BOSQUE SH 317 (0398-01-045)

Items: 87

County: BOSQUE
Length: 0.0000 MILES
Highway: SH 317
District: WACO
Control Number: 0398-01-045
DBE Goal: 6.0%
Project: BR 2025(567)
Guaranty: $100,000.00
Time: 180 WORKING DAYS
Engineer's Estimate: $6,814,396.23
Date: 03/05/2025 (1 year ago)
Contract Number: 3253211
Type: BRIDGE REPLACEMENT
Project ID: A00187704
Contract Type: Federal
Project Description: BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$6,814,396.23
$6,597,547.43
Over/Under Est: -3.18% -$216,848.80
Over/Under Est: -1.71% -$116,671.64
Amt Left: 1.52% $100,177.16
Over/Under Est: 4.47% $304,884.77
Amt Left: 7.91% $521,733.57
Delta: -6.29% -$421,556.41
$7,773,922.51
Over/Under Est: 14.08% $959,526.28
Amt Left: 17.83% $1,176,375.08
Delta: -9.20% -$654,641.51
$7,812,561.37
Over/Under Est: 14.65% $998,165.14
Amt Left: 18.42% $1,215,013.94
Delta: -0.50% -$38,638.86
Subcontractor Percentage Amount
TEXAS CLEAR CUT LLC 9.71% $640,693.47
LONE STAR PAVING COMPANY 4.94% $325,955.28
BEAIRD DRILLING SERVICES, INC. 2.72% $179,473.35
T-BAR FENCE, INC. 1.76% $116,129.82
JB PINNACLE GROUP, LLC 1.25% $82,478.56
AWP SAFETY 0.93% $61,364.05
DIIBS SPECIALISTS, LLC 0.88% $58,064.91
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.74% $48,827.31
TEXAS STEEL INDUSTRIAL PLACING, LLC 0.55% $36,290.57
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.31% $20,454.68
DARKHORSE INDUSTRIES, L.L.C. 0.25% $16,495.71
1 PRIORITY ENVIRONMENTAL SERVICES, LLC 0.17% $11,217.08
SCOTT DERR PAINTING CO, LLC 0.06% $3,958.97
GK CONSTRUCTION, LLC 0.00% $0.00
Total: 24.27% $1,601,403.76

Bid Items & Bid Tabulations

87 Total 0 of 87
BOSQUE  |  SH 317  |  WACO  |  0398-01-045  |  03/05/2025  |  $6,814,396.23  |  BR 2025(567)  |  BRIDGE REPL  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ORION CONSTRUCTION, LLC
MP HEAVY CONSTRUCTION INC
JAMES CONSTRUCTION GROUP, LLC
LAKEY, INC.
ALTUS CONSTRUCTION LLC
PREPARING ROW
STA 18.480 $5,857.620 $10,000.000 $12,000.000 $29,400.000 $3,650.000 $41,863.460
REMOV CONC (DRIVEWAYS)
SY 624.000 $20.000 $14.000 $21.050 $15.630 $24.500 $21.250
REMOV CONC (CURB OR CURB & GUTTER)
LF 175.000 $52.080 $6.500 $19.640 $7.410 $11.000 $9.350
REMOV CONC (APPR SLAB)
SY 223.000 $95.000 $26.000 $24.000 $8.440 $165.000 $318.710
REMOV CONC (FLUME)
SY 104.000 $150.000 $18.000 $30.600 $15.440 $31.310 $26.610
RMV (0"-4") TRT/UNTRT BASE & ASPH PAV
SY 6,767.000 $6.320 $6.000 $5.400 $1.750 $40.000 $3.260
EXCAV (ROADWAY)
CY 1,817.000 $15.000 $25.000 $25.700 $15.000 $23.797 $15.910
EMBANK (FNL)(DC)(TY C)
CY 6,849.000 $37.650 $42.000 $23.480 $25.440 $26.000 $41.250
FURN & PLACE TOPSOIL (4")
SY 9,168.000 $2.090 $2.500 $5.900 $0.310 $19.250 $3.400
DRILL SEED (PERM_RURAL_CLAY)
SY 9,168.000 $0.140 $0.380 $0.460 $0.550 $0.400 $0.340
DRILL SEED (TEMP_WARM_COOL)
SY 9,168.000 $0.090 $0.380 $0.400 $0.500 $0.275 $0.250
VEGETATIVE WATERING
TGL 150.000 $80.000 $50.000 $50.140 $36.890 $34.500 $31.090
SOIL RET BLKT(SL_STEEP_CLAY_SHORT)
SY 788.000 $1.170 $2.750 $2.400 $2.000 $37.700 $45.330
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 2,265.000 $70.000 $95.000 $47.090 $62.750 $50.000 $39.960
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 215.000 $348.180 $355.000 $251.100 $316.280 $360.900 $312.510
LIME TRT (EXIST MATL)(12")
SY 7,957.000 $3.500 $8.000 $5.250 $6.950 $3.800 $3.590
EMULS ASPH (BS OR SUBGR TRT)(CSS-1H)
GAL 9,548.000 $2.350 $4.750 $3.350 $5.000 $14.000 $11.200
FOG SEAL (CSS-1H)
GAL 796.000 $3.000 $6.600 $6.520 $5.000 $2.875 $3.400
ASPH (CRS-2)
GAL 2,387.000 $4.580 $6.600 $4.970 $5.000 $4.760 $4.530
AGGR (TY-D OR L, GR-4)
CY 59.000 $218.290 $450.000 $367.430 $350.000 $197.500 $255.120
SP MIXES SP-C SAC-B PG70-22
TON 1,750.000 $120.600 $210.000 $139.210 $155.000 $135.500 $228.910
TACK COAT
GAL 680.000 $2.600 $6.750 $3.730 $5.000 $4.480 $3.810
CEM STABIL BKFL
CY 224.000 $232.500 $220.000 $274.340 $194.140 $300.000 $247.300
TEMPORARY SPL SHORING
SF 6,057.000 $37.500 $10.500 $28.760 $71.100 $60.000 $32.020
DRILL SHAFT (18 IN)
LF 114.000 $151.190 $200.000 $179.640 $132.010 $375.000 $162.870
DRILL SHAFT (36 IN)
LF 602.000 $324.080 $265.000 $248.300 $189.460 $550.000 $237.340
DRILL SHAFT (48 IN)
LF 240.000 $949.500 $500.000 $737.830 $357.770 $534.300 $451.800
CL B CONC (FLUME)
CY 44.000 $909.180 $750.000 $420.000 $569.580 $1,214.365 $1,032.090
CL C CONC (ABUT)(HPC)
CY 61.800 $1,711.330 $1,900.000 $1,450.000 $780.000 $1,767.750 $1,188.860
CL C CONC (CAP)(HPC)
CY 19.400 $1,650.000 $2,500.000 $1,349.620 $1,605.310 $1,724.630 $3,187.120
CL C CONC (CAP)(HPC)(MASS)
CY 134.300 $1,500.000 $1,350.000 $1,955.000 $773.310 $1,724.630 $1,040.790
CL C CONC (COLUMN)(HPC)
CY 110.400 $1,988.510 $1,600.000 $1,615.000 $985.830 $1,724.630 $1,221.120
REINF CONC SLAB
SF 15,750.000 $29.500 $35.000 $27.000 $35.000 $35.000 $33.910
APPROACH SLAB
CY 64.200 $658.020 $1,000.000 $1,064.650 $593.360 $750.000 $1,011.160
RETAINING WALL (MSE)
SF 5,407.000 $94.250 $90.000 $86.480 $58.790 $70.500 $127.900
PRESTR CONC GIRDER (TX46)
LF 1,117.950 $190.000 $290.000 $238.320 $307.000 $200.000 $267.070
RIPRAP (CONC)(4 IN)
CY 346.000 $1,119.000 $950.000 $642.140 $568.120 $1,000.000 $386.070
RIPRAP (CONC)(6 IN)
CY 24.000 $384.000 $950.000 $435.230 $568.090 $594.070 $1,019.880
RIPRAP (MOW STRIP)(4 IN)
CY 77.000 $643.750 $1,100.000 $649.680 $665.490 $700.000 $560.360
RIPRAP (STONE TY R)(DRY)(18 IN)
CY 41.000 $171.880 $320.000 $250.000 $225.530 $100.000 $280.470
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 14.000 $300.000 $400.000 $244.670 $263.770 $115.000 $97.740
ELASTOMERIC BEARING (F3)
EA 7.000 $6,600.000 $3,500.000 $4,135.200 $3,213.600 $4,000.000 $1,699.800
SLIDING ELASTOMERIC BEARING (ES 3)
EA 7.000 $5,000.000 $3,500.000 $2,804.400 $4,427.290 $5,000.000 $1,699.800
STR STEEL (PLATE GIRDER)
LB 419,200.000 $3.080 $2.750 $2.370 $3.500 $2.860 $2.940
RAIL (TY SSTR)
LF 814.000 $232.500 $125.000 $126.310 $95.000 $101.970 $109.230
RAIL (CLF-RO)
LF 814.000 $102.300 $175.000 $142.500 $151.890 $162.000 $142.780
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 198.000 $166.250 $350.000 $252.180 $211.560 $246.710 $275.540
RC PIPE (CL III)(24 IN)
LF 57.000 $115.000 $125.000 $114.000 $81.140 $127.300 $162.650
RC PIPE (CL III)(30 IN)
LF 30.000 $195.000 $180.000 $148.000 $128.840 $138.800 $122.810
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,775.000 $2,000.000 $4,088.000 $1,610.630 $2,137.850 $1,817.930
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $2,650.000 $4,200.000 $5,702.000 $4,233.920 $3,946.350 $3,353.990
REMOV STR (PIPE)
LF 35.000 $18.000 $20.000 $36.930 $39.820 $31.400 $26.690
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $69,494.860 $150,000.000 $265,830.440 $350,000.000 $127,725.000 $212,553.710
MOBILIZATION
LS 1.000 $600,000.000 $150,000.000 $1,013,641.410 $602,615.260 $995,222.000 $777,544.040
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $8,000.000 $6,000.000 $3,500.000 $3,975.320 $10,000.000 $21,247.440
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 180.000 $143.260 $100.000 $120.330 $132.310 $100.000 $80.230
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $9,331.670 $25,000.000 $11,000.000 $17,509.370 $9,500.000 $8,169.330
TMA (STATIONARY)
DAY 180.000 $183.210 $250.000 $261.050 $717.870 $401.000 $188.910
TMA (MOBILE OPERATION)
HR 40.000 $43.690 $200.000 $90.000 $177.240 $73.950 $62.850
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 40.000 $20.000 $70.000 $47.200 $45.000 $54.300 $46.150
ROCK FILTER DAMS (REMOVE)
LF 40.000 $10.000 $10.000 $13.940 $10.000 $17.030 $14.470
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 159.000 $39.100 $55.000 $28.930 $34.000 $34.000 $28.900
CONSTRUCTION EXITS (REMOVE)
SY 159.000 $14.900 $10.000 $9.290 $12.000 $12.655 $10.760
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,421.000 $9.500 $6.000 $3.300 $3.500 $4.570 $3.880
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,421.000 $4.130 $1.000 $1.080 $1.500 $1.250 $1.170
CONC CURB & GUTTER (TY II)
LF 60.000 $75.000 $70.000 $41.660 $84.010 $62.500 $53.120
DRIVEWAYS (ACP)
SY 744.000 $45.000 $95.000 $62.100 $63.640 $91.155 $77.470
MTL W-BEAM GD FEN (STEEL POST)
LF 925.000 $31.500 $36.000 $21.890 $29.000 $33.000 $29.750
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,850.000 $2,800.000 $1,894.750 $2,250.000 $2,370.000 $2,124.740
REMOVE METAL BEAM GUARD FENCE
LF 958.000 $2.810 $3.250 $4.950 $2.500 $3.000 $2.740
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,075.000 $3,800.000 $2,503.080 $2,950.000 $3,331.540 $2,831.470
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $350.000 $325.000 $600.000 $250.000 $300.000 $271.970
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 11.000 $305.000 $400.000 $424.630 $385.000 $340.200 $436.280
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 8.000 $1,025.000 $1,000.000 $373.320 $720.000 $1,075.000 $815.900
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $675.000 $1,700.000 $627.910 $935.000 $1,000.000 $1,059.540
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 9.000 $20.000 $50.000 $46.200 $38.000 $50.000 $22.100
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 13.000 $42.500 $50.000 $46.200 $38.000 $45.000 $24.360
RE PM TY II (W) 6" (SLD)
LF 3,280.000 $0.790 $1.800 $0.760 $0.430 $0.190 $0.180
RE PM TY II (Y) 6" (SLD)
LF 3,280.000 $0.480 $1.780 $0.770 $0.420 $0.190 $0.190
PAVEMENT SLER 6"
LF 6,560.000 $0.800 $0.100 $0.540 $0.350 $1.000 $0.390
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 3,280.000 $0.680 $2.840 $1.010 $1.250 $2.250 $0.680
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 3,280.000 $0.940 $2.840 $0.990 $1.250 $2.250 $0.660
REFL PAV MRKR TY II-A-A
EA 47.000 $5.910 $21.000 $6.900 $8.900 $6.500 $4.670
ELIM EXT PM & MRKS (4")
LF 7,192.000 $1.550 $1.050 $1.510 $0.760 $1.630 $0.640
PAV SURF PREP FOR MRK (6")
LF 6,560.000 $0.400 $0.430 $0.240 $0.040 $1.000 $0.170
PAV SURF PREP FOR MRK (RPM)
EA 47.000 $6.540 $4.250 $1.510 $1.600 $0.440 $1.030
ANTI-GRAFFITI COATNG (PERMNENT-TY III)
SF 2,416.000 $2.000 $2.500 $2.040 $2.850 $3.000 $1.940
Totals: $6,814,396.230 $6,597,547.430 $6,697,724.592 $7,119,281.011 $7,773,922.507 $7,812,561.360
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FORCE ACCOUNT WORK (NON-PART) $266,640.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $60,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,000.00
Total: $351,640.00