BOSQUE SH 144 (0386-02-026)

Items: 57

County: BOSQUE
Length: N/A
Highway: SH 144
District: WACO
Control Number: 0386-02-026
DBE Goal: N/A
Project: F 2024(112)
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $5,257,067.94
Date: 10/06/2023 (2 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$5,257,067.94
$4,557,803.14
Over/Under Est: -13.3% -$699,264.80
Over/Under Est: -12.99% -$682,974.25
Amt Left: 0.36% $16,290.55
Over/Under Est: -12.88% -$677,213.08
Amt Left: 0.48% $22,051.72
Delta: -0.13% -$5,761.17
Over/Under Est: -12.49% -$656,598.45
Amt Left: 0.94% $42,666.35
Delta: -0.45% -$20,614.63
Subcontractor Percentage Amount
STX CIVIL 5.41% $246,577.15
HJC FARMS, INC. 2.80% $127,618.49
D. I. J. CONSTRUCTION, INC. 2.44% $111,210.40
PROFESSIONAL TRAFFIC CONTROL LLC 0.32% $14,584.97
KING GEORGE TRAFFIC SOLUTIONS LLC 0.25% $11,394.51
NIXON ENGINEERING 0.14% $6,380.92
DALLAS LITE AND BARRICADE, INC. 0.00% $0.00
Total: 11.36% $517,766.44

Bid Items & Bid Tabulations

57 Total 0 of 57
BOSQUE  |  SH 144  |  WACO  |  0386-02-026  |  10/06/2023  |  $5,257,067.94  |  F 2024(112)  |  SURF/ROADWAY RESTOR  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
KNIFE RIVER CORPORATION - SOUTH
NORTHEASTERN PAVERS, LLC
PREPARING ROW
STA 8.000 $1,219.100 $3,000.000 $1,950.000 $920.000 $1,100.000
BACKFILL (TY A OR B)
STA 300.000 $350.000 $250.000 $171.000 $190.000 $260.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 20,027.000 $65.000 $63.000 $59.500 $59.000 $58.000
PLANE ASPH CONC PAV(MICRO-MLLING)(1")
SY 104,551.000 $1.500 $1.250 $1.650 $1.250 $2.000
CEM STABIL BKFL
CY 149.000 $188.350 $225.000 $300.000 $210.000 $305.000
CUT & RESTORE ASPH PAVING
SY 84.000 $102.200 $150.000 $150.000 $260.000 $210.000
TRENCH EXCAVATION PROTECTION
LF 122.000 $116.000 $15.000 $10.000 $21.000 $12.250
TEMPORARY SPL SHORING
SF 296.000 $64.800 $25.000 $80.000 $52.000 $20.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 16.700 $251.700 $300.000 $300.000 $210.000 $365.000
RIPRAP (MOW STRIP)(4 IN)
CY 44.000 $497.300 $800.000 $675.000 $765.000 $825.000
CONC BOX CULV (4 FT X 2 FT)
LF 116.000 $401.350 $500.000 $500.000 $842.000 $610.000
CONC BOX CULV (6 FT X 3 FT)
LF 64.000 $627.600 $750.000 $750.000 $1,000.000 $915.000
WINGWALL (PW - 1) (HW=4 FT)
EA 2.000 $17,766.000 $25,000.000 $9,500.000 $8,400.000 $11,600.000
WINGWALL (PW - 1) (HW=5 FT)
EA 2.000 $21,278.000 $27,500.000 $11,000.000 $10,500.000 $13,500.000
REMOV STR (PIPE)
LF 202.000 $20.800 $25.000 $15.000 $63.000 $20.000
MOBILIZATION
LS 1.000 $468,369.810 $315,000.000 $340,600.000 $379,000.000 $405,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $7,000.000 $5,000.000 $2,500.000 $10,000.000 $7,250.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 900.000 $4.400 $5.000 $6.000 $9.750 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 900.000 $1.600 $1.000 $1.000 $2.100 $3.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 1.000 $3,812.000 $7,500.000 $7,900.000 $8,500.000 $8,000.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 240.000 $20.700 $50.000 $47.000 $48.000 $75.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 240.000 $11.500 $50.000 $47.000 $40.000 $30.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 240.000 $17.000 $50.000 $47.000 $46.000 $75.000
RUMBLE STRIPS (SHOULDER)
LF 58,256.300 $0.200 $0.200 $0.160 $0.300 $0.250
RUMBLE STRIPS (CENTERLINE)
LF 29,128.150 $0.200 $0.200 $0.200 $0.300 $0.350
MTL W-BEAM GD FEN (STEEL POST)
LF 625.000 $34.800 $40.000 $26.500 $27.900 $35.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,412.000 $1,500.000 $1,100.000 $1,150.000 $1,350.000
REMOVE METAL BEAM GUARD FENCE
LF 350.000 $2.200 $5.000 $3.000 $3.150 $3.750
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,150.000 $3,500.000 $2,800.000 $2,950.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $286.000 $500.000 $250.000 $265.000 $310.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,015.000 $2,500.000 $1,650.810 $3,000.000 $2,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,600.000 $1,500.000 $1,239.470 $1,150.000 $2,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $5,000.000 $7,500.000 $8,736.000 $7,500.000 $10,000.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 7.000 $433.000 $800.000 $775.000 $1,000.000 $625.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $40.000 $50.000 $45.000 $50.000 $55.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 4.000 $84.000 $150.000 $125.000 $100.000 $90.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 1,200.000 $0.750 $2.000 $0.550 $2.110 $0.550
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 406.000 $0.750 $1.000 $1.000 $1.050 $1.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 112.000 $4.300 $2.000 $8.000 $2.110 $8.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 10,860.000 $0.550 $0.500 $0.650 $0.470 $0.650
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 57,920.000 $0.450 $0.500 $0.550 $0.470 $0.550
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 102.000 $1.600 $1.500 $0.900 $1.450 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,081.000 $1.600 $1.500 $0.900 $1.450 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 203.000 $1.100 $1.000 $1.000 $1.050 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 56.000 $11.050 $40.000 $7.400 $31.590 $7.400
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 58,100.000 $0.900 $0.800 $0.680 $0.760 $0.680
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 5,430.000 $1.000 $0.800 $0.750 $0.760 $0.750
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 28,960.000 $0.950 $0.800 $0.680 $0.760 $0.680
REFL PAV MRKR TY II-A-A
EA 657.000 $7.750 $5.000 $5.000 $5.250 $5.000
REFL PAV MRKR TY II-C-R
EA 13.000 $6.750 $15.000 $5.000 $12.500 $5.000
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 5,747.000 $135.000 $120.000 $142.000 $130.000 $122.000
SP MIXES SP-C SAC-B PG70-22
TON 11,505.000 $150.000 $110.000 $121.000 $119.000 $122.000
TACK COAT
GAL 10,452.000 $4.000 $3.500 $3.050 $0.010 $0.010
UNDERSEAL COURSE
GAL 26,135.000 $3.100 $4.000 $0.010 $0.010 $0.010
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,772.000 $7,500.000 $10,000.000 $15,000.000 $15,000.000
TMA (STATIONARY)
DAY 90.000 $150.000 $275.000 $261.000 $500.000 $0.010
TMA (MOBILE OPERATION)
HR 360.000 $70.000 $50.000 $20.000 $1.000 $0.010
Totals: $5,257,067.940 $4,557,803.140 $4,574,093.698 $4,579,854.865 $4,600,469.498