BEXAR SL0353 (6332-51-001)

Items: 46

County: BEXAR
Length: N/A
Highway: SL0353
District: SAN ANTONIO
Control Number: 6332-51-001
DBE Goal: N/A
Project: BPM - 633251001
Guaranty: N/A
Time: 32 W
Engineer's Estimate: $592,591.10
Date: 06/04/2019 (7 years ago)
Contract Number: N/A
Type: RIPRAP REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$592,591.10
$549,622.60
Over/Under Est: -7.25% -$42,968.50
$577,746.46
Over/Under Est: -2.51% -$14,844.64
Amt Left: 5.12% $28,123.86
Over/Under Est: 11.01% $65,234.10
Amt Left: 19.69% $108,202.60
Delta: -13.86% -$80,078.74
Over/Under Est: 42.92% $254,363.40
Amt Left: 54.1% $297,331.90
Delta: -28.75% -$189,129.30

Bid Items & Bid Tabulations

46 Total 0 of 46
BEXAR  |  SL0353  |  SAN ANTONIO  |  6332-51-001  |  06/04/2019  |  $592,591.10  |  BPM - 633251001  |  RIPRAP REPAIR  |  32 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
CURRAN CONTRACTING COMPANY
RELMCO, INC.
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
FNH CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 178.000 $15.000 $142.150 $25.000 $90.000 $20.000
COMPOST MANUF TOPSOIL (4")
SY 610.000 $0.710 $6.950 $5.000 $5.300 $20.000
BROADCAST SEED (PERM) (URBAN) (CLAY)
SY 610.000 $3.000 $0.250 $2.000 $0.650 $2.000
VEGETATIVE WATERING
MG 10.000 $15.000 $19.600 $40.000 $100.000 $100.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 610.000 $2.000 $2.150 $3.000 $1.600 $6.500
AGGR (TY-PB GR-4)
CY 12.000 $98.000 $380.000 $185.000 $270.000 $350.000
ASPH (AC-15P OR CRS-2P)
GAL 393.000 $4.000 $8.100 $8.000 $12.000 $20.000
D-GR HMA(SQ) TY-D SAC-B PG70-22
TON 102.000 $90.000 $153.800 $125.000 $225.000 $200.000
PLANE ASPH CONC PAV (1.5" TO 4")
SY 1,245.000 $6.500 $4.000 $8.000 $15.000 $20.000
RIPRAP (MOW STRIP)(4 IN)
CY 24.000 $575.000 $570.000 $395.000 $450.000 $550.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 243.000 $36.000 $47.650 $60.000 $60.000 $50.000
RAIL (TY T1W)
LF 180.000 $250.000 $354.600 $225.000 $250.000 $185.000
GABIONS (GALV)
CY 469.000 $280.000 $288.750 $300.000 $305.000 $320.000
GABION MATTRESSES (GALV)(12 IN)
SY 1,160.000 $100.000 $71.500 $85.000 $90.000 $145.000
MOBILIZATION
LS 1.000 $45,000.000 $50,500.000 $50,000.000 $69,000.000 $85,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $10,000.000 $5,940.660 $7,500.000 $18,000.000 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 280.000 $7.000 $8.300 $15.000 $5.500 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 280.000 $2.000 $2.450 $10.000 $1.000 $9.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 32.000 $175.000 $87.500 $100.000 $180.000 $550.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 630.000 $80.000 $33.000 $35.000 $50.000 $70.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 390.000 $20.000 $4.550 $10.000 $8.000 $20.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 180.000 $25.000 $30.100 $18.000 $35.000 $20.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 390.000 $18.000 $30.000 $20.000 $35.000 $20.000
MTL W-BEAM GD FEN (TIM POST)
LF 412.500 $25.000 $23.450 $25.000 $19.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,900.000 $1,576.750 $2,000.000 $1,750.000 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,200.000 $1,108.000 $1,500.000 $930.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 225.000 $3.000 $3.200 $3.000 $1.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $225.000 $133.150 $250.000 $100.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,800.000 $3,015.000 $2,800.000 $2,300.000 $2,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $275.000 $159.800 $250.000 $100.000 $1,500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,650.000 $1,120.900 $800.000 $500.000 $5,000.000
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $1,050.000 $1,114.100 $650.000 $100.000 $2,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $12,000.000 $6,250.000 $7,500.000 $7,900.000 $12,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $25.000 $13.850 $30.000 $12.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 16.000 $30.000 $17.840 $30.000 $15.000 $100.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 2,764.000 $1.500 $1.350 $1.320 $1.650 $4.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 2,764.000 $1.500 $1.350 $1.320 $1.650 $4.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 760.000 $0.500 $0.550 $0.550 $1.000 $4.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 760.000 $0.500 $0.550 $0.550 $1.000 $4.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 760.000 $0.750 $1.600 $1.100 $3.900 $4.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 760.000 $0.500 $1.600 $1.100 $3.900 $4.000
TRAFFIC BUTTON TY II-A-A
EA 10.000 $5.000 $5.350 $22.000 $100.000 $10.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 0.500 $1,800.000 $3,196.150 $35,000.000 $30,000.000 $30,000.000
TMA (STATIONARY)
DAY 10.000 $240.000 $131.880 $300.000 $215.000 $550.000
TMA (MOBILE OPERATION)
DAY 4.000 $260.000 $240.000 $300.000 $465.000 $850.000
REML & DISPL DRIFTWOOD & DEBRIS
LS 1.000 $10,000.000 $2,130.500 $27,500.000 $11,000.000 $35,000.000
Totals: $592,591.100 $549,622.610 $577,746.460 $657,825.200 $846,954.500