BOSQUE SH0006 (6318-15-001)

Items: 18

County: BOSQUE
Length: N/A
Highway: SH0006
District: WACO
Control Number: 6318-15-001
DBE Goal: N/A
Project: RMC - 631815001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $2,263,656.50
Date: 07/12/2017 (8 years ago)
Contract Number: N/A
Type: FLAGGING AND TRAFFIC CONTROL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,263,656.50
$2,234,850.00
Over/Under Est: -1.27% -$28,806.50
Over/Under Est: 32.4% $733,481.00
Amt Left: 34.11% $762,287.50
Over/Under Est: 72.32% $1,637,093.50
Amt Left: 74.54% $1,665,900.00
Delta: -30.15% -$903,612.50
Over/Under Est: 80.52% $1,822,769.82
Amt Left: 82.85% $1,851,576.32
Delta: -4.76% -$185,676.32

Bid Items & Bid Tabulations

18 Total 0 of 18
BOSQUE  |  SH0006  |  WACO  |  6318-15-001  |  07/12/2017  |  $2,263,656.50  |  RMC - 631815001  |  FLAGGING AND TRAF CONTROL  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
NIXON ENGINEERING
AREA WIDE PROTECTIVE, INC.
TOTAL HIGHWAY MAINTENANCE, LLC
ALTUS TRAFFIC MANAGEMENT LLC
MOBILIZATION
LS 1.000 $128,131.500 $500,000.000 $40,000.000 $325,000.000 $100,789.470
TMA (STATIONARY)
DAY 3,000.000 $250.000 $200.000 $625.000 $592.000 $795.120
LANE CLOSURE (SETUP AND REMOV)(TY 1)
EA 600.000 $200.000 $1,000.000 $300.000 $300.000 $397.230
LANE CLOSURE (SETUP AND REMOV)(TY 2)
EA 150.000 $200.000 $300.000 $300.000 $300.000 $397.230
LANE CLOSURE (SETUP AND REMOV)(TY 3)
EA 125.000 $250.000 $800.000 $305.000 $300.000 $397.230
LANE CLOSURE (SETUP AND REMOV)(TY 4)
EA 20.000 $275.000 $250.000 $320.000 $375.000 $312.820
LANE CLOSURE (SETUP AND REMOV)(TY 5)
EA 15.000 $450.000 $250.000 $610.000 $425.000 $312.820
LANE CLOSURE (SETUP AND REMOV)(TY 6)
EA 10.000 $750.000 $1,500.000 $635.000 $500.000 $312.820
LANE CLOSURE (MAINTENANCE) (TY 1)
HR 5,400.000 $85.000 $20.000 $44.000 $90.000 $86.980
LANE CLOSURE (MAINTENANCE) (TY 2)
HR 1,350.000 $60.000 $10.000 $44.000 $125.000 $87.980
LANE CLOSURE (MAINTENANCE) (TY 3)
HR 1,125.000 $25.000 $10.000 $44.000 $150.000 $83.720
LANE CLOSURE (MAINTENANCE) (TY 4)
HR 200.000 $25.000 $10.000 $44.000 $150.000 $65.930
LANE CLOSURE (MAINTENANCE) (TY 5)
HR 135.000 $40.000 $10.000 $87.500 $225.000 $84.120
LANE CLOSURE (MAINTENANCE) (TY 6)
HR 100.000 $35.000 $50.000 $87.500 $375.000 $66.290
LANE CLOSURE (SETUP AND REMOV)(TY 18)
HR 250.000 $150.000 $80.000 $43.000 $264.000 $99.390
LANE CLOSURE (SETUP AND REMOV)(TY 21)
HR 3,000.000 $10.000 $30.000 $25.500 $12.500 $5.000
LANE CLOSURE (SETUP AND REMOV)(TY 22)
HR 4,000.000 $40.000 $10.000 $23.500 $39.000 $42.170
LANE CLOSURE (SETUP AND REMOV)(TY 23)
HR 7,500.000 $50.000 $10.000 $32.000 $45.000 $42.170
Totals: $2,263,656.500 $2,234,850.000 $2,997,137.500 $3,900,750.000 $4,086,426.320