BEXAR SL1604 (6382-82-001)

Items: 15

County: BEXAR
Length: N/A
Highway: SL1604
District: SAN ANTONIO
Control Number: 6382-82-001
DBE Goal: N/A
Project: BPM - 638282001
Guaranty: N/A
Time: 32 W
Engineer's Estimate: $155,541.34
Date: 01/25/2022 (4 years ago)
Contract Number: N/A
Type: EROSION REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (7)
E
Engineer's Estimate
$155,541.34
$156,331.02
Over/Under Est: 0.51% $789.68
Over/Under Est: 4.49% $6,984.16
Amt Left: 3.96% $6,194.48
Over/Under Est: 5.87% $9,127.30
Amt Left: 5.33% $8,337.62
Delta: -1.32% -$2,143.14
Over/Under Est: 19.13% $29,756.41
Amt Left: 18.53% $28,966.73
Delta: -12.53% -$20,629.11
Over/Under Est: 43.33% $67,388.66
Amt Left: 42.6% $66,598.98
Delta: -20.31% -$37,632.25
Over/Under Est: 91.64% $142,535.66
Amt Left: 90.67% $141,745.98
Delta: -33.71% -$75,147.00
Over/Under Est: 95.73% $148,894.66
Amt Left: 94.74% $148,104.98
Delta: -2.13% -$6,359.00

Bid Items & Bid Tabulations

15 Total 0 of 15
BEXAR  |  SL1604  |  SAN ANTONIO  |  6382-82-001  |  01/25/2022  |  $155,541.34  |  BPM - 638282001  |  EROSION REPAIR  |  32 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
CROSS PLUS CONSTRUCTION, LLC
BECK-REIT & SONS, LTD.
DOUBLE L CONTRACTING, LLC
DAN WILLIAMS COMPANY
TALBRAN ENTERPRISES LLC
PATHFIELD INVESTMENTS LLC
FNH CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 94.000 $32.940 $52.250 $15.000 $50.000 $20.000 $40.000 $65.000 $100.000
EXCAVATION (CHANNEL)
CY 252.000 $30.000 $35.200 $35.000 $26.000 $25.000 $40.000 $50.000 $50.000
COMPOST MANUF TOPSOIL (4")
SY 2,543.000 $4.270 $3.470 $1.000 $6.800 $2.750 $4.000 $5.000 $10.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 2,543.000 $1.100 $0.660 $0.500 $0.460 $0.500 $1.000 $1.000 $2.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 2,543.000 $0.780 $1.210 $1.000 $2.860 $2.000 $5.000 $3.000 $10.000
RIPRAP (CONC)(4 IN)
CY 11.000 $383.060 $308.000 $600.000 $690.000 $850.000 $500.000 $900.000 $850.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 261.000 $110.790 $121.000 $199.000 $98.000 $215.000 $300.000 $600.000 $150.000
GABION MATTRESSES (GALV)(12 IN)
SY 756.000 $82.480 $93.500 $77.000 $100.630 $87.000 $90.000 $75.000 $160.000
MOBILIZATION
LS 1.000 $15,000.000 $12,100.000 $20,222.000 $10,000.000 $15,000.000 $15,000.000 $20,000.000 $30,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $4,500.000 $1,028.500 $2,500.000 $500.000 $5,500.000 $5,000.000 $3,000.000 $8,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $49.750 $23.100 $20.000 $18.500 $30.000 $25.000 $30.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $23.750 $4.400 $10.000 $14.000 $10.000 $15.000 $10.000 $15.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 120.000 $4.770 $49.500 $4.000 $6.210 $8.000 $5.000 $10.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 120.000 $1.720 $1.100 $1.000 $4.600 $2.000 $2.000 $5.000 $9.000
TMA (STATIONARY)
DAY 5.000 $150.000 $1.100 $1.000 $500.000 $170.000 $300.000 $200.000 $350.000
Totals: $155,541.340 $156,331.020 $162,525.500 $164,668.640 $185,297.750 $222,930.000 $298,077.000 $304,436.000