BEXAR VARIOUS (0915-00-285)
Items: 11
County: BEXAR
Length: 0.0010 MILES
Highway: VARIOUS
District: SAN ANTONIO
Control Number: 0915-00-285
DBE Goal: 0.0%
Project: F 2026(705)
Guaranty: $100,000.00
Time: 89 WORKING DAYS
Engineer's Estimate: $3,134,329.90
Date: 06/02/2026 (8 days ago)
Contract Number: 6263009
Type: PREVENTIVE MAINTENANCE
Project ID: A00196424
Contract Type: Federal
Project Description: FINAL THERMOPLASTIC STRIPING FOR FY 2026 SC PROGRAM
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BEXAR VARIOUS (0915-00-285)
Project Name: N/A
Project: F 2026(705)
Length: 0.0010 MILES
Project Type: CONSTRUCTION
Limits From: VARIOUS LOCATIONS DISTRICTWIDE
Limits To: .
Project Description: FINAL THERMOPLASTIC STRIPING FOR FY 2026 SC PROGRAM
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,134,329.90 | |||
| $2,418,379.60 |
-22.84%
-$715,950.30
|
|||
| $2,668,183.40 |
-14.87%
-$466,146.50
|
10.33%
$249,803.80
|
||
| $2,672,683.72 |
-14.73%
-$461,646.18
|
10.52%
$254,304.12
|
-0.17%
-$4,500.32
|
|
| $2,915,942.60 |
-6.97%
-$218,387.30
|
20.57%
$497,563.00
|
-9.10%
-$243,258.88
|
|
| $2,918,916.06 |
-6.87%
-$215,413.84
|
20.7%
$500,536.46
|
-0.10%
-$2,973.46
|
|
| $3,064,506.59 |
-2.23%
-$69,823.31
|
26.72%
$646,126.99
|
-4.99%
-$145,590.53
|
|
| $3,254,544.45 |
3.84%
$120,214.55
|
34.58%
$836,164.85
|
-6.20%
-$190,037.86
|
|
| $3,258,238.71 |
3.95%
$123,908.81
|
34.73%
$839,859.11
|
-0.11%
-$3,694.26
|
|
| $3,479,706.47 |
11.02%
$345,376.57
|
43.89%
$1,061,326.87
|
-6.80%
-$221,467.76
|
E
Engineer's Estimate
$3,134,329.90
$2,418,379.60
Over/Under Est:
-22.84%
-$715,950.30
$2,668,183.40
Over/Under Est:
-14.87%
-$466,146.50
Amt Left:
10.33%
$249,803.80
$2,672,683.72
Over/Under Est:
-14.73%
-$461,646.18
Amt Left:
10.52%
$254,304.12
Delta:
-0.17%
-$4,500.32
$2,915,942.60
Over/Under Est:
-6.97%
-$218,387.30
Amt Left:
20.57%
$497,563.00
Delta:
-9.10%
-$243,258.88
$2,918,916.06
Over/Under Est:
-6.87%
-$215,413.84
Amt Left:
20.7%
$500,536.46
Delta:
-0.10%
-$2,973.46
$3,064,506.59
Over/Under Est:
-2.23%
-$69,823.31
Amt Left:
26.72%
$646,126.99
Delta:
-4.99%
-$145,590.53
$3,254,544.45
Over/Under Est:
3.84%
$120,214.55
Amt Left:
34.58%
$836,164.85
Delta:
-6.20%
-$190,037.86
$3,258,238.71
Over/Under Est:
3.95%
$123,908.81
Amt Left:
34.73%
$839,859.11
Delta:
-0.11%
-$3,694.26
$3,479,706.47
Over/Under Est:
11.02%
$345,376.57
Amt Left:
43.89%
$1,061,326.87
Delta:
-6.80%
-$221,467.76
Bid Items & Bid Tabulations
11
Total
0 of 11
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $15,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $17,000.00 |