Bid Cobra

BLANCO US 281 (0253-02-033)

Items: 59

County: BLANCO
Length: N/A
Highway: US 281
District: AUSTIN
Control Number: 0253-02-033
DBE Goal: N/A
Project: BR 2B23(128)
Guaranty: N/A
Time: 88 WORKING DAYS
Engineer's Estimate: $939,269.00
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$939,269.00
$1,151,580.50
Over/Under Est: 22.6% $212,311.50
Over/Under Est: 22.66% $212,848.35
Amt Left: 0.05% $536.85
$1,186,292.36
Over/Under Est: 26.3% $247,023.36
Amt Left: 3.01% $34,711.86
Delta: -2.97% -$34,175.01
$1,423,414.00
Over/Under Est: 51.54% $484,145.00
Amt Left: 23.61% $271,833.50
Delta: -19.99% -$237,121.64
Subcontractor Percentage Amount
A K FUQUAY CONSTRUCTION 0.00% $0.00
EGGEMEYER LAND CLEARING, LLC 0.00% $0.00
D. I. J. CONSTRUCTION, INC. 0.00% $0.00
MPB, INC. 0.00% $0.00
LONE STAR EROSION CONTROL 0.00% $0.00
KELLER TRUCKING, INC. 0.00% $0.00
AWP SAFETY 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

59 Total 0 of 59
BLANCO  |  US 281  |  AUSTIN  |  0253-02-033  |  08/03/2023  |  $939,269.00  |  BR 2B23(128)  |  BRIDGE MAINT  |  88 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLEN KELLER COMPANY
SCR CIVIL CONSTRUCTION, LLC
CEKRA INC.
ICOS MANAGEMENT, LLC
PREPARING ROW
STA 3.000 $10,000.000 $35,000.000 $15,000.000 $8,500.000 $10,000.000
REMOVING CONC (RIPRAP)
SY 50.000 $50.000 $80.000 $220.000 $400.000 $300.000
FURNISHING AND PLACING TOPSOIL (4")
SY 793.000 $5.000 $10.000 $6.000 $25.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 100.000 $8.000 $5.500 $5.750 $5.000 $10.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 233.000 $9.000 $5.500 $5.750 $5.000 $15.000
SOIL RETENTION BLANKETS (CL 2) (TY G)
SY 460.000 $5.500 $7.250 $7.450 $5.000 $25.000
FLEX PAVEMENT STRUCTURE REPAIR (8"-15")
SY 4.000 $200.000 $1,900.000 $3,370.000 $2,500.000 $1,200.000
FLOWABLE BACKFILL
CY 2.000 $550.000 $1,000.000 $4,410.000 $10,000.000 $2,500.000
CL C CONC (RAIL FOUNDATION)
CY 4.100 $1,100.000 $3,600.000 $13,177.000 $10,000.000 $4,500.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 55.000 $20.000 $100.000 $395.000 $30.000 $120.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 44.000 $283.000 $370.000 $540.000 $1,000.000 $300.000
RIPRAP (CONC) (CL A )
CY 9.000 $800.000 $1,200.000 $1,800.000 $1,000.000 $800.000
RIPRAP (CONC)(CL C)
CY 2.000 $1,000.000 $2,200.000 $2,000.000 $4,000.000 $2,400.000
RIPRAP (STONE PROTECTION)(21 IN)
CY 261.000 $250.000 $290.000 $175.000 $300.000 $260.000
RIPRAP (MOW STRIP)(4 IN)
CY 50.000 $800.000 $900.000 $1,000.000 $450.000 $860.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 184.000 $65.000 $60.000 $96.000 $65.000 $120.000
RETROFIT RAIL (TY T222)
LF 524.700 $250.000 $310.000 $425.000 $400.000 $410.000
MOBILIZATION
LS 1.000 $77,000.000 $100,000.000 $115,000.000 $110,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $8,000.000 $6,000.000 $7,149.368 $8,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 200.000 $5.000 $5.500 $5.750 $2.321 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 200.000 $1.800 $1.000 $3.000 $0.633 $2.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 200.000 $9.000 $7.750 $8.000 $3.501 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $3.500 $1.000 $3.000 $0.856 $4.000
PTB(FRN&INSTL)(SSCB OR CSB)(TY1)OR(STL)
LF 120.000 $75.000 $100.000 $150.000 $240.000 $170.000
PTB(MOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 60.000 $15.000 $50.000 $130.000 $125.000 $170.000
PTB(REMOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 120.000 $32.000 $70.000 $130.000 $125.000 $170.000
PORT CTB (FURN & INST)(TL-3 LPCB)
LF 270.000 $60.000 $200.000 $230.000 $240.000 $150.000
PORT CTB (MOVE) (TL-3 LPCB)
LF 270.000 $16.000 $50.000 $35.000 $125.000 $150.000
PORT CTB (REMOVE) (TL-3 LPCB)
LF 270.000 $32.000 $50.000 $50.000 $125.000 $150.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,100.000 $40.000 $33.000 $38.000 $40.000 $42.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,700.000 $3,700.000 $2,000.000 $2,500.000 $4,500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,900.000 $2,400.000 $2,200.000 $2,500.000 $5,200.000
TL-3 31" SHORT RADIUS (COMPLETE)
EA 2.000 $22,000.000 $20,000.000 $22,000.000 $20,000.000 $25,000.000
REMOVE METAL BEAM GUARD FENCE
LF 350.000 $5.000 $5.500 $10.000 $5.000 $30.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $350.000 $400.000 $400.000 $350.000 $1,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $4,000.000 $4,000.000 $4,100.000 $3,500.000 $5,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $400.000 $400.000 $400.000 $243.581 $2,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $3,400.000 $1,700.000 $1,800.000 $15,000.000 $4,500.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $2,400.000 $1,000.000 $600.000 $1,500.000 $3,500.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 2.000 $35,000.000 $40,000.000 $25,000.000 $34,000.000 $32,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $15,000.000 $10,000.000 $9,945.000 $7,000.000 $24,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $800.000 $900.000 $745.000 $680.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $1,050.000 $1,100.000 $831.000 $765.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,300.000 $1,100.000 $890.000 $815.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 11.000 $50.000 $40.000 $45.000 $77.000 $150.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 7,240.000 $2.000 $1.250 $1.100 $1.050 $2.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 9,414.000 $2.500 $1.250 $1.100 $1.050 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 132.000 $3.500 $9.500 $6.000 $1.050 $12.000
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 1,380.000 $1.000 $3.250 $1.100 $1.050 $7.000
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 330.000 $1.100 $3.250 $1.100 $1.050 $10.000
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 1,300.000 $0.900 $3.250 $1.100 $1.050 $12.000
REFL PAV MRKR TY II-A-A
EA 104.000 $10.000 $4.500 $7.750 $6.750 $75.000
ELIM EXT PAV MRK & MRKS (4")
LF 3,010.000 $4.000 $2.000 $0.900 $0.800 $5.000
CRACK CLEANING AND SEALING (JCP)
LF 100.000 $29.000 $10.000 $25.000 $45.000 $85.000
INSTALL FTB
LF 350.000 $59.000 $275.000 $50.000 $25.000 $75.000
REMOVE FTB
LF 350.000 $29.000 $9.000 $15.000 $10.000 $25.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $300.000 $100.000 $150.000 $150.000 $50.000
TMA (STATIONARY)
DAY 117.000 $500.000 $200.000 $400.000 $192.000 $500.000
TMA (MOBILE OPERATION)
DAY 2.000 $900.000 $2,800.000 $2,000.000 $1,000.000 $1,200.000
Totals: $939,269.000 $1,151,580.500 $1,152,117.350 $1,186,292.370 $1,423,414.000