BEXAR IH0035 (6483-03-001)
Items: 23
County: BEXAR
Length: 0.0100 MILES
Highway: IH0035
District: SAN ANTONIO
Control Number: 6483-03-001
DBE Goal: N/A
Project: BPM - A00214916
Guaranty: $33,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,640,752.00
Date: 07/01/2025 (11 months ago)
Contract Number: 7254004
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00214916
Project Description: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
HENRY FOJTIK
BEXAR IH0035 (6483-03-001)
Project Name: N/A
Project: BPM - A00214916
Length: 0.0100 MILES
Project Type: MAINTENANCE
Limits From: VARIOUS LOCATIONS
Limits To: IN BEXAR COUNTY
Project Description: BRIDGE PREVENTATIVE MAINTENANCE
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,640,752.00 | |||
| $1,143,629.00 |
-30.3%
-$497,123.00
|
|||
| $1,540,980.00 |
-6.08%
-$99,772.00
|
34.74%
$397,351.00
|
||
| $1,562,950.00 |
-4.74%
-$77,802.00
|
36.67%
$419,321.00
|
-1.43%
-$21,970.00
|
|
| $1,567,450.00 |
-4.47%
-$73,302.00
|
37.06%
$423,821.00
|
-0.29%
-$4,500.00
|
|
| $1,609,055.00 |
-1.93%
-$31,697.00
|
40.7%
$465,426.00
|
-2.65%
-$41,605.00
|
E
Engineer's Estimate
$1,640,752.00
1
Awarded
$1,143,629.00
Over/Under Est:
-30.3%
-$497,123.00
$1,540,980.00
Over/Under Est:
-6.08%
-$99,772.00
Amt Left:
34.74%
$397,351.00
$1,562,950.00
Over/Under Est:
-4.74%
-$77,802.00
Amt Left:
36.67%
$419,321.00
Delta:
-1.43%
-$21,970.00
$1,567,450.00
Over/Under Est:
-4.47%
-$73,302.00
Amt Left:
37.06%
$423,821.00
Delta:
-0.29%
-$4,500.00
$1,609,055.00
Over/Under Est:
-1.93%
-$31,697.00
Amt Left:
40.7%
$465,426.00
Delta:
-2.65%
-$41,605.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| SKIDABRADER GROUP LLC | 0.00% | $0.00 |
| Total: | 0.00% | $0.00 |
Bid Items & Bid Tabulations
23
Total
0 of 23