Show Job Controls
Bid Cobra

BLANCO US0281 (6365-20-001)

Items: 9

County: BLANCO
Length: N/A
Highway: US0281
District: AUSTIN
Control Number: 6365-20-001
DBE Goal: N/A
Project: MMC - 636520001
Guaranty: N/A
Time: 120 CALENDAR DAYS
Engineer's Estimate: $1,277,133.00
Date: 09/03/2020 (5 years ago)
Contract Number: N/A
Type: MATERIAL ONLY (HOT MIX CL ASPHALT CONCRETE PVMT)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,277,133.00
$742,075.00
Over/Under Est: -41.9% -$535,058.00
Over/Under Est: -37.28% -$476,159.00
Amt Left: 7.94% $58,899.00
Over/Under Est: -28.69% -$366,408.00
Amt Left: 22.73% $168,650.00
Delta: -13.70% -$109,751.00
Over/Under Est: -27.09% -$345,933.00
Amt Left: 25.49% $189,125.00
Delta: -2.25% -$20,475.00
Over/Under Est: -22.09% -$282,133.00
Amt Left: 34.08% $252,925.00
Delta: -6.85% -$63,800.00
Over/Under Est: -21.04% -$268,761.00
Amt Left: 35.89% $266,297.00
Delta: -1.34% -$13,372.00
$1,127,850.00
Over/Under Est: -11.69% -$149,283.00
Amt Left: 51.99% $385,775.00
Delta: -11.85% -$119,478.00

Bid Items & Bid Tabulations

9 Total 0 of 9
BLANCO  |  US0281  |  AUSTIN  |  6365-20-001  |  09/03/2020  |  $1,277,133.00  |  MMC - 636520001  |  MATERIAL ONLY (HOT MIX CL ASPH CONC...  |  120 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
LONE STAR PAVING COMPANY
AUSTIN MATERIALS, LLC
CENTURY ASPHALT, LTD.
BRAUNTEX MATERIALS, INC.
COLORADO MATERIALS, LTD.
ALLEN KELLER COMPANY
HMCL ACP TYPE B (DELIVERY)(SITE 1)
TON 1,000.000 $89.310 $53.600 $56.900 $61.500 $68.000 $67.000 $63.720 $75.220
HMCL ACP TYPE D (DELIVERY)(SITE 1)
TON 2,000.000 $89.310 $49.250 $53.050 $60.000 $63.500 $65.000 $64.070 $79.500
HMCL ACP TYPE D (DELIVERY)(SITE 2)
TON 2,000.000 $89.310 $48.000 $53.600 $62.000 $59.500 $70.000 $71.690 $84.300
HMCL ACP TYPE D (DELIVERY)(SITE 3)
TON 2,000.000 $89.310 $53.600 $56.900 $61.500 $68.000 $67.000 $67.620 $75.220
HMCL ACP TYPE D (DELIVERY)(SITE 4)
TON 3,000.000 $89.310 $50.250 $53.880 $66.000 $63.500 $71.000 $73.700 $78.990
HMCL ACP TYPE D (DELIVERY)(SITE 5)
TON 3,000.000 $89.310 $55.750 $61.300 $69.000 $68.500 $75.000 $78.840 $74.520
HMCL ACP TYPE D (DELIVERY)(SITE 6)
TON 250.000 $89.310 $52.750 $56.900 $60.000 $63.500 $68.000 $64.070 $89.880
HMCL ACP TYPE D (DELIVERY)(SITE 7)
TON 250.000 $89.310 $52.750 $56.900 $58.500 $64.500 $68.000 $65.370 $89.880
HMCL ACP TYPE D (DELIVERY)(SITE 8)
TON 800.000 $89.310 $53.000 $53.730 $59.500 $66.500 $65.000 $59.890 $86.400
Totals: $1,277,133.000 $742,075.000 $800,974.000 $910,725.000 $931,200.000 $995,000.000 $1,008,372.000 $1,127,850.000