BORDEN FM 669 (0558-03-028)

Items: 46

County: BORDEN
Length: N/A
Highway: FM 669
District: ABILENE
Control Number: 0558-03-028
DBE Goal: N/A
Project: STP 2B23(132)HES
Guaranty: N/A
Time: 67 WORKING DAYS
Engineer's Estimate: $2,422,085.73
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: WIDEN ROAD - ADD SHOULDERS
Mail/Deliver Bids To: N/A
RYAN SAYLES
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$2,422,085.73
$3,149,253.90
Over/Under Est: 30.02% $727,168.17
$3,478,028.75
Over/Under Est: 43.6% $1,055,943.02
Amt Left: 10.44% $328,774.85
$3,566,066.60
Over/Under Est: 47.23% $1,143,980.87
Amt Left: 13.24% $416,812.70
Delta: -2.53% -$88,037.85

Bid Items & Bid Tabulations

46 Total 0 of 46
BORDEN  |  FM 669  |  ABILENE  |  0558-03-028  |  08/02/2023  |  $2,422,085.73  |  STP 2B23(132)HES  |  WIDEN ROAD - ADD SHOULDERS  |  67 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DUININCK, INC.
RK HALL, LLC
GILVIN-TERRILL, LTD.
REMOVING CONC (RIPRAP)
SY 24.000 $25.000 $26.000 $217.360 $50.000
EXCAVATION (CHANNEL)
CY 2,800.000 $15.000 $26.000 $12.520 $15.000
SUBGRADE WIDENING (DENS CONT)
STA 323.000 $450.000 $1,000.000 $990.220 $1,000.000
BACKFILL (TY B)
STA 323.000 $180.000 $98.000 $259.660 $400.000
ASPH (AC-20-5TR)
GAL 41,400.000 $6.000 $4.500 $5.550 $5.500
AGGR(TY-PB GR-3 SAC-B)
CY 1,095.000 $220.000 $150.000 $214.710 $160.000
RIPRAP (CONC)(5 IN)
CY 31.000 $400.000 $830.000 $625.210 $800.000
CMP (GAL STL 24 IN)
LF 9.000 $115.000 $105.000 $107.770 $100.000
CMP (GAL STL 30 IN)
LF 30.000 $172.000 $155.000 $131.120 $150.000
CMP (GAL STL 60 IN)
LF 27.000 $212.000 $415.000 $299.970 $400.000
CMP AR (GAL STL DES 4)
LF 70.000 $212.000 $260.000 $185.000 $250.000
CMP AR (GAL STL DES 5)
LF 46.000 $139.000 $390.000 $241.740 $375.000
CONC BOX CULV (7 FT X 4 FT)(EXTEND)
LF 39.000 $900.000 $1,400.000 $1,266.870 $1,350.000
SET (TY I)(S= 7 FT)(HW= 5 FT)(4:1) (C)
EA 10.000 $12,000.000 $15,500.000 $15,868.840 $15,000.000
SET (TY II) (24 IN) (CMP) (6: 1) (C)
EA 2.000 $1,900.000 $2,200.000 $2,716.460 $2,100.000
SET (TY II) (30 IN) (CMP) (6: 1) (C)
EA 4.000 $4,000.000 $3,100.000 $3,978.770 $3,000.000
SET (TY II) (48 IN) (CMP) (3: 1) (C)
EA 2.000 $4,000.000 $5,200.000 $6,623.420 $5,000.000
SET (TY II) (48 IN) (CMP) (4: 1) (C)
EA 2.000 $5,500.000 $5,400.000 $8,188.610 $5,200.000
SET (TY II) (DES 4) (CMP) (6: 1) (C)
EA 6.000 $4,000.000 $5,700.000 $6,047.250 $5,500.000
SET (TY II) (DES 5) (CMP) (6: 1) (C)
EA 14.000 $5,000.000 $6,000.000 $8,243.210 $5,750.000
CLEAN EXIST CULVERTS
EA 1.000 $2,800.000 $2,600.000 $3,400.960 $10,000.000
MOBILIZATION
LS 1.000 $255,406.000 $310,000.000 $344,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $10,000.000 $37,500.000 $26,544.150 $50,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 792.000 $7.000 $8.150 $10.330 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 792.000 $2.000 $2.350 $2.850 $2.000
RUMBLE STRIPS (SHOULDER)
LF 62,574.000 $0.130 $0.050 $0.230 $0.250
RUMBLE STRIPS (CENTERLINE)
LF 31,287.000 $0.130 $0.080 $0.390 $0.250
ALUMINUM SIGNS (TY A)
SF 64.000 $60.000 $29.000 $49.500 $35.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 32.000 $530.000 $675.000 $715.000 $650.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 15.000 $530.000 $625.000 $660.000 $600.000
REMOVE SM RD SN SUP&AM
EA 9.000 $90.000 $105.000 $110.000 $100.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 22.000 $79.000 $67.500 $71.500 $65.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,032.000 $2.000 $1.450 $5.700 $1.500
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 130,810.000 $1.000 $0.550 $0.580 $0.550
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 14,879.000 $1.000 $0.570 $0.610 $0.550
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 41,018.000 $1.000 $0.570 $0.610 $0.550
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 24.000 $15.000 $13.500 $14.300 $25.000
REFL PAV MRKR TY II-A-A
EA 761.000 $5.000 $4.650 $4.950 $4.500
ELIM EXT PAV MRK & MRKS (4")
LF 2,104.000 $0.700 $1.350 $1.430 $1.500
VEH SIG SEC (12")LED(YEL)
EA 8.000 $300.000 $840.000 $495.000 $810.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 4.000 $7,000.000 $12,500.000 $12,100.000 $12,125.000
D-GR HMA TY-B PG64-22
TON 7,112.000 $100.000 $160.500 $183.000 $190.000
TMA (STATIONARY)
DAY 67.000 $300.000 $210.000 $443.380 $500.000
TMA (MOBILE OPERATION)
DAY 5.000 $700.000 $935.000 $940.910 $950.000
LEAD LED CHEVRON
EA 4.000 $4,000.000 $3,350.000 $3,520.000 $3,200.000
LED CHEVRON
EA 24.000 $1,200.000 $3,000.000 $1,980.000 $1,800.000
Totals: $2,422,085.730 $3,149,253.900 $3,478,028.750 $3,566,066.600