Show Job Controls
Bid Cobra

BEXAR FM 2696 (2708-01-033)

Items: 11

County: BEXAR
Length: N/A
Highway: FM 2696
District: SAN ANTONIO
Control Number: 2708-01-033
DBE Goal: 0.0%
Project: STP 2024(534)HES
Guaranty: N/A
Time: 89 WORKING DAYS
Engineer's Estimate: $1,023,899.69
Date: 01/04/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ORLANDO GALLEGOS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,023,899.69
$778,577.00
Over/Under Est: -23.96% -$245,322.69
Over/Under Est: -3.13% -$32,010.89
Amt Left: 27.4% $213,311.80
$1,107,870.74
Over/Under Est: 8.2% $83,971.05
Amt Left: 42.29% $329,293.74
Delta: -11.69% -$115,981.94
Over/Under Est: 15.99% $163,713.29
Amt Left: 52.54% $409,035.98
Delta: -7.20% -$79,742.24
Subcontractor Percentage Amount
FIBERTEL, LLC 2.75% $24,486.68
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. 0.67% $5,965.84
LLANO AUGER SERVICE 0.36% $3,205.53
LOZANO CONSTRUCTION COMPANY, INC. 0.06% $534.25
ALAMO CRANE SERVICE, INC. 0.01% $89.04
Total: 3.85% $34,281.34

Bid Items & Bid Tabulations

11 Total 0 of 11
BEXAR  |  FM 2696  |  SAN ANTONIO  |  2708-01-033  |  01/04/2024  |  $1,023,899.69  |  STP 2024(534)HES  |  HAZARD ELIM & SAFETY  |  89 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
E-Z BEL CONSTRUCTION, LLC
ELECNOR BELCO ELECTRIC, INC.
THE LEVY COMPANY, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 570.000 $223.940 $210.000 $320.000 $334.520 $601.680
MOBILIZATION
LS 1.000 $30,000.000 $40,000.000 $32,101.000 $110,787.070 $68,249.390
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,530.880 $1,400.000 $3,400.000 $13,453.040 $4,747.430
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 57.000 $4,480.030 $4,900.000 $5,520.000 $5,420.320 $5,822.210
CONDT (PVC) (SCH 40) (2")
LF 13,496.000 $27.150 $12.000 $18.000 $14.480 $17.180
CONDT (PVC) (SCH 40) (2") (BORE)
LF 1,343.000 $32.210 $25.000 $34.000 $67.520 $31.480
ELEC CONDR (NO.8) BARE
LF 14,839.000 $1.450 $1.400 $1.800 $1.230 $1.220
ELEC CONDR (NO.8) INSULATED
LF 30,072.000 $1.700 $1.450 $1.800 $1.260 $1.450
GROUND BOX TY A (122311)W/APRON
EA 20.000 $1,000.000 $1,100.000 $1,485.000 $1,380.290 $1,273.180
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 4.000 $8,010.880 $7,000.000 $7,200.000 $9,047.100 $7,539.450
TMA (STATIONARY)
DAY 89.000 $150.000 $239.000 $162.000 $120.140 $276.260
Totals: $1,023,899.690 $778,577.000 $991,888.800 $1,107,870.740 $1,187,612.980