$608,963.01
|
1.5%
$34,258.63
|
||
| $3,262,730.75 |
11.52%
$337,062.33
|
42.95%
$980,283.97
|
-40.83%
-$946,025.34
|
|
| $3,427,163.90 |
17.14%
$501,495.48
|
50.15%
$1,144,717.12
|
-5.04%
-$164,433.15
|
|
| $4,503,952.75 |
53.95%
$1,578,284.33
|
97.33%
$2,221,505.97
|
-31.42%
-$1,076,788.85
|
E
Engineer's Estimate
$2,925,668.42
1
Awarded
$2,282,446.78
Over/Under Est:
-21.99%
-$643,221.64
$2,316,705.41
Over/Under Est:
-20.81%
-$608,963.01
Amt Left:
1.5%
$34,258.63
$3,262,730.75
Over/Under Est:
11.52%
$337,062.33
Amt Left:
42.95%
$980,283.97
Delta:
-40.83%
-$946,025.34
$3,427,163.90
Over/Under Est:
17.14%
$501,495.48
Amt Left:
50.15%
$1,144,717.12
Delta:
-5.04%
-$164,433.15
$4,503,952.75
Over/Under Est:
53.95%
$1,578,284.33
Amt Left:
97.33%
$2,221,505.97
Delta:
-31.42%
-$1,076,788.85
Bid Items & Bid Tabulations
28
Total
0 of 28