BEXAR US0090 (6382-80-001)

Items: 14

County: BEXAR
Length: N/A
Highway: US0090
District: SAN ANTONIO
Control Number: 6382-80-001
DBE Goal: N/A
Project: BPM - 638280001
Guaranty: N/A
Time: 16 W
Engineer's Estimate: $53,143.49
Date: 03/29/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE SCOUR REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (5)
E
Engineer's Estimate
$53,143.49
Over/Under Est: 41.31% $21,951.51
Over/Under Est: 62.88% $33,416.51
Amt Left: 15.27% $11,465.00
Over/Under Est: 72.49% $38,523.51
Amt Left: 22.07% $16,572.00
Delta: -5.90% -$5,107.00
Over/Under Est: 85.11% $45,232.51
Amt Left: 31% $23,281.00
Delta: -7.32% -$6,709.00
Over/Under Est: 149.01% $79,186.51
Amt Left: 76.22% $57,235.00
Delta: -34.51% -$33,954.00

Bid Items & Bid Tabulations

14 Total 0 of 14
BEXAR  |  US0090  |  SAN ANTONIO  |  6382-80-001  |  03/29/2022  |  $53,143.49  |  BPM - 638280001  |  BRIDGE SCOUR REPAIR  |  16 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
TALBRAN ENTERPRISES LLC
DAN WILLIAMS COMPANY
DOUBLE L CONTRACTING, LLC
FNH CONSTRUCTION, LLC
COMPOST MANUF TOPSOIL (4")
SY 250.000 $4.400 $10.000 $15.000 $9.000 $10.000 $20.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 250.000 $0.670 $1.000 $5.000 $1.500 $1.000 $10.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 250.000 $2.560 $2.000 $5.000 $5.000 $6.000 $10.000
CL A CONC (MISC)
CY 35.000 $380.000 $650.000 $580.000 $680.000 $850.000 $1,500.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 37.000 $173.500 $150.000 $300.000 $260.000 $250.000 $165.000
GABIONS (3' X 3')(GALV)
CY 70.000 $178.000 $300.000 $290.000 $285.000 $300.000 $325.000
CLEAN EXIST CULVERTS
EA 5.000 $730.740 $750.000 $2,500.000 $3,000.000 $4,500.000 $1,500.000
MOBILIZATION
LS 1.000 $6,000.000 $7,500.000 $7,000.000 $9,000.000 $7,500.000 $12,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $800.000 $2,000.000 $200.000 $4,500.000 $500.000 $8,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $24.120 $25.000 $20.000 $21.000 $20.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $19.800 $10.000 $10.000 $5.000 $10.000 $20.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 125.000 $5.280 $10.000 $4.000 $8.000 $1.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 125.000 $1.790 $1.000 $2.000 $2.000 $1.000 $9.000
TMA (STATIONARY)
DAY 16.000 $175.000 $250.000 $300.000 $110.000 $1.000 $250.000
Totals: $53,143.490 $75,095.000 $86,560.000 $91,667.000 $98,376.000 $132,330.000